Pen, Raigarh
Deedo IDDL-RAI-PEN9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects161
Registrations168some projects hold several
Completion still due5897 past their date
Median extension4 months46% of registrations extended
Regulatory cases1on 1 project
9 in 10 registrations run late here
168 MahaRERA registrations in Pen and the places within it
8 not yet due50 extended, not yet due97 past even the latest date13 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Pen
161 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shiv SadanSaniya Developers | Completed | — | 31% |
| Shiv Shrushti ApartmentHarsh Constrution | Completed, extended 1 yr 6 mo | — | 43% |
| Swami SankulPrarambh Associates | 7 yrs 3 mo late | — | 61% |
| Aura Village Phase 1Vector Lifespace LLP | Completed | — | 32% |
| Yash ComplexYash Developers | Completed | — | 22% |
| Redwood IconRedwood Buildcon | Completed | — | 38% |
| Samarth SamruddhiMandar Madhukar Karandikar | Completed | — | 31% |
| Om Palekar And Jitekar ApartmentMaalveer Enterprises | 7 yrs 7 mo late | — | 6% |
| Suhaan SiddhiSuhaan Builders And Developers | Completed, extended 4 yrs 5 mo | — | 63% |
| Mango HomesAshirvad Projects | Completed | — | 100% |
| Shree YashwantShree DattaGuru Construction Company | 7 yrs 8 mo late | — | 50% |
| Aakruti Building No. 4 And 5Aakruti Builders & Developers | Completed, extended 1 yr 9 mo | — | 51% |
| Hiland EmeraldMerchant Construction | 3 yrs 4 mo late | — | 60% |
| Prime New HorizonPrashant Chandrakant Bhoir | Completed | — | 83% |
| TaramatiVast Construction | Completed | — | 48% |
| ChandradarshanChandradarshan Developers | Completed | — | 84% |
| Prathamesh Rama AishwaryaSachin Shringarpure Associates, Builders & Developers | Completed | — | 81% |
| United Galaxy Phase 4The United Group Of Builders And Developers | Completed | — | 32% |
| Prathamesh Swami ChintanShivashakti Builders & Developers | 3 yrs 7 mo late | — | 87% |
| GrandeurRoyal Builders & Developers | Completed | — | 49% |
| Vinayak Sai Residency4Sai Built Con | Completed | — | 18% |
| Mrudagandhar Phase 1The United Group Of Builders And Developers | Completed | — | 51% |
| OrionDarshan Kirtikumar Bafna | Completed | — | 55% |
| Aarambh Residency | No date on record | — | — |
| Bandivadekar Residency | No date on record | — | — |
Nearby: other talukas in Raigarh
Most active promoters
- Sathe Schemes6 projects
- The United Group Of Builders And Developers5 projects
- Jagdamba Enterprises4 projects
- Swastik Group Builders And Developers4 projects
- Gurudarshan Realtors3 projects
- Vast Construction3 projects
- Aakruti Builders & Developers2 projects
- Darshan Kirtikumar Bafna2 projects
- D Bafna Properties2 projects
- Himakshi Akshay Vora2 projects
Pen, in questions
How many projects in Pen run late?
9 in 10 MahaRERA registrations (147 of 168): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Pen by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology