Varne, Raigarh
Deedo IDDL-RAI-VARNE8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects5
Registrations6some projects hold several
Completion still due42 past their date
Median extension4 months67% of registrations extended
Regulatory cases0none on MahaRERA's lists
8 in 10 registrations run late here
6 MahaRERA registrations in Varne
1 not yet due3 extended, not yet due2 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Varne
5 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Sugee VerandasManish R Jhunjhunwala | Due Apr 2029, extended 4 mo | — | — |
| Kalpataru Aria - Phase DArena Orchards Private Limited | Due Apr 2027, extended 4 mo | — | — |
| Kalpataru Aria - Phase CArena Orchards Private Limited | Completed | — | — |
| Kalpataru AriaArena Orchards Private Limited | Due Jul 2028, extended 4 mo | — | 15% |
| Kalpataru Aria - Phase AArena Orchards Private Limited | Completed, extended 3 mo | — | — |
Nearby: other villages in Karjat
Most active promoters
- Arena Orchards Private Limited4 projects
- Manish R Jhunjhunwala1 project
Varne, in questions
How many projects in Varne run late?
8 in 10 MahaRERA registrations (5 of 6): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Varne by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology