Kailash Tower

Completion date passed

Amravati (M Corp.), Amravati 444603 |Promoter: Shyam Prabhakarrao Kedare

18 May 2022Registered with MahaRERA
31 Dec 2024Promised completion
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Land area for this project
279 sq m (3,000 sq ft)
Permissible built-up area
853 sq m (9,181 sq ft)
Sanctioned built-up area
803 sq m (8,643 sq ft)
Designated bank account
Idbi Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Kailash Tower is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2024

The latest completion date on record passed 1 year and 10 months ago.

Registered
18 May 2022
Promised
31 Dec 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030004544218 May 202231 Dec 2024—Shyam Prabhakarrao KedareProject page

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000012
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Kailash Tower

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyAS PER MAP0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER MAP0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER MAP0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

15 documents held by Deedo, 15 filings listed on MahaRERA's project page

Encumbrance

Building plan

Commencement certificates

Others

Allotment letters

Titles

Layout plan

Form b

Registration certificate

Document library

  • Details of encumbrancesnon encum (1).pdf · uploaded 22 Apr 2022View
  • Commencement Certificates / NA Order for plotted developmentCommesment Certificate.pdf · uploaded 22 Apr 2022View
  • Declaration about Commencement CertificateDCC K.pdf · uploaded 22 Apr 2022View
  • Proforma of Allotment letterAgreement to sale.pdf · uploaded 22 Apr 2022View
  • Proforma of Allotment letterallotment k.pdf · uploaded 22 Apr 2022View
  • Building Plan Approval / NA Order for plotted developmentKhandelwal map (1).pdf · uploaded 22 Apr 2022View
  • CERSAI detailsCERSAI_Search_Report_200235608223_For_Asset_Based_Search_22_04_2022_11_55_18_213.pdf · uploaded 22 Apr 2022View
  • Copy of the legal title reportSEARCH 13052022.pdf · uploaded 13 May 2022View
  • Copy of the legal title reportFLOW KEDARE13052022.pdf · uploaded 13 May 2022View
  • Copy of Layout Approval (in case of layout)LAYOUT KEDARE13052022.pdf · uploaded 13 May 2022View
  • Declaration in FORM BShyam FORM B_compressed.pdf · uploaded 13 May 2022View

Promoter documents

  • Legal Title reportSEARCH 13052022.pdf · uploaded 13 May 2022View
  • Legal Title reportFLOW KEDARE13052022.pdf · uploaded 13 May 2022View
  • Declaration Form BShyam FORM B_compressed.pdf · uploaded 13 May 2022View

Proforma allotment letter

  • Proforma allotment letterallotment k.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.)

Survey, CTS, gat or plot numbers

163/2163/2Plot No. 39 Field Survey No. 162/1-APlot No. 39 Field Survey No. 162/1A

As published on MahaRERA's project page

Plot No. 39 Field Survey No. 162/1-A And 163/2

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAbu Sufiyan Abdul Rauf—
Chartered accountantJ S Khandelwal & Co—
EngineerAbu Sufiyan Abdul Rauf—
OtherRishabh Khandelwal—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology