Kansai, Thane
Deedo IDDL-THN-KANSAI7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects11
Registrations11
Completion still due74 past their date
Median extension4 months45% of registrations extended
Regulatory cases0none on MahaRERA's lists
7 in 10 registrations run late here
11 MahaRERA registrations in Kansai
3 not yet due4 extended, not yet due4 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Kansai
11 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shree VastuPA Developers | Due Sep 2028 | — | — |
| Kamlesh Co.Operative Housing Society Ltd.Kulvinder Infrastructure Private Limited | Due May 2029 | — | — |
| Vishwajeet VantageAbhijeet Empire | Due Jul 2030 | — | — |
| Shivam ResidencyAnnapurna Enterprises | Due Apr 2029, extended 4 mo | — | — |
| Janaki SadanShreeji Developers | Due Dec 2027, extended 4 mo | — | — |
| Chaitraban ChsAnnapurna Enterprises | Due Apr 2027, extended 4 mo | — | — |
| Shree GurukrupaShree Sarada Creations | Due Jan 2028, extended 4 mo | — | — |
| Ishwar Saraswati PalaceIshwar Reality | Completed, extended 1 yr | — | 12% |
| Indira Sadan Phase IPrakash Dnyandeo Wankhede | 2 yrs 6 mo late | — | — |
| Adwait GauravAdwait Realty | Completed | — | — |
| SpectrumKulin Enterprises | Completed | — | — |
Nearby: other villages in Ambarnath
Most active promoters
- Annapurna Enterprises2 projects
- Abhijeet Empire1 project
- Adwait Realty1 project
- Gulabrao Baburao Karanjule Patil1 project
- Ishwar Reality1 project
- Kulin Enterprises1 project
- Kulvinder Infrastructure Private Limited1 project
- PA Developers1 project
- Prakash Dnyandeo Wankhede1 project
- Shreeji Developers1 project
Kansai, in questions
How many projects in Kansai run late?
7 in 10 MahaRERA registrations (8 of 11): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Kansai by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology