Residential / Group Housing · 2 buildings · 87 unitsRERA P51700053615

Magic Om Heights

Deedo IDDP-THN-327V

Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.

Bhayandar, Thane 401101 · by Magic Shanti Developer

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 87 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 10 Nov 2023, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700053615
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005361510 Nov 202331 Dec 202630 Apr 2027Magic Shanti DeveloperProject page
Documents84

1 document held by Deedo, 83 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD-Magic Shanti Developer.pdf · uploaded 28 Aug 2023Source

Legal

  • Legal Title reportMAGIC SHANTI DEVELOPER SEARCH REPORT.pdf · uploaded 28 Aug 2023Source
  • Declaration Form BFORMB.pdf · uploaded 28 Aug 2023Source
  • Legal Title reportTitle Report-Magic Shanti_compressed.pdf · uploaded 27 Oct 2023Source

Migrated

  • 1 PAN CardPAN CARD-Magic Shanti Developer.pdf · uploaded 28 Aug 2023Source
  • 1 Copy of the legal title reportMAGIC SHANTI DEVELOPER SEARCH REPORT.pdf · uploaded 28 Aug 2023Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance.pdf · uploaded 28 Aug 2023Source
Show all 84 documentsShow fewer documents

Migrated

  • 2 a Details of encumbrances concerned to FinanceLegal Encumbrance.pdf · uploaded 28 Aug 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance.pdf · uploaded 28 Aug 2023Source
  • 2 b Details of encumbrances concerned to LegalLegal Encumbrance.pdf · uploaded 28 Aug 2023Source
  • 1 Copy of Layout Approval (in case of layout)lAYOUT-fINAL_.pdf · uploaded 28 Aug 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentBLDG PLAN 1-FINAL.pdf · uploaded 28 Aug 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentBLDG PLAN 2-FINAL.pdf · uploaded 28 Aug 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 28 Aug 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentPlinth Completion.pdf · uploaded 28 Aug 2023Source
  • 1 Declaration about Commencement CertificateCc Declaration.pdf · uploaded 28 Aug 2023Source
  • 1 Declaration in FORM BFORMB.pdf · uploaded 28 Aug 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_page-0001.pdf · uploaded 28 Aug 2023Source
  • 1 CERSAI detailsCersai Detail.pdf · uploaded 28 Aug 2023Source
  • 2 CERSAI detailsCERSAI_Search_Report_200278617775_For_Asset_Based_Search_28_08_2023_17_01_31_548.pdf · uploaded 28 Aug 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 28 Aug 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsMAGIC SHANTI ANNEXURE A VIKRAM SINGH.pdf · uploaded 28 Aug 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsMAGIC SHANTI ANNEXURE BHAUSAHEB KALE.pdf · uploaded 28 Aug 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsMAGIC SHANTI BRISHEN SINGH.pdf · uploaded 28 Aug 2023Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTREST-4.pdf · uploaded 28 Aug 2023Source
  • 1 Proforma of Agreement for saleRera Draft Agreement- Magic Shanti Developer.pdf · uploaded 28 Aug 2023Source
  • 1 Proforma of Allotment letterALLOTMENT.pdf · uploaded 28 Aug 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeperate Bank Declaration.pdf · uploaded 28 Aug 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation-Allotment.pdf · uploaded 28 Aug 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation-Agreement.pdf · uploaded 28 Aug 2023Source
  • 1 Other – TechnicalPlinth Completion.pdf · uploaded 28 Aug 2023Source
  • 2 Other – TechnicalSCREENSHOT.pdf · uploaded 17 Oct 2023Source
  • 2 Copy of the legal title reportTitle Report-Magic Shanti_compressed.pdf · uploaded 27 Oct 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 APRIL TO JUNE 24.pdf · uploaded 8 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 RAIGAON.pdf · uploaded 8 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 RAIGAON.pdf · uploaded 8 Oct 2024Source
  • 1 Disclosure of sold/ booked inventorysold unsold magic shnati develoeper.pdf · uploaded 8 Oct 2024Source
  • 1 Copy of Layout Approval (in case of layout)1710593515_MBMC-NEW.pdf · uploaded 12 Nov 2024Source
  • 1 Commencement Certificates / NA Order for plotted development141 CC NEW_11zon.pdf · uploaded 12 Nov 2024Source
  • 1 Building Plan Approval / NA Order for plotted development1710593515_MBMC-NEW.pdf · uploaded 12 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 RAIGAON.pdf · uploaded 12 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 RAIGAON.pdf · uploaded 12 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECH CERTIFICATE OCT TO DEC 24.pdf · uploaded 21 Jan 2025Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMATE A.pdf · uploaded 12 Mar 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)OM HEIGHTS RERA.pdf · uploaded 12 Mar 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)RAIGAON RERA LETTER.pdf · uploaded 25 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)JAN TO MARCH 25.pdf · uploaded 16 Apr 2025Source
  • Withdrawal Update Form 1Form 1_page-0001.pdf · uploaded 27 Dec 2025Source
  • Withdrawal Update Form 2FORM 2 RAIGAON.pdf · uploaded 27 Dec 2025Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 27 Dec 2025Source
  • Withdrawal Update Form 1Form 1_page-0001.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 1Form 1_page-0001.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 2FORM 2 RAIGAON.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 2FORM 2 RAIGAON.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 1FROM 1 Magic Om heights.pdf · uploaded 26 Jun 2026Source
  • Withdrawal Update Form 2Form 2 Magic Om heights.pdf · uploaded 26 Jun 2026Source
  • Withdrawal Update Form 3MAGIC SHANTI DEV FROM 3.pdf · uploaded 26 Jun 2026Source
  • Form 5 (FY 2023-2024)c485131d-22c9-48e4-b008-4463c6136026.pdf · uploaded 26 Jun 2026Source
  • Form 5 (FY 2024-2025)MAGIC SHANTI DEV FROM 5 24-25.pdf · uploaded 26 Jun 2026Source
  • Form 5 (FY 2025-2026)MAGIC SHANTI DEV FROM 5 25-26.pdf · uploaded 26 Jun 2026Source
  • Form 2A (FY 2023-2024)2023-24.pdf · uploaded 10 Aug 2026Source
  • Form 2A (FY 2024-2025)2024-25.pdf · uploaded 10 Aug 2026Source
  • Form 2A (FY 2025-2026)2025-26.pdf · uploaded 10 Aug 2026Source
  • Withdrawal Update Form 1ilovepdf_merged.pdf · uploaded 20 Aug 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 20 Aug 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 20 Aug 2026Source

Technical

  • DocumentlAYOUT-fINAL_.pdf · uploaded 28 Aug 2023Source
  • DocumentBLDG PLAN 1-FINAL.pdf · uploaded 28 Aug 2023Source
  • DocumentBLDG PLAN 2-FINAL.pdf · uploaded 28 Aug 2023Source
  • Other – TechnicalPlinth Completion.pdf · uploaded 28 Aug 2023Source
  • Other – TechnicalSCREENSHOT.pdf · uploaded 17 Oct 2023Source
  • Document1710593515_MBMC-NEW.pdf · uploaded 12 Nov 2024Source
  • Document1710593515_MBMC-NEW.pdf · uploaded 12 Nov 2024Source
  • Documentlayout plans.pdf · uploaded 30 Jul 2026Source
  • Documentlayout plans.pdf · uploaded 30 Jul 2026Source
  • OthersArea statement.pdf · uploaded 30 Jul 2026Source

Technical (Architect)

  • DocumentFORM 1 APRIL TO JUNE 24.pdf · uploaded 8 Oct 2024Source
  • DocumentARCHITECH CERTIFICATE OCT TO DEC 24.pdf · uploaded 21 Jan 2025Source
  • DocumentJAN TO MARCH 25.pdf · uploaded 16 Apr 2025Source
  • Documentilovepdf_merged.pdf · uploaded 20 Aug 2026Source

Technical (Engineer)

  • DocumentFORM 2.pdf · uploaded 20 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel HNO 4, HNO 6

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK87 units in all
Address
Old Sno 218, New Sno 2, Hno 4, Old Sno 219, New Sno 3, Hno 6, Old Sno 231, New Sno 12, Hno 7, Rai Village, BhayandarPIN 401101
Village
Mira-Bhayandar (M Corp.), Thane taluka
Land area for this project
4,040 sq m (43,486 sq ft)
Permissible built-up area
12,812 sq m (1,37,909 sq ft)
Sanctioned built-up area
10,475 sq m (1,12,755 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
28
Developed in phases
Yes

Survey, CTS, gat or plot numbers

HNO 4HNO 6HNO 7NEW SNO 12NEW SNO 2NEW SNO 3OLD SNO 218OLD SNO 219OLD SNO 231

Land as published on MahaRERA's project page

OLD SNO 218, NEW SNO 2, HNO 4, OLD SNO 219, NEW SNO 3, HNO 6, OLD SNO 231, NEW SNO 12, HNO 7

Boundaries

North
Exisiting Road
South
Old Sno 219 Hno 4
East
Old Sno 231 Hno 6
West
Old Sno 220 Hno 4

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking87 units

0 of 87 units booked (0%), as the promoter reported to MahaRERA

1BHK · 87 units
TypeCarpet areaUnitsBooked
1BHK23.69 sq m · 255 sq ft10
1BHK23.94 sq m · 258 sq ft10
1BHK25.12 sq m · 270 sq ft10
1BHK32.88 sq m · 354 sq ft80
1BHK32.97 sq m · 355 sq ft70
1BHK33.49 sq m · 360 sq ft70
1BHK33.53 sq m · 361 sq ft80
1BHK33.74 sq m · 363 sq ft80
Show all 13 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1BHK34.3 sq m · 369 sq ft150
1BHK34.37 sq m · 370 sq ft80
1BHK34.6 sq m · 372 sq ft80
1BHK34.94 sq m · 376 sq ft70
1BHK44.66 sq m · 481 sq ft80

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectBac Plannefrs & Engineers—
Chartered accountantR D Lukad—
EngineerBac Planner Architect & Engineers—
EngineerDaya Shankar Singh—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Bhayandar

All 118 projects in Bhayandar · Compare Magic Om Heights with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology