Deedo IDDL-SOL-SOLAPUR8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects547in 37 localities
Registrations557some projects hold several
Completion still due166330 past their date
Median extension4 months36% of registrations extended
Regulatory cases30on 30 projects
8 in 10 registrations run late here
557 MahaRERA registrations in Solapur and the places within it
43 not yet due123 extended, not yet due330 past even the latest date61 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Solapur
547 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Saryash ApartmentSaryash Constructions | Completed | — | 50% |
| Vinayak SquareShri Vinayak Consstructions | 2 yrs 11 mo late | — | — |
| Smrutigandha ApartmentSunil Uttamrao Furde | Completed | — | 0% |
| Hari Har ResidencyShri Swami Samarth Construciton | Completed | — | — |
| Jv SquareJay Group | Completed | — | — |
| Vijayraj ManorAmar Kalyani Birajdar | Completed | — | 100% |
| Arihant ComplexAdya Constructions | Completed | — | — |
| Vanga ApartmentSadanand Sommayya Vanga | 7 yrs 11 mo late | — | — |
| Royal ResidencyShubhankar Developers | Completed | — | 71% |
| Sarathi Estatevikas popatrao savant | 8 yrs 5 mo late | — | — |
| Shivsmruti ResidencyBhairavnath Developers | 5 yrs 4 mo late | — | — |
| Lokhandwala PrestigeLokhandwala Builders | Completed | — | — |
| GrishmaShri Mauli Buildcon | Completed | — | — |
| Degaonkar ApartmentPrasad Prakash Degaonkar | Completed | — | 36% |
| Sai ParadiseSunrise Developers | 5 yrs 11 mo late | — | — |
| Heritage PalmsManoj Kantilal Shah | Completed | — | — |
| Siddhivinayak HightsSai Developers | Completed | — | 35% |
| Ambal TowerArchana Dayanand Ambal | Completed | — | 59% |
| Saee ResidencyM S Constructions | 7 yrs 8 mo late | — | 75% |
| Narhar ComplexYamuna Developers | Completed | — | — |
| Shree Varad ResidencyMr. Gurbasappa Mallappa Shetty & Smt. Ambavaa Mallappa Shetty | Completed, extended 1 yr | — | — |
| Shindeshahi PhaseIITirupati Construction Promoters & Developers | Completed | — | 62% |
| Picaka GalaxySwapnil Suhas Raut | 3 yrs 11 mo late | — | 55% |
| S. S. Icon - Phase IS S Infrastructure | Completed | — | 53% |
| Anandam Vihar Phase I WING ASv Smart City Developers | Completed, extended 1 yr 3 mo | — | 66% |
Localities in Solapur
- Solapur (M Corp.)303 projects
- Solapur North37 projects
- Pandharpur32 projects
- Majrewadi30 projects
- Barshi26 projects
- Isbavi24 projects
- Barshi8 projects
- Tembhurni7 projects
- Karmala (Rural)6 projects
- Sangole (M Cl)6 projects
- Wakhari5 projects
- Pandharpur4 projects
Other districts
Most active promoters
- Dhariwal And Chhoriya Buildcon Pvt Ltd7 projects
- Devendra Vasudeo Sangolkar6 projects
- Mohsin Haroon Shaikh6 projects
- Dhariwal And Chhoriya Buildcon Pvt Ltd5 projects
- Squareone Builders & Developers5 projects
- Tirupati Construction Promoters & Developers5 projects
- Ayyub Usman Motiwala4 projects
- Hanmantu Komarayya Bura4 projects
- Image Space Incorporated4 projects
- Pandhe Infracons Pvt Ltd4 projects
Solapur, in questions
How many projects in Solapur run late?
8 in 10 MahaRERA registrations (453 of 557): their completion date was extended or has passed, data through 2 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Solapur by Deedo. Medians on fewer than 3 deeds are not shown.
Data through2 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology