Residential / Group Housing · 4 buildings · 231 unitsRERA P52000047600

Gokuldham

Deedo IDDP-RAI-ME4M

Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 4% of its units are booked.

Ghot, Raigarh 410208 · by Gokuldham

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales4% booked10 of 231 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 14 Nov 2022, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000047600
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200004760014 Nov 202231 Dec 202630 Apr 2027GokuldhamProject page
Documents57

1 document held by Deedo, 56 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 25 Jul 2022Source

Legal

  • Declaration Form BRera Declaration Gokuldham.pdf · uploaded 17 Aug 2022Source
  • Legal Title reportTitle Report.pdf · uploaded 13 Oct 2022Source
  • Legal Title reportSearch Report.pdf · uploaded 18 Oct 2022Source
  • Legal Title reportFerfar Scan Copy.pdf · uploaded 27 Oct 2022Source
  • Legal Title report7-12 Scan Copy.pdf · uploaded 27 Oct 2022Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 25 Jul 2022Source
Show all 57 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCC BLDG-1 (COMMENCEMENT CERTIFICATE).pdf · uploaded 25 Jul 2022Source
  • 1 CERSAI detailsCREDAI.pdf · uploaded 25 Jul 2022Source
  • 1 Declaration in FORM BRera Declaration Gokuldham.pdf · uploaded 17 Aug 2022Source
  • 1 a Details of encumbrances concerned to FinanceSelf Declaration Rera.pdf · uploaded 27 Aug 2022Source
  • 1 b Details of encumbrances concerned to LegalSelf Declaration Rera.pdf · uploaded 27 Aug 2022Source
  • 1 Copy of Layout Approval (in case of layout)CC APPROVAL PLAN.pdf · uploaded 27 Aug 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 27 Aug 2022Source
  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 13 Oct 2022Source
  • 1 Declaration about Commencement CertificateCC DECLARATION.pdf · uploaded 13 Oct 2022Source
  • 1 Proforma of Agreement for saleAGREEMENT FOE SALE.pdf · uploaded 13 Oct 2022Source
  • 1 Proforma of Allotment letterAGREEMENT FOE SALE.pdf · uploaded 13 Oct 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameForm -A Declaration of Bank Account.pdf · uploaded 13 Oct 2022Source
  • 2 Copy of the legal title reportSearch Report.pdf · uploaded 18 Oct 2022Source
  • 2 CERSAI detailsCERSAI.pdf · uploaded 21 Oct 2022Source
  • 1 Deviation Report with respect to Allotment letterNo Deviation.pdf · uploaded 21 Oct 2022Source
  • 1 Deviation Report with respect to model copy of AgreementNo Deviation.pdf · uploaded 21 Oct 2022Source
  • 3 Copy of the legal title reportFerfar Scan Copy.pdf · uploaded 27 Oct 2022Source
  • 4 Copy of the legal title report7-12 Scan Copy.pdf · uploaded 27 Oct 2022Source
  • 2 a Details of encumbrances concerned to FinanceDeclaration of No Encumbrance.pdf · uploaded 27 Oct 2022Source
  • 2 b Details of encumbrances concerned to LegalDeclaration of No Encumbrance.pdf · uploaded 27 Oct 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentCC APPROVAL PLAN.pdf · uploaded 31 Oct 2022Source
  • 2 Proforma of Agreement for saleALLOTMENT LETTER.pdf · uploaded 31 Oct 2022Source
  • 2 Copy of Layout Approval (in case of layout)APPROVED PLAN 1.pdf · uploaded 7 Aug 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentAPPROVED PLAN 1.pdf · uploaded 7 Aug 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentAPPROVED PLAN 2.pdf · uploaded 7 Aug 2023Source
  • 4 Building Plan Approval / NA Order for plotted developmentAPPROVED PLAN 3.pdf · uploaded 7 Aug 2023Source
  • 5 Building Plan Approval / NA Order for plotted developmentAPPROVED PLAN 4.pdf · uploaded 7 Aug 2023Source
  • 6 Building Plan Approval / NA Order for plotted developmentAPPROVED PLAN 5.pdf · uploaded 7 Aug 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC SCAN COPY.pdf · uploaded 7 Aug 2023Source
  • 3 a Details of encumbrances concerned to FinanceRERA DECLARATION.pdf · uploaded 30 Nov 2023Source
  • 3 b Details of encumbrances concerned to LegalRERA DECLARATION.pdf · uploaded 30 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Signed RERA Form 5.pdf · uploaded 1 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)RERA 23-24 Signed.pdf · uploaded 27 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE (2).pdf · uploaded 30 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form -2 _Engineer Certificate.pdf · uploaded 30 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 27 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)MAR-2023.pdf · uploaded 28 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)MARCH-2024.pdf · uploaded 28 Feb 2025Source

Technical

  • DocumentCC APPROVAL PLAN.pdf · uploaded 27 Aug 2022Source
  • DocumentCC APPROVAL PLAN.pdf · uploaded 31 Oct 2022Source
  • DocumentAPPROVED PLAN 1.pdf · uploaded 7 Aug 2023Source
  • DocumentAPPROVED PLAN 1.pdf · uploaded 7 Aug 2023Source
  • DocumentAPPROVED PLAN 2.pdf · uploaded 7 Aug 2023Source
  • DocumentAPPROVED PLAN 3.pdf · uploaded 7 Aug 2023Source
  • DocumentAPPROVED PLAN 4.pdf · uploaded 7 Aug 2023Source
  • DocumentAPPROVED PLAN 5.pdf · uploaded 7 Aug 2023Source

Technical (Architect)

  • DocumentARCHITECT CERTIFICATE (2).pdf · uploaded 30 Jan 2025Source
  • DocumentForm 1.pdf · uploaded 27 Feb 2025Source

Technical (Engineer)

  • DocumentForm -2 _Engineer Certificate.pdf · uploaded 30 Jan 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SURVEY NO. 20/3/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop231 units in all
Address
Survey No. 20/3/1, Ghot, GhotPIN 410208
Village
Ghot, Panvel taluka
Land area for this project
5,000 sq m (53,820 sq ft)
Permissible built-up area
7,161 sq m (77,084 sq ft)
Sanctioned built-up area
7,161 sq m (77,084 sq ft)
Designated bank account
82
Developed in phases
Yes

Survey, CTS, gat or plot numbers

SURVEY NO. 20/3/1

Land as published on MahaRERA's project page

SURVEY NO. 20/3/1

Boundaries

North
Survey No 20 1
South
Survey No 7
East
Survey No 20 2
West
Survey No 17 And 19

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking231 units

10 of 231 units booked (4%), as the promoter reported to MahaRERA

1BHK · 189 units2BHK · 28 unitsShop · 14 units
BuildingTypeCarpet areaUnitsBooked
Building 21BHK31.03 sq m · 334 sq ft280
Building 21BHK35.58 sq m · 383 sq ft210
Building 22BHK48.69 sq m · 524 sq ft140
Building 22BHK53.62 sq m · 577 sq ft140
Building 2Shop16.07 sq m · 173 sq ft20
Building 2Shop17.98 sq m · 194 sq ft40
Building 2Shop18.53 sq m · 199 sq ft20
Building 2Shop19.62 sq m · 211 sq ft20
Show all 13 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Building 2Shop21.8 sq m · 235 sq ft40
Building No 1 A-Wing1BHK34.25 sq m · 369 sq ft2810
Building No 1 B-C-Wing1BHK33.86 sq m · 364 sq ft280
Building No 1 B-C-Wing1BHK34.25 sq m · 369 sq ft280
Building No 1 D-E -Wing1BHK35 sq m · 377 sq ft560

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRajesh Rc Architect—
Chartered accountantEa Patil & Associates—
Chartered accountantRj Phadke & Co—
EngineerCse Consultants—

Source: MahaRERA project page. Contact details are not shown.