RERA projects in Pimploli Bk

4 projects under 7 MahaRERA registrations, registered 2018–2024. 71% have a completion date extended beyond the one promised.

Locality
4RERA projects
7Registrationssome projects hold several
5Completion still due2 past their completion date
4 monthsMedian extension beyond promised date71% of registrations extended
0Regulatory casesnone on MahaRERA's lists
27Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20184
20190
20200
20210
20222
20230
20241

Projects in Pimploli Bk

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
ForeverLandHoabl Impactum Land Private LimitedP520000778147 Nov 202430 Jun 202930 Oct 2029Extended 4 mo0
Foothills of MatheranHOABL Impactum Land Private LimitedP52000046022, P5200004603915 Jun 202230 Jun 2025—Promised date passed0
Puranik City Sector 4aPuranik Builders LimitedP520000179943 Oct 20181 May 20311 Sep 2031Extended 4 mo0
Puranik CityPuranik Builders LimitedP52000017953, P52000017954, P5200001799628 Sep 20181 Sep 20291 Jan 2030Extended 4 mo0

Other localities in Karjat

Most active promoters

By projects registered here, as named on MahaRERA.

  1. HOABL Impactum Land Private Limited2 projects
  2. Puranik Builders Limited2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology