RERA projects in Amravati (M Corp.)

303 projects under 309 MahaRERA registrations, registered 2017–2026. 21% have a completion date extended beyond the one promised.

Locality
303RERA projects
309Registrationssome projects hold several
68Completion still due241 past their completion date, 152 marked completed
9 monthsMedian extension beyond promised date21% of registrations extended
15Regulatory caseson 13 projects
942Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201781
201841
201928
202021
202133
202227
202338
202420
202519
20261

Projects in Amravati (M Corp.)

303 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Galaxy TowerSky Line Builders And DevelopersP503000485246 Jan 202331 Dec 2025—Promised date passed1
DhruvataraAda AssociatesP503000483923 Jan 20235 Jul 2025—Promised date passed1
Krushnayan ResidencyRayaji RealtyP5030004831126 Dec 202231 Oct 2025—Promised date passed0
Gayatri HeightsRajesh Rameshpant KherdeP5030004820915 Dec 20221 Apr 2027—Completed0
Rukhmini ResidencyRavindra WankhadeP5030004819915 Dec 202210 Oct 2025—Promised date passed0
G B DesireG B ConstructionP5030004812012 Dec 202231 Mar 2025—Promised date passed0
Sai Sagar Enclave XivSagar Pandharinath BankarP5030004814212 Dec 202231 Mar 2027—Not yet due0
Galaxy TowerFirozkhan MusakhanP503000480898 Dec 202231 Dec 202431 Dec 2024Promised date passed0
DCC Dreamz City ChambersDreamz-City Real Estate Pvt LtdP503000480157 Dec 202231 Oct 202628 Feb 2027Extended 4 mo0
Ali TowerUniversal BuildersP503000479782 Dec 202222 Aug 202422 Aug 2024Promised date passed0
Vijayshree ParkPankajkumar Rameshrao DeshmukhP5030004772021 Nov 202230 Dec 202730 Apr 2028Extended 4 mo0
GokuldhamGokuldham ConstructionP5030004733119 Oct 202231 Mar 202531 Mar 2025Promised date passed0
Krushnai HeightsUrja InfrastructureP5030004690216 Sep 202231 Dec 202415 Dec 2025Extended 12 mo1
Mauli ApartmentPrakash Namdeorao SaurkarP5030004685514 Sep 202221 Dec 202320 Dec 2024Extended 12 mo0
Deep ResidencyDeep Builders And DevelopersP5030004621720 Jun 202231 Mar 202631 Jul 2026Extended 4 mo0
Gokuldham ResidencyM/S C & D Engineer's & DevelopersP5030004613920 Jun 202231 Jul 202630 Nov 2026Extended 4 mo0
Gurumauli ResidencyManoj Santoshrao DeshmukhP5030004622620 Jun 202230 Jun 202430 Jun 2024Promised date passed0
Sai Isha ApartmentAjayshree ApartmentP5030004588115 Jun 202231 Dec 202531 Dec 2025Promised date passed0
Shri Krishna ResidencyS R Builders And DevelopersP5030004599715 Jun 202231 Mar 202531 Mar 2025Promised date passed0
Kailash TowerShyam Prabhakarrao KedareP5030004544218 May 202231 Dec 2024—Promised date passed0
Sai InfinityAgarkar Builders And DeveloperP5030004532312 May 202231 Mar 2027—Not yet due0
Jaee Residency 2Manisha Anantkumar LingotP5030003423425 Mar 202215 Aug 2025—Completed0
ChandanvadiShri Amarnath Builders And DevelopersP5030003392014 Mar 202230 Sep 2026—Promised date passed0
Purvika ResidencyKedia Builders And DevelopersP5030003392914 Mar 202220 Jun 202319 Jun 2024Completed0
Vasudeo ApartmentSaurabh Raju IngoleP503000338008 Mar 202231 Mar 2027—Completed0

Other localities in Amravati

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Vijay Nanakram Talda5 projects
  2. Garden City4 projects
  3. P S Associates4 projects
  4. Amber Builders And Developers3 projects
  5. Kamal Digrilal Malviya3 projects
  6. Laxmikant Prabhakar Joshi3 projects
  7. M/S C & D Engineer's & Developers3 projects
  8. Nitesh Shyam Bundele3 projects
  9. Ravindra Pundlikrao Mahalle3 projects
  10. Sagar Pandharinath Bankar3 projects
Data through19 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology