Ghot, Raigarh

Deedo IDDL-RAI-GHOT

8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects27
Registrations30some projects hold several
Completion still due237 past their date
Median extension4 months67% of registrations extended
Regulatory cases1on 1 project

8 in 10 registrations run late here

30 MahaRERA registrations in Ghot

5 not yet due18 extended, not yet due7 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Ghot

27 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Riddhi Siddhi VantaraRiddhi Siddhi DevelopersDue Apr 2031, extended 4 mo——
Qa Riverfront 2Rs BuildconDue Apr 2031, extended 4 mo——
Square OrnateMohammed Aslam Noor Ullah KhanDue Apr 2030, extended 4 mo——
LA AvenueAurus Prorora LLPDue Dec 2027——
QA Riverfront 3RS Couture LLPDue Apr 2030, extended 4 mo——
Sai Suncity CommercialChariot Properties LLPDue Apr 2027, extended 4 mo——
Sm JewelS M Hitech DevelopersDue Apr 2029, extended 4 mo—10%
The AmbienceBalaji InfraDue Aug 2028, extended 4 mo——
QA RiverfrontRS Couture LLPCompleted—12%
Dattakrupa ComplexPavan Mahatma DevalkarDue Apr 2027, extended 4 mo—80%
GokuldhamGokuldhamDue Apr 2027, extended 4 mo—4%
Mahaveer EmpireMahaveer RealtyDue Apr 2027, extended 4 mo——
Arihant Adarsh Phase IArihant Superstructures LimitedDue Dec 2032, extended 2 yrs 9 mo—17%
Rudra RajendraRudra DevelopersCompleted—30%
Sai Amber ResidencyWalmik Raghunath KhairnarDue Apr 2027, extended 4 mo——
Sai Shri NarayanaSri Venkateshwara BuildersDue Apr 2028, extended 4 mo—28%
Arihant Aakarshan Phase IArihant Superstructures LimitedDue Jul 2030, extended 4 mo——
Riddhi Siddhi ImperialDharmendra Bhanwarlal MaliCompleted——
Sai SuncityChariot Properties LLPDue Apr 2029, extended 4 mo——
Unimax PrideMycity Constructions LLPDue Apr 2027, extended 4 mo—45%
Jijai AnganShubham Infra5 mo late—88%
Happy HomeHappy Leisure Realties LLP1 yr 11 mo late——
Arihant AmberArihant Vatika Realty Private LimitedCompleted—100%
Krushna KunjKrushna Dham Builders & Developers Ghot11 mo late——
Jijai ComplexShubham Builders & DevelopersCompleted, extended 1 yr 10 mo—100%
Ghot market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Arihant Superstructures Limited2 projects
  2. Chariot Properties Llp2 projects
  3. Dharmendra Bhanwarlal Mali2 projects
  4. Rs Couture Llp2 projects
  5. Arihant Aashiyana Private Limited1 project
  6. Arihant Vatika Realty Private Limited1 project
  7. Aurus Prorora Llp1 project
  8. Balaji Infra1 project
  9. Gokuldham1 project
  10. Happy Leisure Realties Llp1 project

Ghot, in questions

How many projects in Ghot run late?

8 in 10 MahaRERA registrations (25 of 30): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ghot by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology