RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52100016218

Azure · Tathwade, Pune · Paranjape Schemes (Construction) Ltd

Promised for 1 Jun 2022 — that date has passed and MahaRERA does not mark the project complete.

4 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 1 Jun 2022, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100016218

Is Azure delayed?

Yes. MahaRERA records a promised completion of 1 Jun 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100016218.

Who is the promoter?

MahaRERA records Paranjape Schemes (Construction) Ltd as the promoter of P52100016218.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100016218.

Answers are generated from the record.

Data through23 Nov 2026, 01:39SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology