Elixir - Phase I

Certificate Signed

Kondhwa Khurd, Pune 411048 |Promoter: Kolte-Patil Developers Limited

6 Aug 2025Registered with MahaRERA
30 Jun 2030Promised completion
30 Oct 2030Revised completionPushed back 4 months
2Buildings
218Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
—218 units in all
Address
S No 35/1 and S.no. 35/2/3/4 Part, Kondhwa KhurdPIN 411048
Designated bank account
220
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.46951, 73.88898
Elixir - Phase I is at latitude 18.46951, longitude 73.88898.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
6 Aug 2025
Promised
30 Jun 2030
Revised
30 Oct 2030

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR12610125005036 Aug 202530 Jun 203030 Oct 2030Kolte-Patil Developers LimitedProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
Tower 11416110
Tower 21416108

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

218 units registered

— · 218 units
BuildingTypeCarpet areaUnits
Tower 1——110
Tower 2——108

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 32 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardKPDL PAN Card.pdf · uploaded 10 Jul 2025Source
  • OthersDeclaration for not opening bank account -Landowner.pdf · uploaded 30 Jul 2025Source

Legal

  • Declaration Form BTitle - NIBM.pdf · uploaded 8 Jul 2025Source
  • Declaration Form BForm B- Promoter.pdf · uploaded 8 Jul 2025Source
  • OthersDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 30 Jul 2025Source

Migrated

  • Withdrawal Update Form 1Form 1 Elixir.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 1Form 1 Elixir.pdf · uploaded 28 Apr 2026Source
Show all 33 documentsShow fewer documents

Migrated

  • Withdrawal Update Form 1Form 1 Elixir.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 2FORM 2 Elixir.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 2FORM 2 Elixir.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 2FORM 2 Elixir.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 3Signed Form 3 Elixir.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 3Signed Form 3 Elixir.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 3Signed Form 3 Elixir.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 1Form 1 Elixir.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Form 2 Elixir.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3SIGNED FORM 3 ELIXIR-compressed.pdf · uploaded 27 Jul 2026Source
  • Form 5 (FY 2025-2026)Elixir.pdf · uploaded 28 Sep 2026Source

Technical

  • Document2 to 6.pdf · uploaded 8 Jul 2025Source
  • Document7 to 11.pdf · uploaded 8 Jul 2025Source
  • Document12 to 15.pdf · uploaded 8 Jul 2025Source
  • Document1-18 rera plot.pdf · uploaded 10 Jul 2025Source
  • OthersDeclaration plot area.pdf · uploaded 10 Jul 2025Source
  • Othersdeclaration parking.pdf · uploaded 10 Jul 2025Source
  • Document16-18.pdf · uploaded 11 Jul 2025Source
  • DocumentDeclaration-cum-Undertaking- double and multiple project.pdf · uploaded 14 Jul 2025Source
  • DocumentIOD Order NIBM.pdf · uploaded 23 Jul 2025Source
  • DocumentIOD Layout NIBM.pdf · uploaded 23 Jul 2025Source
  • OthersPayment proof.pdf · uploaded 30 Jul 2025Source
  • OthersEmail cc.pdf · uploaded 30 Jul 2025Source

Technical (Architect)

  • DocumentForm 1 Elixir.pdf · uploaded 27 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2 Elixir.pdf · uploaded 27 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In kondhwa khurd, Haveli taluka

Survey, CTS, gat or plot numbers

S No 35/1S.no. 35/2/3/4 part

Boundaries

North
S.No. 36 &33
South
Club House, Open Space 3 & Tower 3
East
Adj.S.no.33 & 34
West
Adj.S.no.36(P)

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVishal Deshpande—
Chartered accountantCA Vidhi S Shah—
EngineerGaurang Joshi—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology