RERA projects in Shelu

6 projects under 7 MahaRERA registrations, registered 2017–2025. 29% have a completion date extended beyond the one promised.

6RERA projects
7Registrationssome projects hold several
3Completion still due4 past their completion date
30 monthsMedian extension beyond promised date29% of registrations extended
0Regulatory casesnone on MahaRERA's lists
5Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20180
20190
20201
20210
20221
20230
20241
20252

Projects in Shelu

6 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
shree hari complexShiv Om DevelopersPM127000250154924 Nov 202525 Dec 2029—Not yet due0
Vrindavan HeightsSahajanand InfratechPM127000250058014 Aug 202531 Dec 2033—Not yet due0
Chitrapatjanak Dadasaheb Phalke Township - Phase 1Anukarati Homes Pvt LtdP520000475387 Nov 202230 Jun 2026—Promised date passed0
Swami AashrayStructura RealtyP52000024532, P5200005549718 Feb 202030 Jun 202720 Dec 2023Not yet due0
Arya ParadiseBhole balaji & CompanyP5200001384127 Oct 201730 Mar 2025—Promised date passed0
GokuldhamShreeji DevelopersP5200000960722 Aug 201730 Jun 202125 Dec 2025Extended 54 mo0

Other localities in Karjat

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Anukarati Homes Pvt Ltd1 project
  2. Bhole balaji & Company1 project
  3. Sahajanand Infratech1 project
  4. Shiv Om Developers1 project
  5. Shreeji Developers1 project
  6. Structura Realty1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology