Sai Towers
Deedo IDDP-SAT-RZC5Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Kolki (Ct), Satara 415523 · by Anandrao Haribhau Kalukhe
Buying a flat here?
See every deed registered on it.
Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 3 Oct 2022, completion promised 30 Jun 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52700047097
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52700047097 | 3 Oct 2022 | 30 Jun 2025 | 30 Jun 2025 | Anandrao Haribhau Kalukhe | Project page |
Documents38
1 document held by Deedo, 37 filings listed on MahaRERA's project page
Finance
- PAN CardPAN.pdf · uploaded 13 Jul 2022Source
Legal
Migrated
- 1 PAN CardPAN.pdf · uploaded 13 Jul 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentApproved Layout and Building Plan.pdf · uploaded 15 Jul 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCONSTRUCTION START CERTIFICATE_compressed.pdf · uploaded 15 Jul 2022Source
- 1 Declaration about Commencement CertificateCONSTRUCTION START CERTIFICATE_compressed.pdf · uploaded 15 Jul 2022Source
Show all 38 documentsShow fewer documents
Migrated
- 1 Declaration in FORM BFORM B.pdf · uploaded 17 Jul 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FINAL FORM 3-1_compressed.pdf · uploaded 21 Jul 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FINAL FORM 3-2_compressed.pdf · uploaded 21 Jul 2022Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FINAL FORM 3-3.pdf · uploaded 21 Jul 2022Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FINAL FORM 3-4_compressed.pdf · uploaded 21 Jul 2022Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FINAL FORM 3-5_compressed.pdf · uploaded 21 Jul 2022Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FINAL FORM 3-6_compressed.pdf · uploaded 21 Jul 2022Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)FINAL FORM 3-7.pdf · uploaded 21 Jul 2022Source
- 1 Copy of the legal title reportLegal Title Report in Format.pdf · uploaded 8 Aug 2022Source
- 1 CERSAI detailsSelf-declaration regarding the status of encumbrance on promoter letter head.pdf · uploaded 18 Aug 2022Source
- 1 Copy of Layout Approval (in case of layout)Approved Layout and Building Plan.pdf · uploaded 22 Aug 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentBuilt Up Area.pdf · uploaded 22 Aug 2022Source
- 3 Building Plan Approval / NA Order for plotted developmentFloor Plan 1,2,3 18-Jul-2022.pdf · uploaded 22 Aug 2022Source
- 1 Proforma of Allotment letterSAI Towers AFS.pdf · uploaded 22 Aug 2022Source
- 2 Proforma of Allotment letterAL.pdf · uploaded 22 Aug 2022Source
- 1 a Details of encumbrances concerned to Financeडिक्लेरेशन , 06,09,2022.pdf · uploaded 9 Sep 2022Source
- 1 b Details of encumbrances concerned to Legallitigation Declaration .pdf · uploaded 15 Sep 2022Source
- 1 Deviation Report with respect to Allotment letterDeviation AL.pdf · uploaded 16 Sep 2022Source
- 1 Deviation Report with respect to model copy of AgreementAFS Deviation.pdf · uploaded 16 Sep 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameRera Bank Ac declaration.pdf · uploaded 17 Sep 2022Source
- 1 Proforma of Agreement for saleAFS.pdf · uploaded 6 Feb 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 14 Feb 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 13 Mar 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATES_compressed.pdf · uploaded 13 Mar 2023Source
Technical
Technical (Architect)
- DocumentFORM 1.pdf · uploaded 13 Mar 2023Source
Technical (Engineer)
- DocumentENGINEER CERTIFICATES_compressed.pdf · uploaded 13 Mar 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 119/2/B, Plot No 21
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK1 unit in all
- Address
- 119/2/B, Plot No 21, Grampanchayat Road, near Anganwadi SchoolPIN 415523
- Village
- Kolki (CT), Phaltan taluka
- Land area for this project
- 419 sq m (4,510 sq ft)
- Permissible built-up area
- 1,518 sq m (16,341 sq ft)
- Sanctioned built-up area
- 759 sq m (8,171 sq ft)
- Designated bank account
- 35
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
119/2/B, Plot No 21
Boundaries
- North
- Anganwadi School Kolaki
- South
- Plot No 20 Firoz Husen Mahat
- East
- Plot No 77
- West
- Internal Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking1 unit
0 of 1 unit booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 571.38 sq m · 6,150 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | V C Godse | — |
| Chartered accountant | M S Chandan Udhani & COMPANY | — |
| Engineer | Dhiraj Chavan & Associates | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Kolki (Ct)
- Lambodar ParkRERA PM1300002500614
- Vitthal PrideRERA P52700080645
- Nd ParkRERA P52700080349
- Trimurti HeightsRERA P52700080134
- Mayuresh ParkRERA P52700079780
- Ramsrushti ApartmentRERA P52700079213
- Govind ParkRERA P52700054856
- Kalpataru TowersRERA P52700054039
All 29 projects in Kolki (Ct) · Compare Sai Towers with another project