Phaltan, Satara
Deedo IDDL-SAT-PHALTAN9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects141
Registrations144some projects hold several
Completion still due3897 past their date
Median extension4 months27% of registrations extended
Regulatory cases2on 2 projects
9 in 10 registrations run late here
144 MahaRERA registrations in Phaltan and the places within it
10 not yet due28 extended, not yet due97 past even the latest date9 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Phaltan
141 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Swara TowerSwara Buildcon | Completed | — | 24% |
| Shrinidhi HeightsNiraga Constructions Proprietor Yuvraj Suhas Nikam | Due Apr 2029, extended 4 mo | — | — |
| Prestige PridePrestige Properties | 11 mo late | — | — |
| GokulnagariKrishna Buildcon | Completed | — | 22% |
| Raigad ParkSairam Associates | Due Mar 2028, extended 4 mo | — | — |
| Sai HeightR K Developers | 11 mo late | — | — |
| Tara ResidencyNaik Nimbalkar Infra | Completed | — | 90% |
| Krushnakunj PrideParmeshwar Shamrao Bobade | 1 yr 11 mo late | — | — |
| Vedant ParadiseUnique Construction | 11 mo late | — | — |
| ShubhankarAshish Ramakant Gadkari | Completed | — | 13% |
| Sunshine Landmark Phase IIPSK Group | 1 yr 7 mo late | — | — |
| J.k.classicJ K Associates | Completed | — | 40% |
| Venkatesh ClassicVenkatesh Promoters And Builders | Completed | — | 17% |
| Pruthvi PrimePruthvi Infra | Completed | — | 6% |
| Venkatesh HeritageVenkatesh Promoters And Builders | Completed | — | — |
| City View HeightsShri Ganesh Constructions | 1 yr 8 mo late | — | 28% |
| Mayuresh HeightsShri Balaji Developers | Completed | — | 100% |
| GokuldhamGokuldham | Due Apr 2028, extended 4 mo | — | — |
| Sai TowersAnandrao Haribhau Kalukhe | 1 yr 5 mo late | — | — |
| Swara ParkSwara Construction | Completed | — | 100% |
| Shrikrishna ParkAK Developers | 1 yr 6 mo late | — | — |
| Chandrabhaga PrimeR K Developers | 2 yrs 11 mo late | — | — |
| Pushp ResidencyPushpam Developers | Completed | — | — |
| Kriti ShilpKriti Properties | 2 yrs 8 mo late | — | — |
| Nd VillaNd Developers | Completed | — | — |
Nearby: other talukas in Satara
Most active promoters
- Venkatesh Promoters And Builders7 projects
- Swara Construction5 projects
- Pruthvi Infra3 projects
- Ram Group3 projects
- Shreeram Promoters And Developers3 projects
- Shri Balaji Developers3 projects
- Swara Builders & Devlopers3 projects
- Unique Construction3 projects
- Unity Developers3 projects
- Agastya Properties2 projects
Phaltan, in questions
How many projects in Phaltan run late?
9 in 10 MahaRERA registrations (125 of 144): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Phaltan by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology