Skip to content

Sangavi, Pune

Deedo IDDL-PUN-SANGAVI-2

8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects5
Registrations5
Completion still due50 past their date
Median extension4 months80% of registrations extended
Regulatory cases1on 1 project

8 in 10 registrations run late here

5 MahaRERA registrations in Sangavi

1 not yet due4 extended, not yet due

Extended registrations moved their completion date by a median of 4 months.

Projects in Sangavi

5 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Green Aura 2Rajdheera Realty Private LimitedDue Mar 2027——
Green Aura 4Dimple Ganpat SharmaDue Jul 2027, extended 4 mo——
Green Aura 3Pallavi Mohan NaikDue Jul 2027, extended 4 mo——
Green Aura-1Bhagyashree Yuvraj KakadeDue Jul 2027, extended 4 mo——
Pink TopazPink Topaz AopDue Apr 2028, extended 4 mo——
Sangavi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Bhagyashree Yuvraj Kakade1 project
  2. Dimple Ganpat Sharma1 project
  3. Pallavi Mohan Naik1 project
  4. Pink Topaz Aop1 project
  5. Rajdheera Realty Private Limited1 project

Sangavi, in questions

How many projects in Sangavi run late?

8 in 10 MahaRERA registrations (4 of 5): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sangavi by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology