Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800000454

127 Upper East · Andheri, Mumbai Suburban · Paranjape Schemes (Construction) Ltd

Promised for 31 Oct 2022, extended once to 30 Jun 2024 — and that date has passed without the project marked complete on MahaRERA.

4 years and 1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Oct 2022 to 30 Jun 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2024, has passed.
  • Caution: 1 other MahaRERA order names this registration.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate4 May 2023View
Extension certificate21 Nov 2023View
OtherView

Orders 1

Regulatory order

Regulatory order: PROJECT NAME: 127 UPPER EAST(Regulatory Case No.83 of 2023) dated 7 November 2023.

7 Nov 2023 · matched by RERA number

View order →

Questions about P51800000454

Is 127 Upper East delayed?

Yes. MahaRERA records a promised completion of 31 Oct 2022, revised to 30 Jun 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800000454. The completion date moved from 31 Oct 2022 to 30 Jun 2024.

Who is the promoter?

MahaRERA records Paranjape Schemes (Construction) Ltd as the promoter of P51800000454.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P51800000454.

Answers are generated from the record.

Data through23 Nov 2026, 01:36SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology