Regulatory order: PROJECT NAME: FOREST TRAILS ATHASHRI - B2 (Regulatory Case No.85 of 2023) dated 7 November 2023.
7 Nov 2023 · matched by RERA number
View order →RERA check · free, always
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
Forest Trails Athashri - B2 · Bhugaon, Pune · Paranjape Schemes (Construction) Ltd
Promised for 31 Jul 2022; MahaRERA reports the project completed.
The revised date is 2 years after the original promise.
Facts from the record. A flag is a reason to ask questions, not a verdict.
Regulatory order: PROJECT NAME: FOREST TRAILS ATHASHRI - B2 (Regulatory Case No.85 of 2023) dated 7 November 2023.
7 Nov 2023 · matched by RERA number
View order →Complaint CC005000000208295
matched by RERA number
View on MahaRERAComplaint CC005000000258888
matched by RERA number
View on MahaRERAComplaint CC005000000290036
matched by RERA number
View on MahaRERAComplaint CC005000000290255
matched by RERA number
View on MahaRERAComplaint CC005000000320612
matched by RERA number
View on MahaRERAComplaint CC005000000340654
matched by RERA number
View on MahaRERAComplaint CC005000000421093
matched by RERA number
View on MahaRERAComplaint CC005000000471329
matched by RERA number
View on MahaRERAComplaint CC005000000471507
matched by RERA number
View on MahaRERAComplaint CC12400207
matched by RERA number
View on MahaRERAComplaint CC12400985
matched by RERA number
View on MahaRERAComplaint CC12503253
matched by RERA number
View on MahaRERAComplaint CC12601016
matched by RERA number
View on MahaRERAComplaint CC12604591
matched by RERA number
View on MahaRERAComplaint CC12604742
matched by RERA number
View on MahaRERAComplaint CC12604864
matched by RERA number
View on MahaRERAComplaint CC12606273
matched by RERA number
View on MahaRERAAppeal AT05/01652/2026
matched by RERA number
View on MahaRERAAppeal AT05/01548/2026
matched by RERA number
View on MahaRERAAppeal AT05/00749/2026
matched by RERA number
View on MahaRERAAppeal AT05/00748/2026
matched by RERA number
View on MahaRERAAppeal AT05/00747/2026
matched by RERA number
View on MahaRERAAppeal AT05/00746/2026
matched by RERA number
View on MahaRERAAppeal AT05/00745/2026
matched by RERA number
View on MahaRERAMahaRERA reports it completed. Its promised completion date was 31 Jul 2022.
Deedo holds 1 extension certificate for P52100000029. The completion date moved from 31 Jul 2022 to 31 Jul 2024.
MahaRERA records Paranjape Schemes (Construction) Ltd as the promoter of P52100000029.
25 MahaRERA orders or lists name P52100000029.
Answers are generated from the record.