RERA projects in Mangaon

55 projects under 56 MahaRERA registrations, registered 2017–2026. 26% have a completion date extended beyond the one promised.

55RERA projects
56Registrationssome projects hold several
23Completion still due30 past their completion date
27 monthsMedian extension beyond promised date26% of registrations extended
1Regulatory caseson 1 project
6Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201715
20188
20196
20202
20213
20223
20232
20247
20254
20263

Projects in Mangaon

55 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
More EstatesMore EstatesPR12700026018519 Sep 202617 Feb 2029—Not yet due0
Bhoomi ArcadeBhoomi Builders And DevelopersPR127000260154914 Aug 202631 Dec 2031—Not yet due0
Manohar Apartments B wingAshvattha DevelopersPR12700026013993 Aug 202631 Mar 2029—Not yet due0
Rukmini HeightsRJM Constructions & Developers LLPP5200008092218 Aug 202531 Aug 2027—Not yet due0
VrindavanS P ConstructionPR127000250015027 Jun 202518 Jun 2028—Not yet due0
Gurudev ApartmentRajesh Samarth PrabhuP5200007916110 Feb 202531 Dec 2027—Not yet due0
Sahjeevan Sahakari Gruhnirman Sanstha LtdWangre Builders And Developers Private LimitedP520000787308 Jan 202531 Dec 2025—Promised date passed0
RivieraJairam Nandkishor BhasinP5200007810225 Nov 202430 Sep 2027—Not yet due0
Vishwa ApartmentsRatnmala Ramesh KhanvilkarP5200007816925 Nov 202431 Dec 2026—Not yet due0
Dongre PlazaShoeb Farid DongreP5200007714823 Jul 202431 Mar 2028—Not yet due0
Royal Shopping CentreAflah Builders And DevelopersP520000769029 Jul 202431 Dec 2028—Not yet due0
Chinmay PlazaAtmaram Narayan ShindeP5200005642231 May 202431 Dec 2028—Not yet due0
Rising ResidencyRising Builders And DevelopersP520000559692 May 202431 Dec 2030—Not yet due0
Patel HeritagePatel Builders And DevelopersP5200005578316 Apr 202431 Dec 2027—Not yet due0
Gold Valley Konkan Bungalows Phase2Goka Engineering Company Pvt LtdP520000513078 Jun 202331 Mar 2026—Promised date passed0
Manohar ApartmentAmeya Shrikant BhaveP5200005087215 May 202331 Mar 202431 Mar 2025Extended 12 mo0
The LandmarkPatel Builders And DevelopersP5200003476028 Apr 202231 Oct 2025—Promised date passed0
Infinity EnclaveInfinity BuildconP5200003458511 Apr 202231 Dec 2027—Not yet due0
Gold Valley Konkan Bungalows Phase 1Goka Engineering Co Pvt LtdP5200003394414 Mar 202231 Dec 2025—Promised date passed0
Kadamb Apartments A and BPrasad Janardan MaratheP520000288375 Apr 202115 Jun 202215 Jun 2023Extended 12 mo0
Vakratunda ResidencyGreenfield DevelopersP5200002832818 Feb 202124 Jun 202323 Jun 2024Extended 12 mo0
ShivkrishnaNimesh Gulabchand Chheda (HUF)P5200002817010 Feb 202130 Jun 2023—Promised date passed0
Galande ComplexSantosh Sahadev GalandeP520000252915 Apr 202031 Dec 2028—Not yet due0
Yogeshwari GardenShree Yogeshwari Developers Private LimitedP5200002522323 Mar 202030 Mar 2030—Not yet due0
Farhan DevelopersBashir Hasan KirkireP5200002330011 Dec 201930 Dec 2026—Not yet due0
Royal PalaceSunil Mahadev PusalkarP520000231072 Dec 201914 Oct 2019—Promised date passed0
Falak CityFalak ConstructionP520000226129 Oct 201930 Sep 202331 Mar 2026Extended 30 mo0
Trimurti ApartmentPradip Gauru MoreP520000226009 Oct 201930 Dec 2023—Promised date passed0
Laxmi Narayan ComplexAshwamegh Promoters And DevelopersP5200002208325 Aug 201930 Mar 2023—Promised date passed0
Aakash River ViewAakash DevelopersP520000214553 Jul 201931 Dec 2029—Not yet due0
Shree Pandurang Gore ComplexJain Builders & DevelopersP520000179813 Oct 20183 Aug 2022—Promised date passed0
Shruti ShubhamTechno Associate Builder And DevelopersP5200001755024 Aug 201830 Dec 2022—Promised date passed0
MansarovarUma DevelopersP5200001580226 Mar 201830 Dec 202430 Dec 2025Extended 12 mo0
Ramashray ApartmentNandini Nitin BamgudeP5200001544526 Feb 201822 Feb 2023—Promised date passed0
Rising ComplexRising Builders And DevelopersP5200001525612 Feb 201823 Nov 202130 Sep 2022Extended 10 mo0
CrownBhasin Properties And Developers Pvt LtdP5200001495915 Jan 201831 Dec 2027—Not yet due1
Paradise BSaurabh RealtiesP5200001491711 Jan 201830 Jun 202131 Dec 2023Extended 30 mo0
Sai ManoharSai Shreeram AssociatesP520000147862 Jan 201828 Aug 202231 Dec 2026Extended 52 mo0
Gold Valley KonkanGoka Engineering Co Pvt LtdP5200000533113 Nov 201731 Dec 2017—Promised date passed0
Siddhivinayak Phase 1Goka Engineering Co Pvt LtdP5200000253013 Nov 201731 Dec 2017—Promised date passed0
Anand Nagar Commericial buildingAnubhavshri Realty Pvt. Ltd.P520000139682 Nov 201730 Dec 202131 Dec 2027Extended 72 mo0
Vastuvihar Residency - Building 6 - LilacDhanji Kheta SandhaP520000125724 Sep 201731 Dec 2019—Promised date passed0
Malhar ResidencyRadheshyam Estate and Developers Private LimitedP5200001149731 Aug 201731 Dec 201930 Dec 2022Extended 36 mo0
Sai ResidencySatguru Construction and DevelopersP5200001126531 Aug 201730 Aug 201928 Jun 2023Extended 46 mo0
Amit ComplexDattaram Dhaku Gawade and Shobha Dattaram Gawade Joint Co-OwnerP5200000884919 Aug 201731 Dec 202831 Dec 2028Not yet due0
Harmony Appartment Wing CShantiniketan RealtorsP5200000818518 Aug 201731 Dec 2019—Promised date passed0
Anand Nagar Phase 3Anubhavshri Realty Pvt. Ltd.P5200000714717 Aug 201731 Dec 2028—Not yet due0
Mahalaxmi NivaraMahalaxmi Buildtech LLPP5190000733217 Aug 201730 Jun 202130 Jun 2023Extended 24 mo0
Gandharva BhoomiGandharva Bhoomi (Aop)P5200000539211 Aug 201731 Dec 2019—Promised date passed0
Kondvilkar HeightsShree Yogeshwari Developers Private LimitedP520000048299 Aug 201730 Dec 202030 Jun 2022Extended 18 mo0
Anand NagarAnubhavshri Realty Pvt. Ltd.P52000003466, P520000057475 Aug 201731 Dec 201830 Jun 2022Extended 42 mo0
Gold Valley Konkan Sect CGoka Engineering Company Pvt LtdP520000025351 Aug 201730 Mar 2022—Promised date passed0
Green City Phase 1P52000009668————0
Shubham Complex 1bP52000005083————0
VastushilpP52000012742————0

Other talukas in Raigarh

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Anubhavshri Realty Pvt. Ltd.3 projects
  2. Goka Engineering Co Pvt Ltd3 projects
  3. Goka Engineering Company Pvt Ltd2 projects
  4. Patel Builders And Developers2 projects
  5. Rising Builders And Developers2 projects
  6. Shree Yogeshwari Developers Private Limited2 projects
  7. Aakash Developers1 project
  8. Aflah Builders And Developers1 project
  9. Ameya Shrikant Bhave1 project
  10. Ashvattha Developers1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology