Pen, Raigarh
Deedo IDDL-RAI-PEN9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects161
Registrations168some projects hold several
Completion still due5897 past their date
Median extension4 months46% of registrations extended
Regulatory cases1on 1 project
9 in 10 registrations run late here
168 MahaRERA registrations in Pen and the places within it
8 not yet due50 extended, not yet due97 past even the latest date13 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Pen
161 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| GrandeurRoyal Builders And Developers | Due Oct 2031, extended 4 mo | — | 13% |
| Orion PlusDarshan Kirtikumar Bafna | Completed, extended 6 mo | — | 34% |
| Padmavati DarshanPadmavati Construction | Completed | — | 26% |
| EmvisEmerald Developers | Completed, extended 1 yr | — | 44% |
| ArumThe United Group Of Builders And Developers | Completed | — | 89% |
| Sky VillasK N Developers And Engineers LLP | Completed, extended 4 mo | — | 44% |
| Prithvi ComplexPrithvi Developers | Completed | — | 100% |
| Dr Patwardhan SmrutiShailesh Pundalik Patil | Completed | — | — |
| Balaji TricitySathe Schemes | Completed | — | 100% |
| Swastik OasisSwastik Group Builders And Developers | Completed | — | — |
| Om Vayunand ResidencyAvinash Patil | 4 yrs 2 mo late | — | — |
| Swargiya Ramubai ResidencyTailesh Patil | 4 yrs 6 mo late | — | — |
| Royal Bandhu SmrutiImran Mohsin Sayyed | 4 yrs 4 mo late | — | — |
| Chaitrangan ResidencyConnect Homes | Completed, extended 6 mo | — | 6% |
| Navdurga Shiv Complex - B WingNavdurga Shiv Complex - B Wing | Completed | — | — |
| Akruti ResidencyHimakshi Akshay Vora | 3 yrs 5 mo late | — | — |
| Varadhast ResidencyDee Bee Pee Realities | 4 yrs 11 mo late | — | 31% |
| Jagdamba SiddhiJagdamba Enterprises | Completed | — | 100% |
| GokulSuyash Builders And Developers | Completed, extended 1 yr 5 mo | — | 79% |
| Deccan SquareAfzal Umer Furniturewala | 2 yrs 1 mo late | — | — |
| Saakaar RamkrushnaPrasad Barve | 5 yrs 10 mo late | — | — |
| Aisha ResidencyS.r.developers | Completed | — | 93% |
| Relish ResidencyMukesh Chouhan | 3 yrs 11 mo late | — | 100% |
| Anand TarangOmkar Anand Deodhar | Completed | — | — |
| Vegetable Market Cum Shopping ComplexR.p. Builders | Completed | — | — |
Nearby: other talukas in Raigarh
Most active promoters
- Sathe Schemes6 projects
- The United Group Of Builders And Developers5 projects
- Jagdamba Enterprises4 projects
- Swastik Group Builders And Developers4 projects
- Gurudarshan Realtors3 projects
- Vast Construction3 projects
- Aakruti Builders & Developers2 projects
- Darshan Kirtikumar Bafna2 projects
- D Bafna Properties2 projects
- Himakshi Akshay Vora2 projects
Pen, in questions
How many projects in Pen run late?
9 in 10 MahaRERA registrations (147 of 168): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Pen by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology