RERA projects in Amravati

446 projects under 457 MahaRERA registrations across 29 localities, registered 2017–2026. 23% have a completion date extended beyond the one promised.

District
446RERA projectsin 29 localities
457Registrationssome projects hold several
96Completion still due284 past their completion date, 170 marked completed
4 monthsMedian extension beyond promised date23% of registrations extended
38Regulatory caseson 36 projects
1,125Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201791
201847
201934
202026
202135
202232
202349
202426
202520
202620

Projects in Amravati

446 projects registered with MahaRERA in this district and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
My Orchid Heights Phase INitin BhatkarP5030005645031 May 202431 Dec 2028—Not yet due0
Shree Gajanan EnclaveAjay Namdeorao DambaleP5030005633629 May 202431 Mar 2028—Completed0
The Busyland Block-MBusyland Construction CoP5030005621422 May 20241 Jan 2027—Not yet due0
The PresidentSrushti BandsonsP5030005606510 May 202415 Jun 2026—Promised date passed0
Srushti CommercialsSrushti CommercialsP5030005585823 Apr 202415 Jun 2026—Promised date passed0
Aai Residency IISamir Haribhau PandeP503000555172 Apr 202430 Jun 2026—Completed0
Sky Garden HillsV & M Builders & DevelopersP5030005539922 Mar 202431 Dec 2027—Not yet due1
Krushnayan PrimeRayaji RealtyP5030005525114 Mar 202431 Dec 2027—Completed0
Ratna MauliRatna Mauli ConstructionsP503000551084 Mar 202431 Dec 2025—Promised date passed0
Shivray CommercialShivray BuilderP5030005486015 Feb 202431 Mar 2028—Completed0
Diamond HeightsQuality Stone Construction And Developers LLPP5030005473912 Feb 202431 Dec 2027—Not yet due0
Lifestyle HomesLifestyle Home SpacesP5030005444725 Jan 202430 Nov 2027—Not yet due0
GokulamGovinda Ganesha InfraspacesP50300054287, P5030005563415 Jan 202431 Oct 2026—Not yet due0
Avantika ResidencyPratiksha Pravin MahalleP503000542113 Jan 202429 Jan 2029—Not yet due0
Rukhmini HeightsSadani And Paturde Builders LLPP503000541943 Jan 202431 May 2027—Not yet due0
Indrayani wadaGovind Shridhar TatteP5030005412627 Dec 202331 Dec 2026—Not yet due0
Millenium ParkCity Empire Infra LLPP5030005411227 Dec 202330 Apr 202730 Aug 2027Extended 4 mo0
Keshav Empire Phase IISachin Keshaorao IngoleP5030005375328 Nov 202331 Jul 202930 Nov 2029Extended 4 mo0
Sai CityAnshuman BuildersP5030005361810 Nov 202331 Mar 202631 Jul 2026Extended 4 mo0
Keshavam HeightsShri Govinda BuildconP5030005334027 Oct 202331 Mar 202631 Jul 2026Extended 4 mo0
Datta NagariVijay Nanakram TaldaP50300053198, P5030005339823 Oct 202331 Mar 202531 Mar 2025Promised date passed0
Shri Girijatmaj HeightsSagar Prakashrao ButeP5030005330523 Oct 202331 Dec 202630 Apr 2027Extended 4 mo0
Amravati ComplexRanjana Sunil ZombadeP5030005316117 Oct 202331 Dec 202630 Apr 2027Extended 4 mo0
Nilkanth HeightsBhaskar Gomaji DahatP5030005301610 Oct 202331 May 202531 May 2025Promised date passed0
Grisha Height SkylineSkyline RealitiesP503000528935 Oct 202331 Mar 202931 Jul 2029Extended 4 mo0

Localities in Amravati

By number of registered projects, as MahaRERA names them.

All 29 localities

Other districts

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Vijay Nanakram Talda6 projects
  2. Garden City4 projects
  3. Laxmikant Prabhakar Joshi4 projects
  4. P S Associates4 projects
  5. Ravindra Pundlikrao Mahalle4 projects
  6. Sagar Prakashrao Bute4 projects
  7. Amber Builders And Developers3 projects
  8. Jayant Parmanand Chhutlani3 projects
  9. Kamal Digrilal Malviya3 projects
  10. M/S C & D Engineer's & Developers3 projects
Data through19 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology