RegisteredRevised date passedExtendedMahaRERA status: Certificate Signed

P52100025946

Trident Business Park · Wakad, Pune · Paranjape Schemes (Construction) Ltd

Promised for 30 Jun 2026, extended to 30 Oct 2026 — and that date has passed without the project marked complete on MahaRERA.

5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2026 to 30 Oct 2026.
  • Risk: The latest completion date on record, 30 Oct 2026, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate14 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100025946

Is Trident Business Park delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2026, revised to 30 Oct 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100025946. The completion date moved from 30 Jun 2026 to 30 Oct 2026.

Who is the promoter?

MahaRERA records Paranjape Schemes (Construction) Ltd as the promoter of P52100025946.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100025946.

Answers are generated from the record.

Data through23 Nov 2026, 01:46SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology