Ramsrushti Apartment
Deedo IDDP-SAT-YY1YCompletion was pushed back 4 months, to Mar 2030; no MahaRERA orders on record; 9% of its units are booked.
Kolki (Ct), Satara 415523 · by Ram Group, Jadhavwadi
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Mar 2030
- This projectRegistered 17 Feb 2025, completion promised 1 Nov 2029, revised to 1 Mar 2030.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
- Ramsrushti Apartment Wing A6 floors · 30 units0% booked
- Ramsrushti Apartment Wing B5 floors · 23 units22% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52700079213
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52700079213 | 17 Feb 2025 | 1 Nov 2029 | 1 Mar 2030 | M/S Ram Group, Jadhavwadi | Project page |
Documents81
1 document held by Deedo, 80 filings listed on MahaRERA's project page
Finance
Legal
- Other – LegalDeclaration Cum Undertaking.pdf · uploaded 31 Dec 2024Source
- Legal Title reportLegal Title Report.pdf · uploaded 31 Dec 2024Source
- Legal Title reportFlow of The Title of The Said Land.pdf · uploaded 31 Dec 2024Source
- Legal Title reportSearch And Title Report.pdf · uploaded 31 Dec 2024Source
Show all 81 documentsShow fewer documents
Legal
- Declaration Form BRam shrushti Form B.pdf · uploaded 31 Dec 2024Source
- Other – LegalLetter Of Authorization.pdf · uploaded 1 Jan 2025Source
- Other – LegalSale Deed 1.pdf · uploaded 1 Jan 2025Source
- Other – LegalSale Deed 2.pdf · uploaded 1 Jan 2025Source
- Other – LegalMortgage Deed.pdf · uploaded 1 Jan 2025Source
Migrated
- 2 PAN CardPAN CARD.pdf · uploaded 31 Dec 2024Source
- 2 Copy of the legal title reportFlow of The Title of The Said Land.pdf · uploaded 31 Dec 2024Source
- 3 Copy of the legal title reportSearch And Title Report.pdf · uploaded 31 Dec 2024Source
- 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 31 Dec 2024Source
- 1 Copy of Layout Approval (in case of layout)Lay Out.pdf · uploaded 31 Dec 2024Source
- 2 Copy of Layout Approval (in case of layout)Lay Out Final Approval.pdf · uploaded 31 Dec 2024Source
- 1 Proforma of Allotment letterAllotment.pdf · uploaded 31 Dec 2024Source
- 1 Declaration in FORM BRam shrushti Form B.pdf · uploaded 31 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 31 Dec 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 31 Dec 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 31 Dec 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentCC Mail.pdf · uploaded 31 Dec 2024Source
- 5 Other – LegalDeclaration Cum Undertaking.pdf · uploaded 31 Dec 2024Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 31 Dec 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A.pdf · uploaded 31 Dec 2024Source
- 1 Deviation Report with respect to Allotment letterDeviation Report for Allotment Letter.pdf · uploaded 31 Dec 2024Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report For Agreement.pdf · uploaded 31 Dec 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDislosure of Kapse.pdf · uploaded 31 Dec 2024Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDislosure of Zanjurne.pdf · uploaded 31 Dec 2024Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsDislosure of Bhoite.pdf · uploaded 31 Dec 2024Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsDislosure of Ingale.pdf · uploaded 31 Dec 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentPlan.pdf · uploaded 1 Jan 2025Source
- 4 Other – LegalMortgage Deed.pdf · uploaded 1 Jan 2025Source
- 3 Other – LegalSale Deed 2.pdf · uploaded 1 Jan 2025Source
- 1 Other – LegalLetter Of Authorization.pdf · uploaded 1 Jan 2025Source
- 2 Other – LegalSale Deed 1.pdf · uploaded 1 Jan 2025Source
- 1 Other – FinanceCA Certificate.pdf · uploaded 1 Jan 2025Source
- 1 a Details of encumbrances concerned to FinanceNo Encumbrances Finance.pdf · uploaded 13 Jan 2025Source
- 2 a Details of encumbrances concerned to FinanceNo Encumbrances Legal.pdf · uploaded 13 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 13 Jan 2025Source
- 1 CERSAI detailsNo Cersai.pdf · uploaded 13 Jan 2025Source
- 1 b Details of encumbrances concerned to LegalNo Encumbrances Finance.pdf · uploaded 13 Jan 2025Source
- 2 b Details of encumbrances concerned to LegalNo Encumbrances Legal.pdf · uploaded 13 Jan 2025Source
- 1 Other – TechnicalDeclaration Cum Undertaking.pdf · uploaded 13 Jan 2025Source
- 1 Proforma of Agreement for saleAgreement.pdf · uploaded 13 Jan 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Bank Letter.pdf · uploaded 13 Jan 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure Secured Unsecured Finance.pdf · uploaded 13 Jan 2025Source
- 2 Disclosure for secured/unsecured finance availed for the projectCA Certificate.pdf · uploaded 20 Jan 2025Source
- 1 PAN CardDeclaration Cum Undrtaking.pdf · uploaded 5 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 25 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 25 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 25 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 25 Apr 2025Source
- Form 1Form 1.pdf · uploaded 20 Dec 2025Source
- Form 2Form 2.pdf · uploaded 20 Dec 2025Source
- Form 3Form 3.pdf · uploaded 20 Dec 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Invemtory.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 12 Feb 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 12 Feb 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 12 Feb 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 13 Feb 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 13 Feb 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 13 Feb 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 9 May 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 9 May 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 9 May 2026Source
- Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 9 May 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 31 Jul 2026Source
- Withdrawal Update Form 2form 2.pdf · uploaded 31 Jul 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 31 Jul 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 71/3/4/5 Plot No 30
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —53 units in all
- Address
- 71/3/4/5 Plot No 30, NEAR SHINGANAPUR ROAD, NEAR HOTEL JEETPIN 415523
- Village
- Kolki (CT), Phaltan taluka
- Land area for this project
- 1,388 sq m (14,937 sq ft)
- Permissible built-up area
- 3,770 sq m (40,583 sq ft)
- Sanctioned built-up area
- 3,770 sq m (40,583 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 85
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
71/3/4/5 Plot No 30
Boundaries
- North
- S No 73-3 Paiki Remaining Land
- South
- Open Space And 9 Mtr Wide Road
- East
- S No 71-3-4-5 Plot No 20 And 9 Mtr Wide Road
- West
- Stream And S No 71-2
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking53 units
53 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Ramsrushti Apartment Wing A | — | — | 30 |
| Ramsrushti Apartment Wing B | — | — | 23 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sanket Jangam | — |
| Chartered accountant | Nikhil Bhoite And Associates | — |
| Engineer | Randhir Bhoite | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Kolki (Ct)
- Lambodar ParkRERA PM1300002500614
- Vitthal PrideRERA P52700080645
- Nd ParkRERA P52700080349
- Trimurti HeightsRERA P52700080134
- Mayuresh ParkRERA P52700079780
- Govind ParkRERA P52700054856
- Kalpataru TowersRERA P52700054039
- Sunshine Landmark Phase IIRERA P52700048591
All 29 projects in Kolki (Ct) · Compare Ramsrushti Apartment with another project