Mahad, Raigarh
3 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects136
Registrations136
Completion still due3878 past their date
Median extension4 months29% of registrations extended
Regulatory cases3on 3 projects
8 in 10 registrations run late here
136 MahaRERA registrations in Mahad and the places within it
12 not yet due26 extended, not yet due78 past even the latest date20 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Mahad
136 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Land NextChaitanya Shrikant Mundada | PP1270002602479 | 19 Oct 2026 | 31 Dec 2027 | — | Not yet due | 0 |
| Sangita ComplexAdil Maqbool Matwankar | PM1270002602467 | 19 Oct 2026 | 1 Mar 2029 | — | Not yet due | 0 |
| Nexa PrimeNexafuturity LLP | PM1270002600418 | 15 May 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Ekdant EnclaveSaee Constructions And Builders | PR1270002502655 | 9 Mar 2026 | 31 Dec 2032 | 30 Apr 2033 | Extended 4 mo | 0 |
| Shiv Shalini ComplexGanrai Developers | PM1270002502605 | 5 Mar 2026 | 31 Dec 2028 | 31 Dec 2028 | Not yet due | 0 |
| Shinde arcadeA I Darekhan Constructions | PM1270002501100 | 6 Oct 2025 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Green Park H WingShreeji Associates | P52000080977 | 19 Sep 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Ramkiran Heights B WingPriyanka Prasant Gujar | P52000080674 | 25 Jun 2025 | 31 May 2030 | 30 Sep 2030 | Extended 4 mo | 0 |
| Skyline ResidenciesLucky Group | P52000079304 | 28 Feb 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Mauli PlazaMauli Developers | P52000078934 | 21 Jan 2025 | 31 May 2027 | 30 Sep 2027 | Extended 4 mo | 0 |
| River EdgeAbhijit Ashok Kave | P52000078350 | 6 Dec 2024 | 30 Apr 2028 | 30 Aug 2028 | Extended 4 mo | 0 |
| Cloud 9Neelkanth Enterprises | P52000056475 | 5 Jun 2024 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Shashwats Nirmal Govind ResidencyVaibhav Dhanraj Chandorkar | P52000054511 | 25 Jan 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Ayesha ComplexNawaz Mohiddin Hurzuk | P52000053347 | 27 Oct 2023 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Siya 24 K Phase IINilesh Satish Mehta | P52000052223 | 31 Jul 2023 | 31 Dec 2027 | 31 Dec 2027 | Not yet due | 0 |
| Shelter PlazaMahira Developers | P52000050990 | 19 May 2023 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Ckc HubUday Chandrakant Payelkar | P52000050461 | 17 Apr 2023 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Hari Om ResidencyAparna A Bhosale | P52000049802 | 24 Feb 2023 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Sai TirthDilip Waman Gadgil | P52000049621 | 22 Feb 2023 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Chandra Pushpa PrideRajesh Subhash Dharia | P52000049044 | 30 Jan 2023 | 31 Dec 2024 | 31 Dec 2024 | Promised date passed | 0 |
| Gayatri ParadiseNilesh Satish Mehta Proprietor Of Shree Swami Construction | P52000048201 | 15 Dec 2022 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Narmada ResidencyShree Sai Developers | P52000047911 | 1 Dec 2022 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Jai Tuljabhavani Sahakari Gruhanirman Sanstha LtdAnnaraya Madivalappa Sheelavant | P52000047765 | 28 Nov 2022 | 30 Nov 2023 | 31 Dec 2026 | Extended 37 mo | 0 |
| Sunshine ApartmentRahim Abdul Gafur Pathan | P52000047783 | 28 Nov 2022 | 31 Dec 2023 | 31 Dec 2023 | Promised date passed | 0 |
| NilkanthArihant Innovators | P52000047467 | 2 Nov 2022 | 31 Mar 2027 | 31 Mar 2027 | Not yet due | 0 |
Nearby: other talukas in Raigarh
Most active promoters
- Amitkumar Zaverchand Sheth3 projects
- Chaitanya Builders3 projects
- Dilip Waman Gadgil3 projects
- Javed Latif Haji3 projects
- Mahira Developers3 projects
- Shreeji Associates3 projects
- Aijaz Ismail Darekhan2 projects
- Chandrakaumudi Construction2 projects
- Dhanalaxmi Realtors2 projects
- Lucky Group2 projects
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology