Cliff Residences
Deedo IDDP-PUN-WPNGIt is due for completion in Jan 2028, with no extension on record; MahaRERA lists it: deregistered; 0% of its units are booked.
Bhugaon, Pune 412115 · Promoter: Paranjape Schemes (Construction) Ltd
It is due for completion in Jan 2028, with no extension on record
- This projectRegistered 30 Jan 2023, completion promised 1 Jan 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
12 buildings
Open a building to see every flat, floor by floor.
- Unit 12 floors · 1 unit0% booked
- Unit 102 floors · 1 unit0% booked
- Unit 112 floors · 1 unit0% booked
- Unit 122 floors · 1 unit0% booked
- Unit 22 floors · 1 unit0% booked
- Unit 32 floors · 1 unit0% booked
- Unit 42 floors · 1 unit0% booked
- Unit 52 floors · 1 unit0% booked
- Unit 62 floors · 1 unit0% booked
- Unit 72 floors · 1 unit0% booked
- Unit 82 floors · 1 unit0% booked
- Unit 92 floors · 1 unit0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory record1
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- DeregisteredMatched by RERA number
Deregistered: CLIFF RESIDENCES
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100049098
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100049098 | 30 Jan 2023 | 1 Jan 2028 | 1 Jan 2028 | Paranjape Schemes (Construction) Ltd | Project page |
Documents63
1 document held by Deedo, 62 filings listed on MahaRERA's project page
Finance
- PAN CardPSCL-PAN.pdf · uploaded 23 Dec 2022Source
Legal
- Declaration Form B10 3FORM B-Promoter -Cliff Resi part I.pdf · uploaded 13 Jan 2023Source
- Declaration Form B10 4 FORM b-Promoter Cliff resi-part II.pdf · uploaded 13 Jan 2023Source
- Declaration Form B10 5-FORM B-Promoter-Cliff Resi- Part III.pdf · uploaded 13 Jan 2023Source
- Declaration Form B10 6-FORM B-Promoter-Cliff Resi- Part IV.pdf · uploaded 13 Jan 2023Source
- Declaration Form B10 7-FORM B-promoter-Cliff Resi-Part V.pdf · uploaded 13 Jan 2023Source
- Legal Title reportTitle - PSCL.pdf · uploaded 19 Jan 2023Source
Show all 63 documentsShow fewer documents
Migrated
- 1 PAN CardPSCL-PAN.pdf · uploaded 23 Dec 2022Source
- 1 a Details of encumbrances concerned to FinanceDetails of Encumbrances Signed.pdf · uploaded 7 Jan 2023Source
- 2 a Details of encumbrances concerned to FinanceEncumbrance related to Legal.pdf · uploaded 7 Jan 2023Source
- 1 b Details of encumbrances concerned to LegalDetails of Encumbrances Signed.pdf · uploaded 7 Jan 2023Source
- 2 b Details of encumbrances concerned to LegalEncumbrance related to Legal.pdf · uploaded 7 Jan 2023Source
- 1 Copy of Layout Approval (in case of layout)scan sheet 1_compressed.pdf · uploaded 7 Jan 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentscan sheet 2_compressed.pdf · uploaded 7 Jan 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentscan sheet 3_compressed.pdf · uploaded 7 Jan 2023Source
- 3 Building Plan Approval / NA Order for plotted developmentscan sheet 4_compressed.pdf · uploaded 7 Jan 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_compressed.pdf · uploaded 7 Jan 2023Source
- 1 Declaration about Commencement CertificateFormat D R32 Cliff Resi.pdf · uploaded 7 Jan 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3-C A Certificate-R32 Cliff Resi.pdf · uploaded 7 Jan 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT A- Bank Account Disclosure.pdf · uploaded 7 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation Report_ Allotment Letter.pdf · uploaded 7 Jan 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report _Agreement for Sale.pdf · uploaded 7 Jan 2023Source
- 1 Disclosure of Interest in Other Real Estate Organizationsorganized (53).pdf · uploaded 12 Jan 2023Source
- 1 Proforma of Allotment letterFinal AL 120123.pdf · uploaded 12 Jan 2023Source
- 1 Declaration in FORM B10 3FORM B-Promoter -Cliff Resi part I.pdf · uploaded 13 Jan 2023Source
- 2 Declaration in FORM B10 4 FORM b-Promoter Cliff resi-part II.pdf · uploaded 13 Jan 2023Source
- 3 Declaration in FORM B10 5-FORM B-Promoter-Cliff Resi- Part III.pdf · uploaded 13 Jan 2023Source
- 4 Declaration in FORM B10 6-FORM B-Promoter-Cliff Resi- Part IV.pdf · uploaded 13 Jan 2023Source
- 5 Declaration in FORM B10 7-FORM B-promoter-Cliff Resi-Part V.pdf · uploaded 13 Jan 2023Source
- 1 Copy of the legal title reportTitle - PSCL.pdf · uploaded 19 Jan 2023Source
- 1 Proforma of Agreement for saleAFS_The Cliff Residences_Pranajpee Scheme_18012023.pdf · uploaded 19 Jan 2023Source
- 1 CERSAI detailsCERSAI Cliff.pdf · uploaded 20 Jan 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A Cliff Residences JUNE 23-uploaded.pdf · uploaded 11 Jul 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 -R32 Cliff Residences 21July2023.pdf · uploaded 5 Aug 2023Source
- 1 Disclosure of sold/ booked inventoryInventory Report-Cliff res-June'23.pdf · uploaded 5 Aug 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2-R32 Cliff Resi-Mar'23.pdf · uploaded 8 Aug 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2-R32 Cliff Resi-June'23.pdf · uploaded 8 Aug 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-Cliff residences-Mar'23.pdf · uploaded 10 Aug 2023Source
- 2 Disclosure of sold/ booked inventoryR32 Cliff Resi-Disclosure of Inventory-Mar'23.pdf · uploaded 11 Aug 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Cliff Residences - FOrm 3 - 31st March 23.pdf · uploaded 28 Aug 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3-CA Certificate-Cliff Residences -30th June 23.pdf · uploaded 28 Aug 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2 A SEPT 23 CLIFF RESIDENCIES-uploaded.pdf · uploaded 3 Oct 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2-Forest Trails R32-Sept'23-uploaded.pdf · uploaded 11 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5-Cliff Residencies-Fy-22'23-uploaded-11Oct'23.pdf · uploaded 11 Oct 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-R32 Cliff Residences-July'23 to Sept'23-uploaded.pdf · uploaded 27 Feb 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-R32 Cliff Resi-Oct23 to Dec'23-uploaded.pdf · uploaded 27 Feb 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2-Oct'23 to Dec'23-CLIFF RESI-uplaoded.pdf · uploaded 27 Feb 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-July'23 to Sept'23-CLIFF RESI-uploaded.pdf · uploaded 27 Feb 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-Oct'23 to Dec'23-CLIFF RESI-uploaded.pdf · uploaded 27 Feb 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 Form 1- Cliff Residences-31 mar'24-June'24 query-uploaded.pdf · uploaded 29 Jun 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)4 Form 2-Cliff Residences-31Mar'24-June'24 query-uploaded.pdf · uploaded 29 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2 Form 2A-Cliff Resi-31Mar'24-June'24 query.pdf · uploaded 29 Jun 2024Source
- 3 Disclosure of sold/ booked inventory1 Disclosure of Inventory-Cliff Residences-31Mar'24-June'24 query.pdf · uploaded 29 Jun 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)5 FORM 3-Cliff Resi-31Mar'24.pdf · uploaded 29 Jun 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Cliff Residences - FOrm 3 - 31st March 24.pdf · uploaded 6 Aug 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Form 2-Cliff Resi -31 Mar24 for June24 query-Engg stamp.pdf · uploaded 13 Aug 2024Source
Technical
Technical (Architect)
- Document3 Form 1- Cliff Residences-31 mar'24-June'24 query-uploaded.pdf · uploaded 29 Jun 2024Source
Technical (Engineer)
- Document2 Form 2-Cliff Resi -31 Mar24 for June24 query-Engg stamp.pdf · uploaded 13 Aug 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsSectorR32, Survey No. 16/1/1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- Bungalow12 units in all
- Address
- Survey No. 16/1/1, Sector-R32, Paud Road, Bhugaon, PunePIN 412115
- Village
- Bhugaon, Mulshi taluka
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- U27 Sector R10
- South
- 12 Meter wide internal Road
- East
- 12 Meter wide internal road
- West
- Hg 15
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking12 units
0 of 12 units booked (0%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Unit 1 | Bungalow | 365.35 sq m · 3,933 sq ft | 1 | 0 |
| Unit 10 | Bungalow | 363.95 sq m · 3,918 sq ft | 1 | 0 |
| Unit 11 | Bungalow | 363.95 sq m · 3,918 sq ft | 1 | 0 |
| Unit 12 | Bungalow | 364.15 sq m · 3,920 sq ft | 1 | 0 |
| Unit 2 | Bungalow | 363.03 sq m · 3,908 sq ft | 1 | 0 |
| Unit 3 | Bungalow | 363.03 sq m · 3,908 sq ft | 1 | 0 |
| Unit 4 | Bungalow | 363.03 sq m · 3,908 sq ft | 1 | 0 |
| Unit 5 | Bungalow | 366.23 sq m · 3,942 sq ft | 1 | 0 |
Show all 12 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Unit 6 | Bungalow | 363.65 sq m · 3,914 sq ft | 1 | 0 |
| Unit 7 | Bungalow | 359.75 sq m · 3,872 sq ft | 1 | 0 |
| Unit 8 | Bungalow | 363.95 sq m · 3,918 sq ft | 1 | 0 |
| Unit 9 | Bungalow | 363.95 sq m · 3,918 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Cornerstones Works Pvt Ltd | — |
| Chartered accountant | S T P & Associates | — |
| Engineer | Shekhar Pingale | — |
| Other | Makrand Arvind Prabhu | — |
Source: MahaRERA project page. Contact details are not shown.