Pen, Raigarh
Deedo IDDL-RAI-PEN9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects161
Registrations168some projects hold several
Completion still due5897 past their date
Median extension4 months46% of registrations extended
Regulatory cases1on 1 project
9 in 10 registrations run late here
168 MahaRERA registrations in Pen and the places within it
8 not yet due50 extended, not yet due97 past even the latest date13 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Pen
161 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Magneum MarvelMagneum Developers | Completed | — | — |
| ChintamaniShree Sadguru Builders | Completed, extended 1 yr 10 mo | — | 65% |
| Jagdamba SwaraJagdamba Enterprises | Completed | — | 100% |
| Govardhan PlatinumKhelaan Manoj Unadkat | Completed | — | — |
| Balaji GreensSathe Schemes | Completed | — | — |
| VijayaGandharva Developers | Completed | — | — |
| Sai RajShree Sai Developers | 7 yrs late | — | — |
| Vighnahar SudamaMahesh Sudam Patil | Completed | — | 11% |
| Darshan Business Park1Shankheshwar Associates | Completed, extended 1 yr | — | 7% |
| Tarun Plantations CompanyTarun Plantations Company | Due Jul 2027, extended 4 mo | — | — |
| Bhagyoday ResidencyMangalmay Realities | 8 yrs 6 mo late | — | — |
| SaisadanSaikrupa Developers | Completed | — | — |
| Sai - AarambhSai Shraddha Builders & Developers | 6 yrs 2 mo late | — | 17% |
| Siddhivinayak ResidencySunil Raghunath Vidhate | Completed, extended 9 mo | — | 43% |
| Om ImperiaShree Samarthya Builders & Developers | 8 yrs 8 mo late | — | — |
| Redwood LandmarkRedwood Developers | Completed, extended 1 yr | — | 30% |
| Aakruti Building No.2Aakruti Builders & Developers | Completed | — | 2% |
| Abp VastavAbp Builders & Developers | Completed, extended 1 yr 6 mo | — | — |
| Prabhavati ComplexRahil Roshan Somjee | Completed | — | 7% |
| Shankar Parvati ResidencyR. S. Construction | Completed | — | 79% |
| Darshan Business Park-2Shankheshwar Associates | Completed | — | 29% |
| Durvankur ApartmentManoj Jayant Bhagwat | Completed | — | — |
| Ekvira VishwaOrbit Builders & Developers | 6 yrs 2 mo late | — | 20% |
| Nakshtra PlazaSharvari Builders & Developers | Completed | — | 52% |
| Prayag KalashPrayag Developers | Completed, extended 10 mo | — | 100% |
Nearby: other talukas in Raigarh
Most active promoters
- Sathe Schemes6 projects
- The United Group Of Builders And Developers5 projects
- Jagdamba Enterprises4 projects
- Swastik Group Builders And Developers4 projects
- Gurudarshan Realtors3 projects
- Vast Construction3 projects
- Aakruti Builders & Developers2 projects
- Darshan Kirtikumar Bafna2 projects
- D Bafna Properties2 projects
- Himakshi Akshay Vora2 projects
Pen, in questions
How many projects in Pen run late?
9 in 10 MahaRERA registrations (147 of 168): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Pen by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology