Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 34% of its units are booked.

Warud (M Cl), Amravati 444906 · by Ranjana Sunil Zombade

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales34% booked14 of 41 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 17 Oct 2023, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP50300053161
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030005316117 Oct 202331 Dec 202630 Apr 2027Ranjana Sunil ZombadeProject page
Documents143

47 documents held by Deedo, 96 filings listed on MahaRERA's project page

Registration certificate

Commencement certificate (2)

  • Commencement certificateDate not statedView
  • Commencement certificateDate not statedView

Form 1 (17)

  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
Show all 143 documentsShow fewer documents

Form 1 (17)

  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView

Other (14)

  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView

Title report

  • Title reportDate not statedView

Encumbrance details (2)

  • Encumbrance detailsDate not statedView
  • Encumbrance detailsDate not statedView

Layout plan (5)

  • Layout planDate not statedView
  • Layout planDate not statedView
  • Layout planDate not statedView
  • Layout planDate not statedView
  • Layout planDate not statedView

Allotment letter

  • Allotment letterDate not statedView

Form 2 (3)

  • Form 2Date not statedView
  • Form 2Date not statedView
  • Form 2Date not statedView

Form B

  • Form BDate not statedView

Finance

  • PAN CardPAN.pdf · uploaded 15 Jun 2023View

Legal

  • Legal Title reportMTR form.pdf · uploaded 15 Jun 2023View
  • Declaration Form BForm B.pdf · uploaded 23 Jun 2023View

Migrated

  • 1 PAN CardPAN.pdf · uploaded 15 Jun 2023View
  • 1 Copy of the legal title reportMTR form.pdf · uploaded 15 Jun 2023View
  • 1 a Details of encumbrances concerned to FinanceNon encumbrance declaration.pdf · uploaded 15 Jun 2023View
  • 1 b Details of encumbrances concerned to LegalNon encumbrance declaration.pdf · uploaded 15 Jun 2023View
  • 1 Copy of Layout Approval (in case of layout)ZOMBADE DRG (2).pdf · uploaded 15 Jun 2023View
  • 1 Building Plan Approval / NA Order for plotted developmentZOMBADE DRG (2).pdf · uploaded 15 Jun 2023View
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 15 Jun 2023View
  • 1 Declaration about Commencement CertificateDeclaration about commencement certificate.pdf · uploaded 15 Jun 2023View
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest in other organisation.pdf · uploaded 15 Jun 2023View
  • 1 Proforma of Allotment letterzombade allotment letter.pdf · uploaded 15 Jun 2023View
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameorder 34 declaration abt bank account.pdf · uploaded 15 Jun 2023View
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report AFS.pdf · uploaded 15 Jun 2023View
  • 1 CERSAI detailsCERSAI declaration.pdf · uploaded 18 Jun 2023View
  • 1 Proforma of Agreement for saleRanjana Zombade Agreement.pdf · uploaded 19 Jun 2023View
  • 1 Declaration in FORM BForm B.pdf · uploaded 23 Jun 2023View
  • 1 Deviation Report with respect to Allotment letterDEVIATION REPORT FOR ALLOTMENT LETTER.pdf · uploaded 23 Jun 2023View
  • 2 Copy of Layout Approval (in case of layout)Sanctioned Map.pdf · uploaded 27 Jun 2023View
  • 2 Building Plan Approval / NA Order for plotted developmentSanctioned Map.pdf · uploaded 27 Jun 2023View
  • 1 Other – TechnicalFORM 3 final 28 7.pdf · uploaded 1 Aug 2023View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 23 8 23.pdf · uploaded 24 Aug 2023View
  • 2 Other – TechnicalNMC CC letter.pdf · uploaded 11 Oct 2023View
  • 3 Other – TechnicalEmail To MAHARERA.pdf · uploaded 11 Oct 2023View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect (1).pdf · uploaded 26 Dec 2023View
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate .pdf · uploaded 26 Dec 2023View
  • 1 Disclosure of sold/ booked inventoryAmravati unit book sold.pdf · uploaded 26 Dec 2023View
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 final.pdf · uploaded 31 Dec 2023View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 12 Apr 2024View
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 12 Apr 2024View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 12 Apr 2024View
  • 2 Disclosure of sold/ booked inventoryAmravati unit book sold.pdf · uploaded 12 Apr 2024View
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 12 Apr 2024View
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 8 Jul 2024View
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 8 Jul 2024View
  • 3 Disclosure of sold/ booked inventoryAmravati Book Sold 6-2024.pdf · uploaded 8 Jul 2024View
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 final 14_07_2024.pdf · uploaded 15 Jul 2024View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 15 Oct 2024View
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 final _compressed.pdf · uploaded 15 Oct 2024View
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 15 Oct 2024View
  • 2 Disclosure of sold/ booked inventoryBook sold 30_09_2024.pdf · uploaded 15 Oct 2024View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 15 Jan 2025View
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 15 Jan 2025View
  • 1 Disclosure of sold/ booked inventorysold unsold declaration.pdf · uploaded 15 Jan 2025View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 18 Jan 2025View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 17 Apr 2025View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed (1).pdf · uploaded 17 Apr 2025View
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 17 Apr 2025View
  • 1 Disclosure of sold/ booked inventoryBook Sold 31-03-2025.pdf · uploaded 17 Apr 2025View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 17 Apr 2025View
  • Withdrawal Update Form 1Form 1.pdf · uploaded 6 Nov 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 6 Nov 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 6 Nov 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 6 Nov 2025Source
  • Withdrawal Update Form 3Amravati Complex FORM-3 Sep 25.pdf · uploaded 6 Nov 2025Source
  • Withdrawal Update Form 3Amravati Complex FORM-3 Sep 25.pdf · uploaded 6 Nov 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 3Amravati Complex FORM-3 Sep 25.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 3Amravati Complex FORM-3 Sep 25.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 3Amravati Complex FORM-3 Sep 25.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 1form 1_compressed.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 2Form 2_compressed.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 3FORM-3.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 1Form 1_compressed (1).pdf · uploaded 30 Apr 2026Source
  • Withdrawal Update Form 2Form 2_compressed (1).pdf · uploaded 30 Apr 2026Source
  • Withdrawal Update Form 3Form 3 March 26.pdf · uploaded 30 Apr 2026Source
  • Withdrawal Update Form 1Form 1_compressed (2).pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 1Form 1_compressed (2).pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 1Form 1_compressed (2).pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 2Form 2_compressed (2).pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 2Form 2_compressed (2).pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 2Form 2_compressed (2).pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 3form 3.pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 3form 3.pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 3form 3.pdf · uploaded 9 Jul 2026Source

Technical

  • DocumentZOMBADE DRG (2).pdf · uploaded 15 Jun 2023View
  • DocumentZOMBADE DRG (2).pdf · uploaded 15 Jun 2023View
  • DocumentSanctioned Map.pdf · uploaded 27 Jun 2023View
  • DocumentSanctioned Map.pdf · uploaded 27 Jun 2023View
  • Other – TechnicalFORM 3 final 28 7.pdf · uploaded 1 Aug 2023View
  • Other – TechnicalNMC CC letter.pdf · uploaded 11 Oct 2023View
  • Other – TechnicalEmail To MAHARERA.pdf · uploaded 11 Oct 2023View

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 15 Oct 2024View
  • Documentform 1.pdf · uploaded 15 Jan 2025View
  • DocumentForm 1.pdf · uploaded 17 Apr 2025View
  • DocumentForm 1_compressed (2).pdf · uploaded 9 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 15 Oct 2024View
  • DocumentForm 2.pdf · uploaded 15 Jan 2025View
  • DocumentForm 2.pdf · uploaded 17 Apr 2025View
  • DocumentForm 2_compressed (2).pdf · uploaded 9 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 182, 39B10 SR. NO. 180/1A

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, Hall, Shop41 units in all
Address
3-9b-10 Sr. No. 180/1a, 182, Mouje Warud Bhag-2, Warud Part 2PIN 444906
Village
Warud (M Cl), Warud taluka
Land area for this project
859 sq m (9,248 sq ft)
Permissible built-up area
2,618 sq m (28,185 sq ft)
Sanctioned built-up area
2,101 sq m (22,615 sq ft)
Designated bank account
220
Developed in phases
No

Survey, CTS, gat or plot numbers

18239B10 SR. NO. 180/1A

Land as published on MahaRERA's project page

3-9B-10 SR. NO. 180/1A,182

Boundaries

North
9 M Wide Raod
South
12 M Wide Road
East
Plot No 4
West
12 M Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking41 units

14 of 41 units booked (34%), as the promoter reported to MahaRERA

1BHK · 1 unitHall · 4 unitsShop · 36 units
TypeCarpet areaUnitsBooked
1BHK464.86 sq m · 5,004 sq ft10
Hall72.51 sq m · 780 sq ft21
Hall92.95 sq m · 1,001 sq ft20
Shop15.09 sq m · 162 sq ft32
Shop16.13 sq m · 174 sq ft21
Shop16.14 sq m · 174 sq ft10
Shop17.17 sq m · 185 sq ft31
Shop18.12 sq m · 195 sq ft31
Show all 19 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop19.16 sq m · 206 sq ft43
Shop20.42 sq m · 220 sq ft21
Shop20.67 sq m · 222 sq ft30
Shop21.71 sq m · 234 sq ft31
Shop22.87 sq m · 246 sq ft31
Shop23.96 sq m · 258 sq ft31
Shop24.04 sq m · 259 sq ft21
Shop25.09 sq m · 270 sq ft10
Shop25.62 sq m · 276 sq ft10
Shop33.39 sq m · 359 sq ft10
Shop38.76 sq m · 417 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectGirish Nagpure Nagpure—
Chartered accountantCap and Co Thakre—
EngineerAMIT MEHARE Mehare—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Warud (M Cl)

All 2 projects in Warud (M Cl) · Compare Amravati Complex with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology