Gokulam

Lapsed

Hirapur, Amravati 444602 |Promoter: Govinda Ganesha Infraspaces

15 Jan 2024Registered with MahaRERAFirst of 2 registrations
31 Oct 2026Promised completionLatest across registrations
59Buildings2 phases
20Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
RERA registrations
2
Phases
2
Buildings
59
Unit types
Row house20 units in all
Land area for this project
1,823 sq m (19,625 sq ft)
Permissible built-up area
2,066 sq m (22,234 sq ft)
Sanctioned built-up area
2,066 sq m (22,234 sq ft)
Address
Survey No 17/1 & 17/2 Mouje Hirapur Prangane Nandgaonpeth, Hirapur To Rewsa Road, HirapurPIN 444602
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.99847, 77.74960
Gokulam is at latitude 20.99847, longitude 77.74960.

Also registered as

Gokulam 2

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Oct 2025

P50300054287

The latest completion date on record passed 1 year ago.

Registered
15 Jan 2024
Promised
31 Oct 2025

Completion promised for 31 Oct 2026

P50300055634
Registered
5 Apr 2024
Promised
31 Oct 2026

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030005428715 Jan 202431 Oct 2025—Govinda Ganesha InfraspacesProject page
P503000556345 Apr 202431 Oct 2026—Govinda Ganesha InfraspacesProject page

59 buildings

Buildings and wings named in the registration

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

20 units registered

Row house · 20 units
RERABuildingTypeCarpet areaUnits
P50300054287Row House No 130 To 142/12Row house76.56 sq m · 824 sq ft1
P50300054287Row House No 130 To 142/15Row house77.4 sq m · 833 sq ft1
P50300054287Row House No 130 To 142/16Row house77.4 sq m · 833 sq ft1
P50300054287Row House No 130 To 142/18Row house77.4 sq m · 833 sq ft1
P50300054287Row House No 130 To 142/19Row house77.4 sq m · 833 sq ft1
P50300054287Row House No 130 To 142/20Row house77.4 sq m · 833 sq ft1
P50300054287Row House No 130 To 142/21Row house77.4 sq m · 833 sq ft1
P50300054287Row House No 130 To 142/22Row house76.56 sq m · 824 sq ft1
P50300054287Row House No 145 To 157/1Row house83.96 sq m · 904 sq ft1
P50300054287Row House No 145 To 157/2Row house87.65 sq m · 943 sq ft1
P50300054287Row House No 145 To 157/3Row house87.65 sq m · 943 sq ft1
P50300054287Row House No 145 To 157/4Row house87.65 sq m · 943 sq ft1
P50300054287Row House No 145 To 157/5Row house87.65 sq m · 943 sq ft1
P50300054287Row House No 145 To 157/6Row house83.96 sq m · 904 sq ft1
P50300054287Row House No 158 To 169/1Row house87.34 sq m · 940 sq ft1
P50300054287Row House No 158 To 169/2Row house87.35 sq m · 940 sq ft1
P50300054287Row House No 158 To 169/3Row house79.63 sq m · 857 sq ft1
P50300054287Row House No 158 To 169/4Row house87.64 sq m · 943 sq ft1
P50300054287Row House No 158 To 169/5Row house87.35 sq m · 940 sq ft1
P50300054287Row House No 158 To 169/6Row house87.35 sq m · 940 sq ft1

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Gokulam House 01 C22Closed/Covered00000
Gokulam House 01 C22Open Space00000
Gokulam House 01 D1Closed/Covered00000
Gokulam House 01 D1Open Space00000
Gokulam House 02 C21Closed/Covered00000
Gokulam House 02 C21Open Space00000
Gokulam House 02 D2Closed/Covered00000
Gokulam House 02 D2Open Space00000
Gokulam House 03 C20Closed/Covered00000
Gokulam House 03 C20Open Space00000
Gokulam House 03 D3Closed/Covered00000
Gokulam House 03 D3Open Space00000
Gokulam House 04 C19Closed/Covered00000
Gokulam House 04 C19Open Space00000
Gokulam House 04 D4Closed/Covered00000
Gokulam House 04 D4Open Space00000
Gokulam House 05 C18Closed/Covered00000
Gokulam House 05 C18Open Space00000
Gokulam House 05 D5Closed/Covered00000
Gokulam House 05 D5Open Space00000
Gokulam House 06 C17Closed/Covered00000
Gokulam House 06 C17Open Space00000
Gokulam House 06 D6Closed/Covered00000
Gokulam House 06 D6Open Space00000
Gokulam House 07 A7Closed/Covered00000
Gokulam House 07 A7Open Space00000
Gokulam House 07 C16Closed/Covered00000
Gokulam House 07 C16Open Space00000
Gokulam House 07 D7Closed/Covered00000
Gokulam House 07 D7Open Space00000
Gokulam House 08 A8Closed/Covered00000
Gokulam House 08 A8Open Space00000
Gokulam House 08 C15Closed/Covered00000
Gokulam House 08 C15Open Space00000
Gokulam House 08 D8Closed/Covered00000
Gokulam House 08 D8Open Space00000
Gokulam House 09 A9Closed/Covered00000
Gokulam House 09 A9Open Space00000
Gokulam House 09 C14Closed/Covered00000
Gokulam House 09 C14Open Space00000
Gokulam House 09 D9Closed/Covered00000
Gokulam House 09 D9Open Space00000
Gokulam House 10 A10Closed/Covered00000
Gokulam House 10 A10Open Space00000
Gokulam House 10 C13Closed/Covered00000
Gokulam House 10 C13Open Space00000
Gokulam House 10 D10Closed/Covered00000
Gokulam House 10 D10Open Space00000
Gokulam House 11 A11Closed/Covered00000
Gokulam House 11 A11Open Space00000
Gokulam House 11 C12Closed/Covered00000
Gokulam House 11 C12Open Space00000
Gokulam House 11 D11Closed/Covered00000
Gokulam House 11 D11Open Space00000
Gokulam House 12 A12Closed/Covered00000
Gokulam House 12 A12Open Space00000
Gokulam House 12 D12Closed/Covered00000
Gokulam House 12 D12Open Space00000
Gokulam House 13Closed/Covered00000
Gokulam House 13Open Space00000
Gokulam House 13 A13Closed/Covered00000
Gokulam House 13 A13Open Space00000
Gokulam House 13 D13Closed/Covered00000
Gokulam House 13 D13Open Space00000
Gokulam House 14Closed/Covered00000
Gokulam House 14Open Space00000
Gokulam House 14 D14Closed/Covered00000
Gokulam House 14 D14Open Space00000
Gokulam House 15 D15Closed/Covered00000
Gokulam House 15 D15Open Space00000
Gokulam House 16 D16Closed/Covered00000
Gokulam House 16 D16Open Space00000
Gokulam House 17Closed/Covered00000
Gokulam House 17Open Space00000
Gokulam House 17 D17Closed/Covered00000
Gokulam House 17 D17Open Space00000
Gokulam House 18 D18Closed/Covered00000
Gokulam House 18 D18Open Space00000
Row House No 130 To 142/12Closed/Covered00000
Row House No 130 To 142/12Open Space00000
Row House No 130 To 142/15Closed/Covered00000
Row House No 130 To 142/15Open Space00000
Row House No 130 To 142/16Closed/Covered00000
Row House No 130 To 142/16Open Space00000
Row House No 130 To 142/18Closed/Covered00000
Row House No 130 To 142/18Open Space00000
Row House No 130 To 142/19Closed/Covered00000
Row House No 130 To 142/19Open Space00000
Row House No 130 To 142/20Closed/Covered00000
Row House No 130 To 142/20Open Space00000
Row House No 130 To 142/21Closed/Covered00000
Row House No 130 To 142/21Open Space00000
Row House No 130 To 142/22Closed/Covered00000
Row House No 130 To 142/22Open Space00000
Row House No 145 To 157/1Closed/Covered00000
Row House No 145 To 157/1Open Space00000
Row House No 145 To 157/2Closed/Covered00000
Row House No 145 To 157/2Open Space00000
Row House No 145 To 157/3Closed/Covered00000
Row House No 145 To 157/3Open Space00000
Row House No 145 To 157/4Closed/Covered00000
Row House No 145 To 157/4Open Space00000
Row House No 145 To 157/5Closed/Covered00000
Row House No 145 To 157/5Open Space00000
Row House No 145 To 157/6Closed/Covered00000
Row House No 145 To 157/6Open Space00000
Row House No 158 To 169/1Closed/Covered00000
Row House No 158 To 169/1Open Space00000
Row House No 158 To 169/2Closed/Covered00000
Row House No 158 To 169/2Open Space00000
Row House No 158 To 169/3Closed/Covered00000
Row House No 158 To 169/3Open Space00000
Row House No 158 To 169/4Closed/Covered00000
Row House No 158 To 169/4Open Space00000
Row House No 158 To 169/5Closed/Covered00000
Row House No 158 To 169/5Open Space00000
Row House No 158 To 169/6Closed/Covered00000
Row House No 158 To 169/6Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Gokulam House 01 C22

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Gokulam House 01 D1

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 02 C21

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 02 D2

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 03 C20

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 03 D3

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 04 C19

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 04 D4

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 05 C18

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 05 D5

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 06 C17

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 06 D6

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 07 A7

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 07 C16

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 07 D7

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 08 A8

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 08 C15

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 08 D8

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 09 A9

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 09 C14

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 09 D9

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 10 A10

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 10 C13

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 10 D10

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 11 A11

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 11 C12

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 11 D11

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 12 A12

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 12 D12

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 13

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 13 A13

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 13 D13

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 14

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 14 D14

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 15 D15

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 16 D16

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 17

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 17 D17

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Gokulam House 18 D18

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 130 To 142/12

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 130 To 142/15

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 130 To 142/16

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 130 To 142/18

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 130 To 142/19

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 130 To 142/20

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 130 To 142/21

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 130 To 142/22

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 145 To 157/1

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Row House No 145 To 157/2

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 145 To 157/3

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 145 To 157/4

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 145 To 157/5

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 145 To 157/6

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 158 To 169/1

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 158 To 169/2

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 158 To 169/3

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 158 To 169/4

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 158 To 169/5

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Row House No 158 To 169/6

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsAS PER PLAN50%
  • Water SupplyAS PER PLAN0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER PLAN0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingAS PER PLAN0%
  • Street LightingAS PER PLAN0%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER PLAN0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationAS PER PLAN0%
  • Aggregate area of recreational Open SpaceAS PER PLAN0%
  • Open ParkingAS PER PLAN0%
  • Internal Roads & FootpathsAS PER PLAN0%
  • Water SupplyAS PER PLAN0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER PLAN0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingAS PER PLAN0%
  • Street LightingAS PER PLAN0%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationAS PER PLAN0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingAS PER PLAN0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

64 documents held by Deedo, 350 filings listed on MahaRERA's project page

Commencement certificates

  • Commencement certificateP50300054287 · 15 Nov 2023ViewSource
  • Commencement certificateP50300055634 · 31 Jan 2024ViewSource
  • Commencement certificateP50300055634 · 31 Jan 2024ViewSource

Form b

Others

Registration certificates

  • Registration certificateP50300054287 · 15 Jan 2024ViewSource
  • Registration certificateP50300055634 · 5 Apr 2024ViewSource

Encumbrance

Allotment letter

Form 1s

Form 2s

Building plans

  • Building planP50300054287 · Date not statedViewSource
  • Building planP50300054287 · Date not statedViewSource
  • Building planP50300054287 · Date not statedViewSource
  • Building planP50300054287 · Date not statedViewSource
  • Building planP50300054287 · Date not statedViewSource
  • Building planP50300054287 · Date not statedViewSource
  • Building planP50300054287 · Date not statedViewSource
  • Building planP50300054287 · Date not statedViewSource
  • Building planP50300054287 · Date not statedViewSource
  • Building planP50300054287 · Date not statedViewSource
  • Building planP50300055634 · Date not statedViewSource
  • Building planP50300055634 · Date not statedViewSource
  • Building planP50300055634 · Date not statedViewSource
  • Building planP50300055634 · Date not statedViewSource
  • Building planP50300055634 · Date not statedViewSource
  • Building planP50300055634 · Date not statedViewSource
  • Building planP50300055634 · Date not statedViewSource
  • Building planP50300055634 · Date not statedViewSource
  • Building planP50300055634 · Date not statedViewSource
  • Building planP50300055634 · Date not statedViewSource
  • Building planP50300055634 · Date not statedViewSource
  • Building planP50300055634 · Date not statedViewSource

Layout plans

Document library

  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 130 to 142-12.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 130 to 142-15.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 130 To 142-16.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 130 to 142-18.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 130 to 142-19.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 130 To 142-20.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 130 to 142-21.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 130 to 142-22.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 145 To 157-1.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 145 To 157-2 Permit.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 145 To 157-3.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 145 To 157-4.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 145 To 157-5.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 145 To 157-6 Permit.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 158 to 169-1.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 158 to 169-2.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 158 To 169-3.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 158 To 169-4.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 158 to 169-5.pdf · uploaded 14 Nov 2023Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · 158 To 169-6 Permit.pdf · uploaded 14 Nov 2023Source
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · dsc 130 to 142-12.pdf · uploaded 14 Nov 2023View
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · dsc 130 to 142-15.pdf · uploaded 14 Nov 2023View
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · dsc 130 to 142-18.pdf · uploaded 14 Nov 2023View
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · dsc 130 to 142-19.pdf · uploaded 14 Nov 2023View
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · dsc 130 to 142-21.pdf · uploaded 14 Nov 2023View
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · dsc 130 to 142-22.pdf · uploaded 14 Nov 2023View
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · Final Draw DSC 130 to 142-16.pdf · uploaded 14 Nov 2023View
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · Final Draw DSC 130 to 142-20.pdf · uploaded 14 Nov 2023View
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · 145 To 157-2 Draw DSC.pdf · uploaded 14 Nov 2023View
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · 145 To 157-6 Draw DSC.pdf · uploaded 14 Nov 2023View
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · Fianl Draw DSC 145 To 157-1.pdf · uploaded 14 Nov 2023Source
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · Fianl Draw DSC 145 To 157-3.pdf · uploaded 14 Nov 2023Source
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · Final Draw DSC 145 To 157-4.pdf · uploaded 14 Nov 2023Source
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · Final Draw DSC 145 TO 157-5.pdf · uploaded 14 Nov 2023Source
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · 158 To 169-1.pdf · uploaded 14 Nov 2023Source
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · 158 TO 169-6 Draw DSC.pdf · uploaded 14 Nov 2023Source
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · Draw dsc 158 to 169-2.pdf · uploaded 14 Nov 2023Source
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · Draw dsc 158 to 169-5.pdf · uploaded 14 Nov 2023Source
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · Draw158 to 169-4.pdf · uploaded 14 Nov 2023Source
  • Building Plan Approval / NA Order for plotted developmentP50300054287 · Final Draw DSC 158 to 169-3.pdf · uploaded 14 Nov 2023Source
  • Copy of the legal title reportP50300054287 · Search RERA_ (1).pdf · uploaded 14 Nov 2023Source
  • Copy of Layout Approval (in case of layout)P50300054287 · Govinda_NA Order Land.pdf · uploaded 14 Nov 2023View
  • Copy of Layout Approval (in case of layout)P50300054287 · NA_Part I.pdf · uploaded 14 Nov 2023View
  • Copy of Layout Approval (in case of layout)P50300054287 · NA_Part II.pdf · uploaded 14 Nov 2023View
  • Copy of Layout Approval (in case of layout)P50300054287 · NA_Part III.pdf · uploaded 14 Nov 2023View
  • a Details of encumbrances concerned to FinanceP50300054287 · Gokulam_Encumberance.pdf · uploaded 15 Nov 2023Source
  • b Details of encumbrances concerned to LegalP50300054287 · Gokulam_Encumberance.pdf · uploaded 15 Nov 2023Source
  • Declaration about Commencement CertificateP50300054287 · Gokulam_Format D Commencement.pdf · uploaded 15 Nov 2023View
  • Declaration in FORM BP50300054287 · Gokulam_Form B.pdf · uploaded 15 Nov 2023View
  • CERSAI detailsP50300054287 · Gokulam_Cersai.pdf · uploaded 15 Nov 2023Source
  • Disclosure of Interest in Other Real Estate OrganizationsP50300054287 · Gokulam_Annexure A Dipak.pdf · uploaded 15 Nov 2023Source
  • Disclosure of Interest in Other Real Estate OrganizationsP50300054287 · Gokulam_Annexure A Ajinkya.pdf · uploaded 15 Nov 2023Source
  • Disclosure of Interest in Other Real Estate OrganizationsP50300054287 · Gokulam_Annexure A Aman.pdf · uploaded 15 Nov 2023Source
  • Disclosure of Interest in Other Real Estate OrganizationsP50300054287 · Gokulam_Annexure A Arjun.pdf · uploaded 15 Nov 2023Source
  • Proforma of Allotment letterP50300054287 · Gokulam_Allotment.pdf · uploaded 15 Nov 2023Source
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP50300054287 · Gokulam_Format A Bank.pdf · uploaded 15 Nov 2023Source
  • Deviation Report with respect to Allotment letterP50300054287 · Gokulam_Deviation Allotment.pdf · uploaded 15 Nov 2023Source
  • Deviation Report with respect to model copy of AgreementP50300054287 · Gokulam_Deviation AFS.pdf · uploaded 15 Nov 2023Source
  • Copy of Layout Approval (in case of layout)P50300054287 · Hirapur 17 - Manoj Bhende _compressed.pdf · uploaded 16 Nov 2023View
  • Proforma of Agreement for saleP50300054287 · ATS_RERA Format_Gokulam_06122023.pdf · uploaded 9 Dec 2023View
  • Other – LegalP50300054287 · Gokulam_Declaration.pdf · uploaded 9 Dec 2023View
  • Other – FinanceP50300054287 · Gokulam_Declaration.pdf · uploaded 9 Dec 2023View
  • Other – TechnicalP50300054287 · Gokulam_Declaration.pdf · uploaded 9 Dec 2023View
  • Other – LegalP50300054287 · Gokulam_Mail.pdf · uploaded 9 Dec 2023View
  • Other – FinanceP50300054287 · Gokulam_Mail.pdf · uploaded 9 Dec 2023View
  • Other – TechnicalP50300054287 · Gokulam_Mail.pdf · uploaded 9 Dec 2023View
  • Copy of Layout Approval (in case of layout)P50300054287 · Gokulam_Layout Map Clear.pdf · uploaded 9 Dec 2023View
  • Other – TechnicalP50300054287 · Gokulam_Declaration Area 020124.pdf · uploaded 2 Jan 2024Source
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP50300054287 · Gokulam_Format A Bank Revised.pdf · uploaded 2 Jan 2024Source
  • Other – FinanceP50300054287 · Gokulam_Declaration Area 020124.pdf · uploaded 2 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · NA_Part I.pdf · uploaded 8 Jan 2024View
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · NA_Part II.pdf · uploaded 8 Jan 2024View
  • Commencement Certificates / NA Order for plotted developmentP50300054287 · NA_Part III.pdf · uploaded 8 Jan 2024View
  • Copy of Layout Approval (in case of layout)P50300054287 · Second Stamp Map.pdf · uploaded 10 Jan 2024View
  • Other – TechnicalP50300054287 · Second Stamp Map.pdf · uploaded 10 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-1-C22.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-2-C21.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-3-C20.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-4-C19.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-5-C18.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-6-C17.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-7-C16.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-8-C15.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-9-C14.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-10-C13.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-11-C12.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-13 C10.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-14 C9.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 130 to 142-17-C6.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 158 to 169-11-A11.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 158 to 169-12-A12.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 158 to 169-13-A13.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 158 to 169-7 A7.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 158 to 169-8 A8.pdf · uploaded 30 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 158 to 169-9 A9.pdf · uploaded 30 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 158 to 169-10 A10.pdf · uploaded 30 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 118 to 129-D2.pdf · uploaded 30 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 118 to 129-D3.pdf · uploaded 30 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 118 to 129-D4.pdf · uploaded 30 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 118 to 129-D14.pdf · uploaded 30 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 118 to 129-D16.pdf · uploaded 30 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 118 to 129-D17.pdf · uploaded 30 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · 118 to 129-D18.pdf · uploaded 30 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 118 to 129-1.pdf · uploaded 30 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 118 to 129-5.pdf · uploaded 30 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 118 to 129-6.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 118 to 129-7.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 118 to 129-8.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 118 to 129-9.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 118 to 129-10.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 118 to 129-11.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 118 to 129-12.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 118 to 129-13.pdf · uploaded 30 Jan 2024Source
  • Building Plan Approval / NA Order for plotted developmentP50300055634 · Draw 118 to 129-15.pdf · uploaded 30 Jan 2024Source
  • Copy of Layout Approval (in case of layout)P50300055634 · Govinda_NA Order Land.pdf · uploaded 30 Jan 2024Source
  • a Details of encumbrances concerned to FinanceP50300055634 · Gokulam 2_Encumberance.pdf · uploaded 31 Jan 2024Source
  • b Details of encumbrances concerned to LegalP50300055634 · Gokulam 2_Encumberance.pdf · uploaded 31 Jan 2024Source
  • CERSAI detailsP50300055634 · Gokulam 2_Cersai.pdf · uploaded 31 Jan 2024Source
  • Disclosure of Interest in Other Real Estate OrganizationsP50300055634 · Gokulam 2_Annexure A Dipak.pdf · uploaded 31 Jan 2024Source
  • Disclosure of Interest in Other Real Estate OrganizationsP50300055634 · Gokulam 2_Annexure A Arjun.pdf · uploaded 31 Jan 2024Source
  • Disclosure of Interest in Other Real Estate OrganizationsP50300055634 · Gokulam 2_Annexure A Aman.pdf · uploaded 31 Jan 2024Source
  • Disclosure of Interest in Other Real Estate OrganizationsP50300055634 · Gokulam 2_Annexure A Ajinkya.pdf · uploaded 31 Jan 2024Source
  • Proforma of Allotment letterP50300055634 · Gokulam 2_Allotment.pdf · uploaded 31 Jan 2024View
  • Deviation Report with respect to model copy of AgreementP50300055634 · Gokulam 2_Deviation AFS.pdf · uploaded 31 Jan 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP50300055634 · Gokulam 2_Format A Bank.pdf · uploaded 31 Jan 2024View
  • Deviation Report with respect to Allotment letterP50300055634 · Gokulam 2_Deviation Allotment.pdf · uploaded 31 Jan 2024View
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-1.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-2.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-3.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-4.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-5.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-6.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-7.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-8.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-9.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-10.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-11.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-12.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-13.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-14.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-15.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-16.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-17.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 118 to 129-18 D18.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-1 C22.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-2.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-3.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-4.pdf · uploaded 31 Jan 2024View
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-5.pdf · uploaded 31 Jan 2024View
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-6.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-7.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-8.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-9.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-10.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-11.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-13.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-14.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 130 to 142-17.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 158 to 169-7 A7.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 158 To 169-8.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 158 to 169-9 A9.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 158 to 169-10 A10.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 158 To 169-11.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 158 To 169-12.pdf · uploaded 31 Jan 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · Cert 158 To 169-13.pdf · uploaded 31 Jan 2024Source
  • Other – LegalP50300055634 · Gokulam 2_Declaration.pdf · uploaded 31 Jan 2024View
  • Other – FinanceP50300055634 · Gokulam 2_Declaration.pdf · uploaded 31 Jan 2024View
  • Other – TechnicalP50300055634 · Gokulam 2_Declaration.pdf · uploaded 31 Jan 2024View
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · NA Order 118 to 129.pdf · uploaded 2 Feb 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · NA_Part I.pdf · uploaded 2 Feb 2024Source
  • Commencement Certificates / NA Order for plotted developmentP50300055634 · NA_Part III.pdf · uploaded 2 Feb 2024Source
  • Copy of Layout Approval (in case of layout)P50300055634 · Second Stamp Map (1).pdf · uploaded 2 Feb 2024View
  • Copy of Layout Approval (in case of layout)P50300055634 · A SERIES.pdf · uploaded 2 Feb 2024View
  • Copy of Layout Approval (in case of layout)P50300055634 · C SERIES.pdf · uploaded 2 Feb 2024View
  • Copy of Layout Approval (in case of layout)P50300055634 · D SERIES.pdf · uploaded 2 Feb 2024View
  • Other – TechnicalP50300055634 · Gokulam 2_Mail.pdf · uploaded 2 Feb 2024View
  • Other – LegalP50300055634 · 118-123.pdf · uploaded 14 Feb 2024View
  • Other – LegalP50300055634 · 124-129.pdf · uploaded 14 Feb 2024View
  • Other – LegalP50300055634 · 130 to 157.pdf · uploaded 14 Feb 2024View
  • Other – LegalP50300055634 · 131-136.pdf · uploaded 14 Feb 2024View
  • Other – LegalP50300055634 · 137-142.pdf · uploaded 14 Feb 2024View
  • Other – LegalP50300055634 · 158-163.pdf · uploaded 14 Feb 2024View
  • Other – LegalP50300055634 · 164-169.pdf · uploaded 14 Feb 2024View
  • Copy of the legal title reportP50300055634 · Gokulam 2_Title Search_Govinda Ganesha Infraspace.pdf · uploaded 14 Feb 2024Source
  • Other – TechnicalP50300055634 · Gokulam 2_Annexure A OPOR.pdf · uploaded 14 Feb 2024View
  • Declaration in FORM BP50300055634 · Gokulam 2_Format B.pdf · uploaded 27 Mar 2024Source
  • Declaration about Commencement CertificateP50300055634 · Gokulam 2_Format D CC.pdf · uploaded 27 Mar 2024Source
  • Proforma of Agreement for saleP50300055634 · ATS Gokulam 2 Final 270324.pdf · uploaded 27 Mar 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300054287 · Gokulam 1_Form 1_310324.pdf · uploaded 20 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300054287 · Gokulam 1_Form 2_310324.pdf · uploaded 20 Apr 2024View
  • Disclosure of sold/ booked inventoryP50300054287 · Gokulam 1_Sold Unsold_310324.pdf · uploaded 20 Apr 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300054287 · Gokulam Arc Cert_Q1_FY 24-25.pdf · uploaded 20 Jul 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300054287 · GOKULAM ENGINEER CERTIFICATE_Form 2 Q1 24-25.pdf · uploaded 20 Jul 2024View
  • Disclosure of sold/ booked inventoryP50300054287 · GOKULAM SOLD UNSOLD INVENTORY _Q1_24-25.pdf · uploaded 20 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300055634 · 2 1 GOKULAM.pdf · uploaded 20 Jul 2024Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300055634 · 2 2 GOKULAM.pdf · uploaded 20 Jul 2024Source
  • Disclosure of sold/ booked inventoryP50300055634 · 2 SOLD - UNSOLD.pdf · uploaded 20 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300054287 · GOKULAM_FORM 1_Q2.pdf · uploaded 21 Oct 2024Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300054287 · GOKULAM_FORM 2_Q2.pdf · uploaded 21 Oct 2024Source
  • Disclosure of sold/ booked inventoryP50300054287 · GOKULAM_SOLD_Q2.pdf · uploaded 21 Oct 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300055634 · GOKULAM 2_FORM 1_SEP 24.pdf · uploaded 21 Oct 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300055634 · GOKULAM 2_FORM 2_SEP 24.pdf · uploaded 21 Oct 2024Source
