8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects547in 37 localities
Registrations557some projects hold several
Completion still due166330 past their date
Median extension4 months36% of registrations extended
Regulatory cases30on 30 projects

8 in 10 registrations run late here

557 MahaRERA registrations in Solapur and the places within it

43 not yet due123 extended, not yet due330 past even the latest date61 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Solapur

547 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Manjul PlazaAslam Babalal MujawarDue Dec 2026——
Vardhaman ResidencyAmar Kalyani BirajdarCompleted—100%
Kamtam Icon A WingPrakash Shankar Kamtam8 yrs 8 mo late—75%
F.f AmoraF F City Tower DevelopersDue Oct 2027, extended 4 mo—100%
Vijayraj MarvelAruna Amar BirajdarCompleted—100%
SunshreeSantosh Nagesh SurwaseCompleted——
Pioneer Icon Wing APioneer Promoters And DevelopersCompleted—64%
Shree Vishwa ResidencyKishor Rajendra SanjekarCompleted——
Shree Shambhavi ResidencyRSDevelopersCompleted——
Pawan ResidencyVyankateshwara DevelopersCompleted—78%
Shree HeritageHemant Damu PingaleCompleted, extended 1 yr 2 mo—40%
Shri Pawan ApartmentShriniwas Hanmantu YangantiCompleted—17%
505 Bahava Row Houses, Open PlotsPandhe Infracons Pvt Ltd7 yrs 4 mo late—100%
Ananta SolapurPropwizz Infra LLPDue Mar 2029, extended 9 yrs 3 mo—31%
G N NagarNazir Nadaf Hamid Nadaf Ibrahim Nadaf3 yrs 8 mo late——
Iris ResidencyRathi InfraconCompleted——
Manomay ViharSukhakarta RealityCompleted——
Satya Shanti ViharAnwarhusen Mahamud ShaikhCompleted, extended 1 yr 4 mo——
Sayali HeightsRahul DevelopersCompleted—32%
Swapna PushpaPushpam Infra LLPCompleted, extended 3 yrs 6 mo——
Vasant Vihar Phase IIIPandhe Infracons Pvt Ltd7 yrs 4 mo late—93%
Kurdu Plotting on Gat No 264Pragati Infra Services Pvt. Ltd.Completed, extended 2 yrs——
Rushi CelebrationMeghasham Mallikarjun YemulCompleted—5%
Crystal TowerAsif Sattar PathanCompleted—45%
522Pandhe Infracons Pvt Ltd3 yrs 3 mo late——
Solapur market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Dhariwal And Chhoriya Buildcon Pvt Ltd7 projects
  2. Devendra Vasudeo Sangolkar6 projects
  3. Mohsin Haroon Shaikh6 projects
  4. Dhariwal And Chhoriya Buildcon Pvt Ltd5 projects
  5. Squareone Builders & Developers5 projects
  6. Tirupati Construction Promoters & Developers5 projects
  7. Ayyub Usman Motiwala4 projects
  8. Hanmantu Komarayya Bura4 projects
  9. Image Space Incorporated4 projects
  10. Pandhe Infracons Pvt Ltd4 projects

Solapur, in questions

How many projects in Solapur run late?

8 in 10 MahaRERA registrations (453 of 557): their completion date was extended or has passed, data through 2 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Solapur by Deedo. Medians on fewer than 3 deeds are not shown.

Data through2 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology