Waksai, Pune
Deedo IDDL-PUN-WAKSAI3 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects6
Registrations6
Completion still due15 past their date
Median extension8 months33% of registrations extended
Regulatory cases1on 1 project
10 in 10 registrations run late here
6 MahaRERA registrations in Waksai
1 extended, not yet due5 past even the latest date
Extended registrations moved their completion date by a median of 8 months.
Projects in Waksai
6 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| 7villaDnyandeo Bapu Katkar | 2 yrs 3 mo late | — | 0% |
| Lonavala's Finest Phase2Rahul Hanumant Satav | Due Apr 2027, extended 4 mo | — | — |
| Lonavalas Finest Phase 1Rahul Hanumant Satav | 3 yrs 10 mo late | — | — |
| Pragati GreenwoodsPragati Construction | 8 yrs 9 mo late | — | 33% |
| Mont Vert CrestaMont Vert Constructions | 6 yrs 10 mo late | — | 54% |
| Sapphire GreensShreem Corporation | 8 yrs 4 mo late | — | 68% |
Nearby: other localities in Mawal
Most active promoters
- Rahul Hanumant Satav2 projects
- Dnyandeo Bapu Katkar1 project
- Mont Vert Constructions1 project
- Pragati Construction1 project
- Shreem Corporation1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology