24K Manor
Completion due Jun 2028Pimple Nilakh, Pune 411027 |Promoter: Kolte-Patil Developers Limited
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Jun 2028
P52100052151- Registered
- 24 Jul 2023
- Promised
- 30 Jun 2028
Completion promised for 30 Jun 2028
P52100054048- Registered
- 27 Dec 2023
- Promised
- 30 Jun 2028
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100052151 | 24 Jul 2023 | 30 Jun 2028 | — | Kolte-Patil Developers Limited | Project page |
| P52100054048 | 27 Dec 2023 | 30 Jun 2028 | — | Kolte-Patil Developers Limited | Project page |
Documents
2 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Pimple Nilakh
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.