Company or firm · first RERA registration 2017

Kolte-Patil Developers Limited

Deedo IDDD-Z0TB

Of 21 registrations whose promised date has arrived, 8 kept it (38%). The rest ran a median 4 mo late.

Projects5362 RERA registrations
Kept RERA date38%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time225registered sale deeds
Regulatory cases0none on record

47 registrations of 62 ran past the RERA date

Months late against the original RERA promise, per registration

Show all 62 registrations

62 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
GlitteratiP52100000319Pimpri Chinchawad (M Corp.)Certificate Signed30 Apr 201830 Apr 2018On date
24k OpulaP52100000398Pimpri Chinchawad (M Corp.)Certificate Signed30 Dec 202231 Dec 2025+46 mo*
24k AtriaP52100000428Pimpri Chinchawad (M Corp.)Certificate Signed30 Dec 202130 Dec 2021On date
Ivy Estate Umang PremierP52100000655WagholiCertificate Signed30 Sep 201830 Sep 2018On date
Western AvenueP52100000917WakadCertificate Signed30 Dec 202229 Dec 2023+12 mo
Ivy Estate - Ivy Apartments and Villas and Umang Premiere and Umang PrimoP52100001066WagholiCertificate Signed30 Dec 202229 Dec 2023+46 mo*
Life Republic Sector R1 - 1st AvenueP52100002646MarunjiCertificate Signed30 Dec 202730 Apr 2028+4 mo
Redevelopment of Jai Vijay CHSL - Phase IP51800004446MumbaiCertificate Signed29 Mar 202129 Sep 2022+18 mo
Little Earth Masulkar City Phase 2P52100005032KivaleCertificate Signed30 Dec 202030 Dec 2021+70 mo*
GlitteratiP52100006257Pimpri Chinchawad (M Corp.)Certificate Signed30 Jun 201830 Jun 2018On date
StargazeP52100009722Bavadhan BkCertificate Signed31 Dec 201831 Dec 2018On date
Little Earth Masulkar City Phase 3P52100014875KivaleCertificate Signed30 Jun 202031 Dec 2023+42 mo
Ivy Estate-NiaP52100017955WagholiCertificate Signed30 Dec 202229 Dec 2023+46 mo*
24K StargazeP52100018473Bavadhan BkCertificate Signed30 Mar 202329 Jun 2023+3 mo
EvaraP51800026949BorivaliCertificate Signed30 Oct 202430 Oct 2024On date
24K StargazeP52100027791Bavadhan BkCertificate Signed30 Jun 202430 Jun 2024On date
VerveP51800028783BorivaliCertificate Signed31 Jul 202531 Jul 2025On date
VaayuP51800029034BorivaliCertificate Signed30 Apr 202731 Jan 2025On date
24K StargazeP52100032303Bavadhan BkCertificate Signed31 Dec 202421 Feb 2025+2 mo
Giga PlatinumP52100033371LohgaonCertificate Signed31 Dec 202330 Dec 2024+12 mo
K52P51800047424MumbaiCertificate Signed31 Dec 202531 Dec 2025+10 mo*
Little Earth, Kiwale Building C16P52100047721KivaleCertificate Signed30 Jun 202530 Jun 2025+16 mo*
Little Earth, Kiwale- Building B11P52100047722KivaleCertificate Signed31 Dec 202630 Apr 2027+4 mo
Life Republic Sector R13/13th Avenue/Aros/Phase IP52100047921NereCertificate Signed31 Dec 202630 Apr 2027+4 mo
Life Republic Sector R17A/17A Avenue-Sound of Soul/Phase-IP52100048241JambeCertificate Signed31 Dec 202531 Dec 2025+10 mo*
AloraP51800049048KolekalyanCertificate Signed14 May 202714 Sep 2027+4 mo
Life Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and ShopsP52100050599JambeCertificate Signed30 Mar 202830 Jul 2028+4 mo
24K AlturaP52100051316BanerCertificate Signed31 Mar 202831 Jul 2028+4 mo
45 WestP52100051475BanerCertificate Signed31 Mar 202831 Jul 2028+4 mo
Life Republic Sector R22/22nd Avenue - Atmos/Phase - IP52100051765JambeCertificate Signed31 Oct 202729 Feb 2028+4 mo
Life Republic Sector R31/31st Avenue/24K-EspadaP52100051876JambeCertificate Signed31 Dec 202630 Apr 2027+4 mo
24K ManorP52100052151Pimple NilakhCertificate Signed30 Jun 202830 Oct 2028+4 mo
Aleria - Block BP52100053031HaveliCertificate Signed29 Jun 202729 Jun 2027On date
24K ManorP52100054048Pimple NilakhCertificate Signed30 Oct 202830 Oct 2028On date
24K AlturaP52100054175BanerCertificate Signed31 Mar 202931 Jul 2029+4 mo
Little Earth, Kiwale - Building C14P52100054389KiwaleCertificate Signed30 Jun 202830 Oct 2028+4 mo
Little Earth, Kiwale - Building C13P52100054592KiwaleCertificate Signed30 Jun 202830 Oct 2028+4 mo
Life Republic Sector R22/22nd Avenue - Atmos/Phase-IIP52100056082JambeCertificate Signed31 Dec 202830 Apr 2029+4 mo
Giga Platinum - Tower BP52100056265LohgaonCertificate Signed31 Mar 202831 Jul 2028+4 mo
SpringshireP52100076743WagholiCertificate Signed31 Mar 202831 Jul 2028+4 mo
Life Republic Sector R5 5th Avenue CanvasP52100077008JambeCertificate Signed30 Sep 202930 Jan 2030+4 mo
24K AlturaP52100077098BanerCertificate Signed31 Dec 203030 Apr 2031+4 mo
Little Earth, Kiwale - Building D1P52100078759KiwaleCertificate Signed30 Jun 202930 Oct 2029+4 mo
Little Earth, Kiwale - Buildng D2P52100078800Pune (M Corp.)Certificate Signed30 Jun 202930 Oct 2029+4 mo
24K Manor - Tower C and ShopsP52100079296Pimple NilakhCertificate Signed30 Jun 202930 Oct 2029+4 mo
Life Republic Sector R34 34th Avenue DuetP52100079424JambeCertificate Signed31 Dec 202930 Apr 2030+4 mo
Life Republic Sector R35/35thAvenue Harmony ResidencyP52100079586JambeCertificate Signed31 Dec 202730 Apr 2028+4 mo
Life Republic Sector R17a/17a Avenue-Sound Of Soul/Sound SquareP52100079593JambeCertificate Signed30 Nov 202730 Mar 2028+4 mo
Life Republic Sector R14 14th Avenue QriousP52100079623JambeCertificate Signed30 Apr 203030 Aug 2030+4 mo
Life Republic Sector R34 34th Avenue DuetPM1261012500469JambeCertificate Signed31 Dec 203030 Apr 2031+4 mo
Elixir - Phase IPR1261012500503Kondhwa KhurdCertificate Signed30 Jun 203030 Oct 2030+4 mo
SerenovaPR1180002500850AmbivaliCertificate Signed31 May 202931 May 2029On date
Life Republic Sector R5 5th Avenue CanvasPM1260002501184JambeCertificate Signed31 Dec 203030 Apr 2031+4 mo
Life Republic Sector R14 14th Avenue QriousPM1261012501226JambeCertificate Signed31 Dec 203030 Apr 2031+4 mo
LIFE REPUBLIC SECTOR R31/31st AVENUE – ECHOES/PHASE – 1PM1261012502409JambeCertificate Signed31 Dec 203030 Apr 2031+4 mo
ViverePR1180002502702Pahadi-GoregaonCertificate Signed31 Aug 203031 Dec 2030+4 mo
The Winds Phase-1, Sector 1b At Avian ValleyPR1261012600258BhugaonCertificate Signed30 Jun 203130 Oct 2031+4 mo
Little Earth, Kiwale - Building B7PR1260002600560KiwaleCertificate Signed30 Apr 203130 Aug 2031+4 mo
Vyana Phase-I-T5, T6, T7 at The ReservePM1261012600748Vadgaon-KhurdCertificate Signed30 Dec 203130 Apr 2032+4 mo
Vyana Phase-I-T1 At The ReservePM1261012601645Vadgaon-KhurdCertificate Signed31 Dec 203331 Dec 2033On date
Vyana Phase-I-T2,t3 At The ReservePM1261012601667Vadgaon-KhurdCertificate Signed31 Dec 203231 Dec 2032On date
Vyana Phase-I-T8 At The ReservePR1261012601671Vadgaon-KhurdCertificate Signed31 Dec 203331 Dec 2033On date
Show all 62 registrationsShow fewer
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology