Deedo IDDL-THN-BHAYANDAR8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects118
Registrations120some projects hold several
Completion still due6951 past their date
Median extension4 months46% of registrations extended
Regulatory cases2on 2 projects
8 in 10 registrations run late here
120 MahaRERA registrations in Bhayandar
22 not yet due47 extended, not yet due51 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Bhayandar
118 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Swastick MangalamShree Swastick Buildinfra LLP | Due Apr 2030, extended 4 mo | — | — |
| Benevolent MB HeightsBenevolent M.b Constructions Pvt Ltd | Due Apr 2028, extended 4 mo | — | — |
| Hiya AvenueVinod Lalchandji Mehta | Due Jul 2029, extended 4 mo | — | — |
| NARMADALIFESTYLE Building No.3Chirag Associates | Due Apr 2030, extended 4 mo | — | — |
| Savaliya SkyShree Giriraj Infra Developers | Due Apr 2030, extended 4 mo | — | — |
| Tirupati NamaahOm Shree Tirupati Balaji Builders | Due Apr 2031, extended 4 mo | — | 1% |
| Sheetal DharaJ. K. Associates | Due Dec 2026 | — | — |
| Vardhaman EnclaveVardhaman Builders | Due Apr 2027, extended 4 mo | — | — |
| ElanzaStonewall Buildcon LLP | Due Mar 2028 | — | 40% |
| Leena OasisLeena Constructions Private Limited | Due Apr 2030, extended 4 mo | — | — |
| Shree Krishna DhamSawariya Construction Co | Due Dec 2026, extended 2 yrs | — | — |
| Arihant TowerArihant Realty | Due Dec 2028 | — | — |
| Masaakin HatimiyahIndus Infratech | Due Jul 2029, extended 4 mo | — | 12% |
| Vasudev RatnaKrisha Builders | Due Apr 2028, extended 4 mo | — | 4% |
| Magic Om HeightsMagic Shanti Developer | Due Apr 2027, extended 4 mo | — | — |
| North Westend Tower 1JP Infra Realty Private Limited | Due Apr 2030, extended 4 mo | — | 7% |
| Panchvati ComplexNational Associates | Due Dec 2027 | — | 9% |
| Windermere Tower AA G Superstructures Private Limited | Due Apr 2029, extended 4 mo | — | 9% |
| Garden Court-D WingRitu Developers | Due Jul 2028, extended 4 mo | — | 3% |
| Lovedale ChslSushil Chothmal Varma | 2 yrs 8 mo late | — | 17% |
| Windermere Tower CA G Superstrcutures Pvt Ltd | Due Apr 2029, extended 4 mo | — | 1% |
| Windermere Tower BA G Superstructures Pvt Ltd | Due Apr 2029, extended 4 mo | — | 32% |
| Blue BellBrick Wall Homes LLP | 2 yrs 4 mo late | — | 83% |
| Salasar Kasturi GrandeurMaxus Lifespaces LLP | Due Apr 2031, extended 4 mo | — | — |
| Salasar Kasturi SolitaireSalasar Realtors LLP | Due Apr 2029, extended 4 mo | — | 39% |
Nearby: other villages in Thane
Thane (M Corp.) · 898 projectsNavi Mumbai (M Corp.) · 271 projectsMirabhayandar (M Corp.) · 225 projectsMira Bhayandar (M Corp.) · 106 projectsNaupada · 72 projectsPanchpakhadi · 65 projectsNerul · 58 projectsGhansoli · 57 projectsMajiwade · 43 projectsMumbra · 28 projectsOwale · 28 projectsVashi · 28 projects
Most active promoters
- Geeta Developers3 projects
- A G Superstructures Pvt Ltd2 projects
- Grandbuild Land Developers Llp2 projects
- Jp Infra Realty Private Limited2 projects
- Maxus Lifespaces Llp2 projects
- Salasar Estate Developers Llp2 projects
- Seven Eleven Construction Private Limited2 projects
- Shree Ostwal Builders Ltd2 projects
- Sunil Mangilal Jain2 projects
- A G Superstrcutures Pvt Ltd1 project
Bhayandar, in questions
How many projects in Bhayandar run late?
8 in 10 MahaRERA registrations (98 of 120): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhayandar by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology