RERA projects in Umbare Navalakh
2 projects under 2 MahaRERA registrations, registered 2017–2026. 50% have a completion date extended beyond the one promised.
2RERA projects
2Registrations
1Completion still due1 past their completion date
30 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 0 |
| 2025 | 0 |
| 2026 | 1 |
Projects in Umbare Navalakh
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| AasthaResolute Buildcon LLP | PM1260002600359 | 7 May 2026 | 30 Dec 2028 | — | Not yet due | 0 |
| Sai ShivamS.r. Developers | P52100012266 | 1 Sep 2017 | 30 Apr 2019 | 30 Oct 2021 | Extended 30 mo | 0 |
Other localities in Mawal
- Talegaon Dabhade (M Cl)199 projects
- Wadagaon (Ct)111 projects
- Talegaon Dabhade (R)96 projects
- Lonavala (M Cl)40 projects
- Kivale39 projects
- Varale38 projects
- Gahunje31 projects
- Somatane25 projects
- Urse12 projects
- Kanhe11 projects
- Chandkhed10 projects
- Jambhul10 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Resolute Buildcon LLP1 project
- S.r. Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology