Residential / Group Housing · 1 building · 269 unitsRERA P51700050737

Windermere Tower B

Deedo IDDP-THN-GEWR

Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 32% of its units are booked.

Bhayandar, Thane 401101 · by A G Superstructures Pvt Ltd

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales32% booked86 of 269 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 28 Apr 2023, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700050737
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005073728 Apr 202331 Dec 202830 Apr 2029A G Superstructures Pvt LtdProject page
Documents149

1 document held by Deedo, 148 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardAGS - PAN Card.pdf · uploaded 22 Feb 2023Source

Legal

  • Legal Title reportTitle Certificate - RERA.pdf · uploaded 22 Feb 2023Source
  • Legal Title reportTitle Certiciate - RERA Format A.pdf · uploaded 22 Feb 2023Source
  • Legal Title reportTitile Certifictae.pdf · uploaded 22 Feb 2023Source
  • Declaration Form BDeclaration _Form B.pdf · uploaded 22 Feb 2023Source
  • Otherspan card.pdf · uploaded 21 Aug 2025Source

Migrated

  • 1 PAN CardAGS - PAN Card.pdf · uploaded 22 Feb 2023Source
Show all 149 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportTitle Certificate - RERA.pdf · uploaded 22 Feb 2023Source
  • 2 Copy of the legal title reportTitle Certiciate - RERA Format A.pdf · uploaded 22 Feb 2023Source
  • 3 Copy of the legal title reportTitile Certifictae.pdf · uploaded 22 Feb 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC 041122.pdf · uploaded 22 Feb 2023Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 22 Feb 2023Source
  • 1 Declaration in FORM BDeclaration _Form B.pdf · uploaded 22 Feb 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 22 Feb 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Certificate.pdf · uploaded 22 Feb 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAV_Disclosure of interest.pdf · uploaded 22 Feb 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsSL_Disclosure of interest.pdf · uploaded 22 Feb 2023Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 22 Feb 2023Source
  • 2 Proforma of Allotment letterAllotment_AnnexA.pdf · uploaded 22 Feb 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 22 Feb 2023Source
  • 1 CERSAI detailsCERSAI REPORTS.pdf · uploaded 25 Feb 2023Source
  • 1 a Details of encumbrances concerned to FinanceNo Encumbrance Cert_revised.pdf · uploaded 9 Mar 2023Source
  • 1 b Details of encumbrances concerned to LegalNo Encumbrance Cert_revised.pdf · uploaded 9 Mar 2023Source
  • 1 Proforma of Agreement for saleAgreement for Sale_Tower B_Revised.pdf · uploaded 9 Mar 2023Source
  • 1 Deviation Report with respect to Allotment letterNo Deviation of Allotment let_revised.pdf · uploaded 9 Mar 2023Source
  • 1 Deviation Report with respect to model copy of AgreementNo Deviation of Allotment let_revised.pdf · uploaded 9 Mar 2023Source
  • 2 CERSAI detailsCersai Report_Revised.pdf · uploaded 13 Mar 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate _Revised.pdf · uploaded 14 Mar 2023Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Cert _Revised.pdf · uploaded 17 Mar 2023Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Cert _Revised.pdf · uploaded 17 Mar 2023Source
  • 1 Copy of Layout Approval (in case of layout)Layout plan Revised.pdf · uploaded 17 Mar 2023Source
  • 1 Building Plan Approval / NA Order for plotted development14.pdf · uploaded 17 Mar 2023Source
  • 2 Deviation Report with respect to model copy of AgreementNo Deviation on Agmt_revised.pdf · uploaded 17 Mar 2023Source
  • 1 Other – TechnicalBreakup of BUA.pdf · uploaded 17 Mar 2023Source
  • 2 Other – TechnicalProject details.pdf · uploaded 17 Mar 2023Source
  • 2 Building Plan Approval / NA Order for plotted development10.pdf · uploaded 5 Apr 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentGetUserDocumentFileContent (6).pdf · uploaded 5 Apr 2023Source
  • 4 Building Plan Approval / NA Order for plotted developmentRERA reply_TowerB.pdf · uploaded 5 Apr 2023Source
  • 5 Building Plan Approval / NA Order for plotted developmentGetUserDocumentFileContent (8).pdf · uploaded 5 Apr 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Cert.pdf · uploaded 26 Sep 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Cert.pdf · uploaded 26 Sep 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 30-06-23.pdf · uploaded 26 Sep 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Tower B_Arch Cert.pdf · uploaded 12 Oct 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Tower B_Eng Cert.pdf · uploaded 12 Oct 2023Source
  • 1 Disclosure of sold/ booked inventoryTower B_Inventory.pdf · uploaded 12 Oct 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Tower B_CA Cert.pdf · uploaded 12 Oct 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Tower B.pdf · uploaded 9 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Tower B.pdf · uploaded 9 Jan 2024Source
  • 2 Disclosure of sold/ booked inventoryTower B.pdf · uploaded 9 Jan 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Tower B.pdf · uploaded 15 Jan 2024Source
  • 2 Copy of Layout Approval (in case of layout)SHEET 1.pdf · uploaded 2 Apr 2024Source
  • 3 Copy of Layout Approval (in case of layout)SHEET 9.pdf · uploaded 2 Apr 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentSHEET 9.pdf · uploaded 2 Apr 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC- 33 Floors - 31 01 2024_compressed.pdf · uploaded 2 Apr 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Cert_Tower B.pdf · uploaded 18 Apr 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate.pdf · uploaded 18 Apr 2024Source
  • 3 Disclosure of sold/ booked inventoryTower B_Sold Unsold.pdf · uploaded 18 Apr 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_AGS.pdf · uploaded 18 Apr 2024Source
  • 3 Other – TechnicalCorrection Letter.pdf · uploaded 26 Apr 2024Source
  • 4 Other – TechnicalLetter of Intent from MBMC.pdf · uploaded 26 Apr 2024Source
  • 5 Other – TechnicalCommencement Certificates.pdf · uploaded 26 Apr 2024Source
  • 6 Other – TechnicalFormat D.pdf · uploaded 26 Apr 2024Source
  • 7 Other – TechnicalB702 Agreement.pdf · uploaded 26 Apr 2024Source
  • 8 Other – TechnicalB1006 Agreement.pdf · uploaded 26 Apr 2024Source
  • 9 Other – TechnicalB1101 Agreement.pdf · uploaded 26 Apr 2024Source
  • 10 Other – TechnicalB1105 Agreement.pdf · uploaded 26 Apr 2024Source
  • 11 Other – TechnicalB1706 Agreement.pdf · uploaded 26 Apr 2024Source
  • 12 Other – TechnicalPlan.pdf · uploaded 26 Apr 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 23-24.pdf · uploaded 31 May 2024Source
  • 2 Declaration about Commencement CertificateFormat D_Revised.pdf · uploaded 14 Jun 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cert_Tower B.pdf · uploaded 19 Jul 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Cert_Tower B.pdf · uploaded 19 Jul 2024Source
  • 4 Disclosure of sold/ booked inventoryTower B_Sold Unsold.pdf · uploaded 19 Jul 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A Certificate_Towr B.pdf · uploaded 19 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 March 2024.pdf · uploaded 10 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cert Tower B.pdf · uploaded 19 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA cert_B.pdf · uploaded 19 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 19 Oct 2024Source
  • 2 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 19 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cert.pdf · uploaded 18 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA cert_B.pdf · uploaded 18 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Certificate.pdf · uploaded 18 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorysold_unsold_Tower B.pdf · uploaded 18 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cert_Tower B.pdf · uploaded 16 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Cert_B.pdf · uploaded 16 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate - Tower B.pdf · uploaded 16 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySold_Unsold_B.pdf · uploaded 16 Apr 2025Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance_B.pdf · uploaded 23 Apr 2025Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance_B.pdf · uploaded 23 Apr 2025Source
  • 3 a Details of encumbrances concerned to FinanceEncumbrance_C.pdf · uploaded 23 Apr 2025Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance_B.pdf · uploaded 23 Apr 2025Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance_B.pdf · uploaded 23 Apr 2025Source
  • 3 b Details of encumbrances concerned to LegalEncumbrance_C.pdf · uploaded 23 Apr 2025Source
  • Form 1Architect Cert_B.pdf · uploaded 17 Jul 2025Source
  • Form 2Engg Cert Tower B.pdf · uploaded 17 Jul 2025Source
  • Form 3CA cert_B.pdf · uploaded 17 Jul 2025Source
  • Disclosure of Sold and Booked InventorySold_Unsold_B.pdf · uploaded 17 Jul 2025Source
  • Form 5 (FY 2023-2024)Form 5 March 2024.pdf · uploaded 25 Sep 2025Source
  • Form 5 (FY 2024-2025)Tower B Form 5 FY 2024-25.pdf · uploaded 3 Oct 2025Source
  • Withdrawal Update Form 1Architect Certificate - Tower B.pdf · uploaded 15 Oct 2025Source
  • Withdrawal Update Form 2Engineer Certificate - Tower B.pdf · uploaded 15 Oct 2025Source
  • Withdrawal Update Form 3CA Certificate - Tower B.pdf · uploaded 15 Oct 2025Source
  • Withdrawal Update Form 1Architect Certificate - Tower B.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 1Architect Certificate - Tower B.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 2Engineer Certificate - Tower B.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 2Engineer Certificate - Tower B.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 3CA Certificate - Tower B.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 3CA Certificate - Tower B.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 1Architect Cert_Tower B.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 2Engineer Certificate_Tower B.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 3CA Certificate - Tower B.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 1WM Arch Cert_Tower B.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2Eng Cert_Tower B.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3CA Certificate_Tower B.pdf · uploaded 20 Apr 2026Source
  • Form 2A (FY 2025-2026)Form 2A_Windermere_Tower B.pdf · uploaded 25 Jun 2026Source
  • Withdrawal Update Form 1Architect Certificate Tower B.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2Engineer Cert_Tower B.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3CA Cert_ Tower B.pdf · uploaded 20 Jul 2026Source
  • Form 5 (FY 2025-2026)WM_Tower B_Form_5_FY_25-26.pdf · uploaded 28 Sep 2026Source

Technical

  • DocumentLayout plan Revised.pdf · uploaded 17 Mar 2023Source
  • Document14.pdf · uploaded 17 Mar 2023Source
  • Other – TechnicalBreakup of BUA.pdf · uploaded 17 Mar 2023Source
  • Other – TechnicalProject details.pdf · uploaded 17 Mar 2023Source
  • DocumentRERA reply_TowerB.pdf · uploaded 5 Apr 2023Source
  • DocumentGetUserDocumentFileContent (8).pdf · uploaded 5 Apr 2023Source
  • Document10.pdf · uploaded 5 Apr 2023Source
  • DocumentGetUserDocumentFileContent (6).pdf · uploaded 5 Apr 2023Source
  • DocumentSHEET 1.pdf · uploaded 2 Apr 2024Source
  • DocumentSHEET 9.pdf · uploaded 2 Apr 2024Source
  • DocumentSHEET 9.pdf · uploaded 2 Apr 2024Source
  • Other – TechnicalCorrection Letter.pdf · uploaded 26 Apr 2024Source
  • Other – TechnicalLetter of Intent from MBMC.pdf · uploaded 26 Apr 2024Source
  • Other – TechnicalCommencement Certificates.pdf · uploaded 26 Apr 2024Source
  • Other – TechnicalFormat D.pdf · uploaded 26 Apr 2024Source
  • Other – TechnicalB702 Agreement.pdf · uploaded 26 Apr 2024Source
  • Other – TechnicalB1006 Agreement.pdf · uploaded 26 Apr 2024Source
  • Other – TechnicalB1101 Agreement.pdf · uploaded 26 Apr 2024Source
  • Other – TechnicalB1105 Agreement.pdf · uploaded 26 Apr 2024Source
  • Other – TechnicalB1706 Agreement.pdf · uploaded 26 Apr 2024Source
  • Other – TechnicalPlan.pdf · uploaded 26 Apr 2024Source

Technical (Architect)

  • DocumentArch Cert Tower B.pdf · uploaded 19 Oct 2024Source
  • DocumentArch Cert.pdf · uploaded 18 Jan 2025Source
  • DocumentArch Cert_Tower B.pdf · uploaded 16 Apr 2025Source
  • DocumentArchitect Certificate Tower B.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • DocumentEngineer Certificate.pdf · uploaded 19 Oct 2024Source
  • DocumentEng Certificate.pdf · uploaded 18 Jan 2025Source
  • DocumentEngineers Certificate - Tower B.pdf · uploaded 16 Apr 2025Source
  • DocumentEngineer Cert_Tower B.pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop269 units in all
Address
New S.no./Old S.no./H.no. 221/564/1, 3, 4a, 4b, 8, New S.no/Olds.no./H.no/220/565/1/4, 6, 7, 8, 9, 10.new S.no/Olds.no/H.no/267/567/1, 2/1new S.no/Olds.no/245/579/1a, 1b, 2, 3a3b, 3c, 4, 5, 6, 7, 8.news.no/Old/S.no/H.no.222/580/1, 2, 6, Near Platina Complex, Bhayander WestPIN 401101
Village
Bhayandar, Thane taluka
Land area for this project
2,858 sq m (30,764 sq ft)
Permissible built-up area
24,346 sq m (2,62,058 sq ft)
Sanctioned built-up area
24,346 sq m (2,62,058 sq ft)
Recreational open space
1,196 sq m (12,868 sq ft)
Designated bank account
85
Developed in phases
No

Land as published on MahaRERA's project page

NEW S.NO./OLD S.NO./H.NO. 221/564/1,3,4A,4B,8,NEW S.NO/OLDS.NO./H.NO/220/565/1/4,6,7,8,9,10.NEW S.NO/OLDS.NO/H.NO/267/567/1,2/1NEW S.NO/OLDS.NO/245/579/1A,1B,2,3A3B,3C,4,5,6,7,8.NEWS.NO/OLD/S.NO/H.NO.222/580/1,2,6

Boundaries

North
Plot No 266
South
18 M Road
East
Plot No 220
West
Plot No 244

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking269 units

86 of 269 units booked (32%), as the promoter reported to MahaRERA

1BHK · 59 units2BHK · 198 unitsShop · 12 units
TypeCarpet areaUnitsBooked
1BHK44.55 sq m · 480 sq ft5921
2BHK60.71 sq m · 653 sq ft6622
2BHK60.8 sq m · 654 sq ft6628
2BHK62.56 sq m · 673 sq ft6611
Shop65.2 sq m · 702 sq ft62
Shop98.28 sq m · 1,058 sq ft11
Shop122.4 sq m · 1,318 sq ft11
Shop122.72 sq m · 1,321 sq ft20
Shop164.04 sq m · 1,766 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRujuta Mody—
Chartered accountantArchana Parikh—
EngineerSachin Shirke—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Bhayandar

All 118 projects in Bhayandar · Compare Windermere Tower B with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology