Pen, Raigarh

Deedo IDDL-RAI-PEN

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects161
Registrations168some projects hold several
Completion still due5897 past their date
Median extension4 months46% of registrations extended
Regulatory cases1on 1 project

9 in 10 registrations run late here

168 MahaRERA registrations in Pen and the places within it

8 not yet due50 extended, not yet due97 past even the latest date13 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Pen

161 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Jagdamba NakshatraJagdamba EnterprisesDue Dec 2030——
Shree Samarth Krupa ApartmentSanjay Vithoba KateDue Dec 2028——
Heyansh HeightsF Nd H GroupDue Sep 2029, extended 4 mo——
Sathe SukrutAce RealtorsDue Apr 2031, extended 4 mo——
Shree ParkShree InfraDue Apr 2032, extended 4 mo——
Mauli Laxmi PujaMoiz Shabbir ShirpurwalaDue Jul 2029, extended 4 mo——
SwapnashilpaS S BuildconDue Nov 2029, extended 4 mo——
AvantikaSathe SchemesDue Sep 2032, extended 4 mo——
Kavya ResidencyHjs Infrastructure LLPDue Apr 2028, extended 4 mo——
Antilia - 1Bharatkumar Hiralal ShahDue Jul 2029, extended 4 mo——
Haware GrandeHaware GrandeDue Nov 2030, extended 4 mo——
Vast Vitha Govind ResidencyVast Builders DevelopersDue Apr 2033, extended 4 mo——
Gurukul ResidencyJagruti Mangesh MhatreDue Dec 2027, extended 4 mo——
Hari DarshanHari ConstructionDue Oct 2027, extended 4 mo——
Royal AvenueRoyal DevelopersDue Oct 2028, extended 4 mo——
dbafna ONED Bafna PropertiesDue Jul 2029, extended 4 mo——
Nirvana HeightsGurudarshan RealtorsDue Apr 2028, extended 4 mo——
Mrudagandhar Phase 3 Rageshree D Type BuildingThe United Group Of Builders And DevelopersDue Apr 2028, extended 4 mo—8%
Redwood ParadiseRedwood BuildersDue Jan 2029, extended 4 mo——
Shiv Sai ResidencyHarsh ConstructionDue Jul 2028, extended 4 mo——
Swastik SapphireSwastik Group Builders And DevelopersDue Apr 2028, extended 4 mo—2%
Gurukrupa ResidencyS R ConstructionDue Apr 2028, extended 4 mo——
Shree Sadguru ParkSafal DevelopersDue Dec 2027, extended 4 mo—4%
MithilaSathe Schemes LLPDue Sep 2030, extended 4 mo—16%
ArhamIys Properties LLPDue Apr 2027, extended 4 mo——
Pen market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Sathe Schemes6 projects
  2. The United Group Of Builders And Developers5 projects
  3. Jagdamba Enterprises4 projects
  4. Swastik Group Builders And Developers4 projects
  5. Gurudarshan Realtors3 projects
  6. Vast Construction3 projects
  7. Aakruti Builders & Developers2 projects
  8. Darshan Kirtikumar Bafna2 projects
  9. D Bafna Properties2 projects
  10. Himakshi Akshay Vora2 projects

Pen, in questions

How many projects in Pen run late?

9 in 10 MahaRERA registrations (147 of 168): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Pen by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology