Ghot, Raigarh
Deedo IDDL-RAI-GHOT8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects27
Registrations30some projects hold several
Completion still due237 past their date
Median extension4 months67% of registrations extended
Regulatory cases1on 1 project
8 in 10 registrations run late here
30 MahaRERA registrations in Ghot
5 not yet due18 extended, not yet due7 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Ghot
27 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Riddhi Siddhi VantaraRiddhi Siddhi Developers | Due Apr 2031, extended 4 mo | — | — |
| Qa Riverfront 2Rs Buildcon | Due Apr 2031, extended 4 mo | — | — |
| Square OrnateMohammed Aslam Noor Ullah Khan | Due Apr 2030, extended 4 mo | — | — |
| LA AvenueAurus Prorora LLP | Due Dec 2027 | — | — |
| QA Riverfront 3RS Couture LLP | Due Apr 2030, extended 4 mo | — | — |
| Sai Suncity CommercialChariot Properties LLP | Due Apr 2027, extended 4 mo | — | — |
| Sm JewelS M Hitech Developers | Due Apr 2029, extended 4 mo | — | 10% |
| The AmbienceBalaji Infra | Due Aug 2028, extended 4 mo | — | — |
| QA RiverfrontRS Couture LLP | Completed | — | 12% |
| Dattakrupa ComplexPavan Mahatma Devalkar | Due Apr 2027, extended 4 mo | — | 80% |
| GokuldhamGokuldham | Due Apr 2027, extended 4 mo | — | 4% |
| Mahaveer EmpireMahaveer Realty | Due Apr 2027, extended 4 mo | — | — |
| Arihant Adarsh Phase IArihant Superstructures Limited | Due Dec 2032, extended 2 yrs 9 mo | — | 17% |
| Rudra RajendraRudra Developers | Completed | — | 30% |
| Sai Amber ResidencyWalmik Raghunath Khairnar | Due Apr 2027, extended 4 mo | — | — |
| Sai Shri NarayanaSri Venkateshwara Builders | Due Apr 2028, extended 4 mo | — | 28% |
| Arihant Aakarshan Phase IArihant Superstructures Limited | Due Jul 2030, extended 4 mo | — | — |
| Riddhi Siddhi ImperialDharmendra Bhanwarlal Mali | Completed | — | — |
| Sai SuncityChariot Properties LLP | Due Apr 2029, extended 4 mo | — | — |
| Unimax PrideMycity Constructions LLP | Due Apr 2027, extended 4 mo | — | 45% |
| Jijai AnganShubham Infra | 5 mo late | — | 88% |
| Happy HomeHappy Leisure Realties LLP | 1 yr 11 mo late | — | — |
| Arihant AmberArihant Vatika Realty Private Limited | Completed | — | 100% |
| Krushna KunjKrushna Dham Builders & Developers Ghot | 11 mo late | — | — |
| Jijai ComplexShubham Builders & Developers | Completed, extended 1 yr 10 mo | — | 100% |
Nearby: other villages in Panvel
Most active promoters
- Arihant Superstructures Limited2 projects
- Chariot Properties Llp2 projects
- Dharmendra Bhanwarlal Mali2 projects
- Rs Couture Llp2 projects
- Arihant Aashiyana Private Limited1 project
- Arihant Vatika Realty Private Limited1 project
- Aurus Prorora Llp1 project
- Balaji Infra1 project
- Gokuldham1 project
- Happy Leisure Realties Llp1 project
Ghot, in questions
How many projects in Ghot run late?
8 in 10 MahaRERA registrations (25 of 30): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ghot by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology