Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100000917

Western Avenue · Wakad, Pune · KoltePatil Developers Limited

Promised for 30 Dec 2022, extended once to 29 Dec 2023 — and that date has passed without the project marked complete on MahaRERA.

3 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2022 to 29 Dec 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 29 Dec 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate9 Sep 2021View
Extension certificate19 Jan 2023View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100000917

Is Western Avenue delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2022, revised to 29 Dec 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100000917. The completion date moved from 30 Dec 2022 to 29 Dec 2023.

Who is the promoter?

MahaRERA records KoltePatil Developers Limited as the promoter of P52100000917.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100000917.

Answers are generated from the record.

Data through3 Nov 2026, 01:37SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology