City View Heights
Certificate SignedPhaltan (M Cl), Satara 415523 |Promoter: Shri Ganesh Constructions
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 2BHK, Shop18 units in all
- Address
- CTS NO. 6482 PLOT NO. 3 & 8, Opp Upalekar Maharaj Mandir, LaxminagarPIN 415523
- Designated bank account
- 85
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Mar 2025
The latest completion date on record passed 1 year and 7 months ago.
- Registered
- 17 Oct 2022
- Promised
- 31 Mar 2025
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52700047269 | 17 Oct 2022 | 31 Mar 2025 | 31 Mar 2025 | Shri Ganesh Constructions | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| City View Heights | 5 | 18 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
5 of 18 units booked (28%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 77.64 sq m · 836 sq ft | 10 | 3 |
| Shop | 14.9 sq m · 160 sq ft | 2 | 0 |
| Shop | 14.95 sq m · 161 sq ft | 2 | 1 |
| Shop | 17.73 sq m · 191 sq ft | 2 | 1 |
| Shop | 20.51 sq m · 221 sq ft | 2 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 71 filings listed on MahaRERA's project page
Finance
- PAN CardPan.pdf · uploaded 25 Aug 2022Source
Legal
Show all 72 documentsShow fewer documents
Migrated
- 2 Copy of the legal title reportTitle (Flow).pdf · uploaded 25 Aug 2022Source
- 3 Copy of the legal title reportTitle Certificate.pdf · uploaded 25 Aug 2022Source
- 1 a Details of encumbrances concerned to FinanceNo Encumbrances (Finance).pdf · uploaded 25 Aug 2022Source
- 1 b Details of encumbrances concerned to LegalNo Encumbrances (Legel).pdf · uploaded 25 Aug 2022Source
- 1 Copy of Layout Approval (in case of layout)Bldg Plan.pdf · uploaded 25 Aug 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentBldg Plan.pdf · uploaded 25 Aug 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 25 Aug 2022Source
- 1 Declaration about Commencement CertificateDeclaration CC.pdf · uploaded 25 Aug 2022Source
- 1 Declaration in FORM BDeclaration Form B.pdf · uploaded 25 Aug 2022Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 25 Aug 2022Source
- 1 Proforma of Allotment letterAllotment.pdf · uploaded 25 Aug 2022Source
- 2 Proforma of Allotment letterAgreement.pdf · uploaded 25 Aug 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration Bank Account.pdf · uploaded 25 Aug 2022Source
- 1 Deviation Report with respect to Allotment letterDeviation (Allotment).pdf · uploaded 25 Aug 2022Source
- 1 Deviation Report with respect to model copy of AgreementDeviation (Agreement).pdf · uploaded 25 Aug 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 13 Oct 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 1 Jun 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 1 Jun 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A.pdf · uploaded 1 Jun 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 1 Jun 2023Source
- 1 Disclosure of sold/ booked inventoryDisclosure.pdf · uploaded 2 Jun 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 (1).pdf · uploaded 20 Mar 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 (2).pdf · uploaded 20 Mar 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 (3).pdf · uploaded 20 Mar 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 2 (1).pdf · uploaded 20 Mar 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (1).pdf · uploaded 20 Mar 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (2).pdf · uploaded 20 Mar 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (3).pdf · uploaded 20 Mar 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 20 Mar 2024Source
- 2 Disclosure of sold/ booked inventoryInventory.pdf · uploaded 20 Mar 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 (1).pdf · uploaded 20 Mar 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 (2).pdf · uploaded 20 Mar 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 (3).pdf · uploaded 20 Mar 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 (4).pdf · uploaded 20 Mar 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 (5).pdf · uploaded 20 Mar 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 (6).pdf · uploaded 20 Mar 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 20 Mar 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 2 Jul 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 2 Jul 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 2 Jul 2024Source
- 3 Disclosure of sold/ booked inventoryInventory.pdf · uploaded 2 Jul 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 (1).pdf · uploaded 2 Jul 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 (2).pdf · uploaded 2 Jul 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 16 Jan 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 16 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 16 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 16 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 16 Jan 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 16 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold booked inventory.pdf · uploaded 16 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5.pdf · uploaded 16 Jan 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 3 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 3 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 3 Feb 2025Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Phaltan (M Cl), Phaltan taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Municipal Road
- South
- Municipal Road
- East
- Remaining area out of Plot No 3 8 9 4
- West
- Property of Mandakini Shrikrushna Date
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Rahul Nalawade | — |
| Chartered accountant | S B Chavan and Associates | — |
| Engineer | S S Randive Jain | — |
Source: MahaRERA project page. Contact details are not shown.