  • Disclosure of sold/ booked inventoryP50300055634 · GOKULAM 2_SOLD_SEP 24.pdf · uploaded 21 Oct 2024Source
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P50300054287 · Form 5_Gokulam 310324.pdf · uploaded 14 Nov 2024Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300054287 · Gokulam 1 Form 2 Eng Cert Q3 24-25.pdf · uploaded 18 Feb 2025Source
  • Disclosure of sold/ booked inventoryP50300054287 · Gokulam 1 Sold Unsold Q3 24-25.pdf · uploaded 18 Feb 2025Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300055634 · Gokulam 2 Form 2 Eng Cert Q3 24-25.pdf · uploaded 18 Feb 2025Source
  • Disclosure of sold/ booked inventoryP50300055634 · Gokulam 2 Sold Unsold Q3 24-25.pdf · uploaded 18 Feb 2025Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300054287 · Gokulam 1 Form 1 Arch Cert Q3 24-25.pdf · uploaded 19 Feb 2025Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300055634 · Gokulam 2 Form 1 Arch Cert Q3 24-25.pdf · uploaded 19 Feb 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300054287 · Gokulam 1_Arc Cert_Form1_Q4_24-25.pdf · uploaded 8 May 2025Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300054287 · Gokulam 1_Eng Cert_Form 2_Q4_24-25.pdf · uploaded 8 May 2025Source
  • Disclosure of sold/ booked inventoryP50300054287 · Gokulam 1_Sold Unsold Inventory_Q4_24-25.pdf · uploaded 8 May 2025Source
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P50300054287 · Gokulam 1_Quality Cert_Form 2A_Q4_24-25.pdf · uploaded 8 May 2025Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300055634 · Gokulam 2_Arc Cert_Form 2_Q4_24-25.pdf · uploaded 8 May 2025Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300055634 · Gokulam 2_Eng Cert_Form 2_Q4_24-25.pdf · uploaded 8 May 2025Source
  • Disclosure of sold/ booked inventoryP50300055634 · Gokulam 2_Sold Unsold Inventory_Q4_24-25.pdf · uploaded 8 May 2025Source
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P50300055634 · Gokulam 2_Quality Cert_Form 2A_Q4_24-25.pdf · uploaded 8 May 2025Source
  • Form 1P50300054287 · Gokulam 1_Form 1_310324.pdf · uploaded 5 Aug 2025View
  • Form 2P50300054287 · Gokulam 1_Form 2_310324.pdf · uploaded 5 Aug 2025View
  • Disclosure of Sold and Booked InventoryP50300054287 · Gokulam 1_Sold Unsold_310324.pdf · uploaded 5 Aug 2025Source
  • Form 1P50300054287 · GOKULAM_FORM 1_Q2.pdf · uploaded 5 Aug 2025Source
  • Form 1P50300054287 · Gokulam 1 Form 1 Arch Cert Q3 24-25.pdf · uploaded 5 Aug 2025Source
  • Form 2P50300054287 · GOKULAM_FORM 2_Q2.pdf · uploaded 5 Aug 2025Source
  • Form 2P50300054287 · Gokulam 1 Form 2 Eng Cert Q3 24-25.pdf · uploaded 5 Aug 2025Source
  • Disclosure of Sold and Booked InventoryP50300054287 · GOKULAM_SOLD_Q2.pdf · uploaded 5 Aug 2025Source
  • Disclosure of Sold and Booked InventoryP50300054287 · Gokulam 1 Sold Unsold Q3 24-25.pdf · uploaded 5 Aug 2025Source
  • Form 1P50300054287 · Gokulam 1_Arc Cert_Form1_Q4_24-25.pdf · uploaded 5 Aug 2025Source
  • Form 2P50300054287 · Gokulam 1_Eng Cert_Form 2_Q4_24-25.pdf · uploaded 5 Aug 2025Source
  • Disclosure of Sold and Booked InventoryP50300054287 · Gokulam 1_Sold Unsold Inventory_Q4_24-25.pdf · uploaded 5 Aug 2025Source
  • OthersP50300054287 · Gokulam 1_Quality Cert_Form 2A_Q4_24-25.pdf · uploaded 5 Aug 2025Source
  • Form 1P50300055634 · GOKULAM 2_FORM 1_SEP 24.pdf · uploaded 5 Aug 2025View
  • Form 2P50300055634 · GOKULAM 2_FORM 2_SEP 24.pdf · uploaded 5 Aug 2025Source
  • Disclosure of Sold and Booked InventoryP50300055634 · GOKULAM 2_SOLD_SEP 24.pdf · uploaded 5 Aug 2025Source
  • Form 1P50300055634 · Gokulam 2 Form 1 Arch Cert Q3 24-25.pdf · uploaded 5 Aug 2025View
  • Form 2P50300055634 · Gokulam 2 Form 2 Eng Cert Q3 24-25.pdf · uploaded 5 Aug 2025Source
  • Disclosure of Sold and Booked InventoryP50300055634 · Gokulam 2 Sold Unsold Q3 24-25.pdf · uploaded 5 Aug 2025Source
  • Form 1P50300055634 · Gokulam 2_Arc Cert_Form 2_Q4_24-25.pdf · uploaded 5 Aug 2025Source
  • Form 2P50300055634 · Gokulam 2_Eng Cert_Form 2_Q4_24-25.pdf · uploaded 5 Aug 2025Source
  • Disclosure of Sold and Booked InventoryP50300055634 · Gokulam 2_Sold Unsold Inventory_Q4_24-25.pdf · uploaded 5 Aug 2025Source
  • OthersP50300055634 · Gokulam 2_Quality Cert_Form 2A_Q4_24-25.pdf · uploaded 5 Aug 2025Source
  • Form 1P50300054287 · Form 1_300624.pdf · uploaded 6 Aug 2025Source
  • Form 2P50300054287 · Form 2_300624.pdf · uploaded 6 Aug 2025Source
  • Disclosure of Sold and Booked InventoryP50300054287 · Sold Unsold_300624.pdf · uploaded 6 Aug 2025Source
  • Form 1P50300055634 · Form 1_300624.pdf · uploaded 6 Aug 2025Source
  • Form 2P50300055634 · Form 2_300624.pdf · uploaded 6 Aug 2025Source
  • Disclosure of Sold and Booked InventoryP50300055634 · Sold Unsold_300624.pdf · uploaded 6 Aug 2025Source
  • Form 1P50300054287 · GOKULAM 1 Form 1 Arc Cerf_Q1 25-26.pdf · uploaded 25 Aug 2025Source
  • Form 2P50300054287 · GOKULAM 1 Form 2 Eng Cert_Q1 25-26.pdf · uploaded 25 Aug 2025Source
  • Disclosure of Sold and Booked InventoryP50300054287 · Gokulam 1_Sold unsold Inventory_Q1 25-26.pdf · uploaded 25 Aug 2025Source
  • Form 1P50300055634 · GOKULAM 2 Form 1 Arc Cerf_Q1 25-26.pdf · uploaded 25 Aug 2025Source
  • Form 2P50300055634 · GOKULAM 2 Form 2 Eng Cert_Q1 25-26.pdf · uploaded 25 Aug 2025Source
  • Disclosure of Sold and Booked InventoryP50300055634 · GOKULAM 2 Form 3 CA Cert_Q1 25-26.pdf · uploaded 25 Aug 2025Source
  • Form 1P50300054287 · GOKULAM 1 Form 1 Arc Cerf_Q2 25-26.pdf · uploaded 13 Nov 2025Source
  • Form 2P50300054287 · GOKULAM 1 Form 2 Eng Cert_Q2 25-26.pdf · uploaded 13 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP50300054287 · Gokulam 1_Sold unsold Inventory_Q2 25-26.pdf · uploaded 13 Nov 2025Source
  • Form 1P50300055634 · GOKULAM 2 Form 1 Arc Cerf_Q2 25-26.pdf · uploaded 13 Nov 2025Source
  • Form 2P50300055634 · GOKULAM 2 Form 2 Eng Cert_Q2 25-26.pdf · uploaded 13 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP50300055634 · Gokulam 2_Sold unsold Inventory_Q2 25-26.pdf · uploaded 13 Nov 2025Source

Promoter documents

  • Legal Title reportP50300054287 · Search RERA_ (1).pdf · uploaded 14 Nov 2023Source
  • Declaration Form BP50300054287 · Gokulam_Form B.pdf · uploaded 15 Nov 2023View
  • Legal Title reportP50300055634 · Gokulam 2_Title Search_Govinda Ganesha Infraspace.pdf · uploaded 14 Feb 2024Source
  • Declaration Form BP50300055634 · Gokulam 2_Format B.pdf · uploaded 27 Mar 2024Source

Technical documents

  • Layout ApprovalP50300054287 · Govinda_NA Order Land.pdfView
  • Layout ApprovalP50300054287 · NA_Part I.pdfView
  • Layout ApprovalP50300054287 · NA_Part II.pdfView
  • Layout ApprovalP50300054287 · NA_Part III.pdfView
  • Layout ApprovalP50300054287 · Hirapur 17 - Manoj Bhende _compressed.pdfView
  • Layout ApprovalP50300054287 · Gokulam_Layout Map Clear.pdfView
  • Layout ApprovalP50300054287 · Second Stamp Map.pdfView
  • Building Plan ApprovalP50300054287 · dsc 130 to 142-12.pdfView
  • Building Plan ApprovalP50300054287 · dsc 130 to 142-15.pdfView
  • Building Plan ApprovalP50300054287 · dsc 130 to 142-18.pdfView
  • Building Plan ApprovalP50300054287 · dsc 130 to 142-19.pdfView
  • Building Plan ApprovalP50300054287 · dsc 130 to 142-21.pdfView
  • Building Plan ApprovalP50300054287 · dsc 130 to 142-22.pdfView
  • Building Plan ApprovalP50300054287 · Final Draw DSC 130 to 142-16.pdfView
  • Building Plan ApprovalP50300054287 · Final Draw DSC 130 to 142-20.pdfView
  • Building Plan ApprovalP50300054287 · 145 To 157-2 Draw DSC.pdfView
  • Building Plan ApprovalP50300054287 · 145 To 157-6 Draw DSC.pdfView
  • Building Plan ApprovalP50300054287 · Fianl Draw DSC 145 To 157-1.pdfSource
  • Building Plan ApprovalP50300054287 · Fianl Draw DSC 145 To 157-3.pdfSource
  • Building Plan ApprovalP50300054287 · Final Draw DSC 145 To 157-4.pdfSource
  • Building Plan ApprovalP50300054287 · Final Draw DSC 145 TO 157-5.pdfSource
  • Building Plan ApprovalP50300054287 · 158 To 169-1.pdfSource
  • Building Plan ApprovalP50300054287 · 158 TO 169-6 Draw DSC.pdfSource
  • Building Plan ApprovalP50300054287 · Draw dsc 158 to 169-2.pdfSource
  • Building Plan ApprovalP50300054287 · Draw dsc 158 to 169-5.pdfSource
  • Building Plan ApprovalP50300054287 · Draw158 to 169-4.pdfSource
  • Building Plan ApprovalP50300054287 · Final Draw DSC 158 to 169-3.pdfSource
  • Layout ApprovalP50300055634 · Second Stamp Map (1).pdfView
  • Layout ApprovalP50300055634 · A SERIES.pdfView
  • Layout ApprovalP50300055634 · C SERIES.pdfView
  • Layout ApprovalP50300055634 · D SERIES.pdfView
  • Layout ApprovalP50300055634 · Govinda_NA Order Land.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-1-C22.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-2-C21.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-3-C20.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-4-C19.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-5-C18.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-6-C17.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-7-C16.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-8-C15.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-9-C14.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-10-C13.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-11-C12.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-13 C10.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-14 C9.pdfSource
  • Building Plan ApprovalP50300055634 · 130 to 142-17-C6.pdfSource
  • Building Plan ApprovalP50300055634 · 158 to 169-11-A11.pdfSource
  • Building Plan ApprovalP50300055634 · 158 to 169-12-A12.pdfSource
  • Building Plan ApprovalP50300055634 · 158 to 169-13-A13.pdfSource
  • Building Plan ApprovalP50300055634 · Draw 158 to 169-7 A7.pdfSource
  • Building Plan ApprovalP50300055634 · Draw 158 to 169-8 A8.pdfView
  • Building Plan ApprovalP50300055634 · Draw 158 to 169-9 A9.pdfView
  • Building Plan ApprovalP50300055634 · Draw 158 to 169-10 A10.pdfView
  • Building Plan ApprovalP50300055634 · 118 to 129-D2.pdfView
  • Building Plan ApprovalP50300055634 · 118 to 129-D3.pdfView
  • Building Plan ApprovalP50300055634 · 118 to 129-D4.pdfView
  • Building Plan ApprovalP50300055634 · 118 to 129-D14.pdfView
  • Building Plan ApprovalP50300055634 · 118 to 129-D16.pdfView
  • Building Plan ApprovalP50300055634 · 118 to 129-D17.pdfView
  • Building Plan ApprovalP50300055634 · 118 to 129-D18.pdfView
  • Building Plan ApprovalP50300055634 · Draw 118 to 129-1.pdfView
  • Building Plan ApprovalP50300055634 · Draw 118 to 129-5.pdfView
  • Building Plan ApprovalP50300055634 · Draw 118 to 129-6.pdfSource
  • Building Plan ApprovalP50300055634 · Draw 118 to 129-7.pdfSource
  • Building Plan ApprovalP50300055634 · Draw 118 to 129-8.pdfSource
  • Building Plan ApprovalP50300055634 · Draw 118 to 129-9.pdfSource
  • Building Plan ApprovalP50300055634 · Draw 118 to 129-10.pdfSource
  • Building Plan ApprovalP50300055634 · Draw 118 to 129-11.pdfSource
  • Building Plan ApprovalP50300055634 · Draw 118 to 129-12.pdfSource
  • Building Plan ApprovalP50300055634 · Draw 118 to 129-13.pdfSource
  • Building Plan ApprovalP50300055634 · Draw 118 to 129-15.pdfSource

Other legal documents

  • Other – LegalP50300054287 · Gokulam_Declaration.pdfView
  • Other – LegalP50300054287 · Gokulam_Mail.pdfView
  • Other – LegalP50300055634 · 118-123.pdfView
  • Other – LegalP50300055634 · 124-129.pdfView
  • Other – LegalP50300055634 · 130 to 157.pdfView
  • Other – LegalP50300055634 · 131-136.pdfView
  • Other – LegalP50300055634 · 137-142.pdfView
  • Other – LegalP50300055634 · 158-163.pdfView
  • Other – LegalP50300055634 · 164-169.pdfView
  • Other – LegalP50300055634 · Gokulam 2_Declaration.pdfView

Financial documents

  • Other – FinanceP50300054287 · Gokulam_Declaration.pdf · uploaded 9 Dec 2023View
  • Other – FinanceP50300054287 · Gokulam_Mail.pdf · uploaded 9 Dec 2023View
  • Other – FinanceP50300054287 · Gokulam_Declaration Area 020124.pdf · uploaded 2 Jan 2024Source
  • Other – FinanceP50300055634 · Gokulam 2_Declaration.pdf · uploaded 31 Jan 2024View

Proforma allotment letter

  • Proforma allotment letterP50300054287 · Gokulam_Allotment.pdfSource
  • Proforma allotment letterP50300055634 · Gokulam 2_Allotment.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Hirapur, Amravati taluka

Survey, CTS, gat or plot numbers

17/2 MOUJE HIRAPUR17/2 MOUJE HIRAPUR PRANGANE NANDGAONPETHSURVEY NO 17/1

As published on MahaRERA's project page

SURVEY NO 17/1 & 17/2 MOUJE HIRAPUR PRANGANE NANDGAONPETH

Boundaries

North
Layout Plot No 170
South
Open Space
East
Field Of Shri Patil
West
9 Mtr Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectShubham Mundhada—P50300054287
ArchitectShubham Mundhada—P50300055634
Chartered accountantCa Deepak S Zambani G A D And Associates—P50300054287
Chartered accountantCa Deepak Zambani G A D & Associates—P50300055634
EngineerPankaj Bajaj—P50300054287
EngineerPankaj Bajaj—P50300055634

Source: MahaRERA project page. Contact details are not shown.