10 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects3
Registrations3
Completion still due12 past their date
Median extension12 months100% of registrations extended
Regulatory cases0none on MahaRERA's lists
Sudumbare market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

10 in 10 registrations run late here

3 MahaRERA registrations in Sudumbare

1 extended, not yet due2 past even the latest date

Extended registrations moved their completion date by a median of 12 months.

Projects in Sudumbare

3 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
river oaksk.k.m.associates7 yrs 7 mo late—0%
Samarth Leela Heights Phase IShri Balaji GroupDue Oct 2028, extended 4 mo—48%
Sai VishwaSaikrupa Builders And Developers7 yrs 10 mo late—66%

Most active promoters

  1. k.k.m.associates1 project
  2. Saikrupa Builders And Developers1 project
  3. Shri Balaji Group1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology