KoltePatil Developers Limited
Company or firm · 29 projects · 34 MahaRERA registrations
Also appears as KOLTE-PATIL DEVELOPERS LIMITED
29Projects34 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date10 of 20 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 23 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| GlitteratiP52100000319 | Pimpri Chinchawad (M Corp.) | 2017 | Certificate Signed | 30 Apr 2018 | 30 Apr 2018 | On date |
| 24k OpulaP52100000398 | Pimpri Chinchawad (M Corp.) | 2017 | Certificate Signed | 30 Dec 2022 | 31 Dec 2025 | +36 months |
| 24k AtriaP52100000428 | Pimpri Chinchawad (M Corp.) | 2017 | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Ivy Estate Umang PremierP52100000655 | Wagholi | 2017 | Certificate Signed | 30 Sep 2018 | 30 Sep 2018 | On date |
| Western AvenueP52100000917 | Wakad | 2017 | Certificate Signed | 30 Dec 2022 | 29 Dec 2023 | +12 months |
| Ivy Estate - Ivy Apartments and Villas and Umang Premiere and Umang PrimoP52100001066 | Wagholi | 2017 | Certificate Signed | 30 Dec 2022 | 29 Dec 2023 | +12 months |
| Redevelopment of Jai Vijay CHSL - Phase IP51800004446 | Mumbai | 2017 | Certificate Signed | 29 Mar 2021 | 29 Sep 2022 | +18 months |
| GlitteratiP52100006257 | Pimpri Chinchawad (M Corp.) | 2017 | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Redevelopment of Link Palace Premises Co-Op Soc. Ltd. Phase IP51800008272 | Andheri | 2017 | Certificate Signed | 31 Dec 2017 | 31 Mar 2018 | +3 months |
| StargazeP52100009722 | Bavadhan Bk | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Little Earth Masulkar City Phase 3P52100014875 | Kivale | 2018 | Certificate Signed | 30 Jun 2020 | 31 Dec 2023 | +42 months |
| Ivy Estate-NiaP52100017955 | Wagholi | 2018 | Certificate Signed | 30 Dec 2022 | 29 Dec 2023 | +12 months |
| 24K StargazeP52100018473 | Bavadhan Bk | 2018 | Certificate Signed | 30 Mar 2023 | 29 Jun 2023 | +3 months |
| EvaraP51800026949 | Borivali | 2020 | Certificate Signed | 30 Oct 2024 | 30 Oct 2024 | On date |
| 24K StargazeP52100027791 | Bavadhan Bk | 2021 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| VerveP51800028783 | Borivali | 2021 | Certificate Signed | 31 Jul 2025 | 31 Jul 2025 | On date |
| VaayuP51800029034 | Borivali | 2021 | Certificate Signed | 30 Apr 2027 | 31 Jan 2025 | On date |
| 24K StargazeP52100032303 | Bavadhan Bk | 2021 | Certificate Signed | 31 Dec 2024 | 21 Feb 2025 | +2 months |
| Giga PlatinumP52100033371 | Lohgaon | 2022 | Certificate Signed | 31 Dec 2023 | 30 Dec 2024 | +12 months |
| K52P51800047424 | Mumbai | 2022 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Little Earth, Kiwale Building C16P52100047721 | Kivale | 2022 | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | On date |
| Little Earth, Kiwale- Building B11P52100047722 | Kivale | 2022 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| AloraP51800049048 | Kolekalyan | 2023 | Certificate Signed | 14 May 2027 | 14 Sep 2027 | +4 months |
| 24K AlturaP52100051316 | Baner | 2023 | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 months |
| 45 WestP52100051475 | Baner | 2023 | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 months |
| 24K ManorP52100052151 | Pimple Nilakh | 2023 | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 months |
| 24K AlturaP52100054175 | Baner | 2024 | Certificate Signed | 31 Mar 2029 | 31 Jul 2029 | +4 months |
| Little Earth, Kiwale - Building C14P52100054389 | Kiwale | 2024 | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 months |
| Little Earth, Kiwale - Building C13P52100054592 | Kiwale | 2024 | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 months |
| Giga Platinum - Tower BP52100056265 | Lohgaon | 2024 | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 months |
| SpringshireP52100076743 | Wagholi | 2024 | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 months |
| 24K AlturaP52100077098 | Baner | 2024 | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 months |
| Little Earth, Kiwale - Building D1P52100078759 | Kiwale | 2025 | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 months |
| Little Earth, Kiwale - Buildng D2P52100078800 | Pune (M Corp.) | 2025 | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 months |
Show all 34 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 34 registrations
Track record notes
- 10 of 20 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 42 months, for Little Earth Masulkar City Phase 3 (P52100014875).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology