Parandvadi, Pune
8 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects8
Registrations8
Completion still due62 past their date
Median extension4 months75% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Parandvadi
8 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Riverland Ph-3Urbanbrick Developers LLP | P52100054898 | 15 Feb 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Riverland Ph-5Padma-Raj Realtors LLP | P52100054817 | 12 Feb 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Riverland Ph-4Homeway Creations LLP | P52100054427 | 19 Jan 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Urbanbrick Castle Phase 2Urbanbrick Developers LLP | P52100052701 | 22 Sep 2023 | 31 Dec 2028 | 31 Dec 2028 | Not yet due | 0 |
| Riverland Ph 1Urbanbrick Realtors LLP | P52100052111 | 24 Jul 2023 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Riverland Ph 2Terracotta Developers LLP | P52100051744 | 27 Jun 2023 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Urbanbrick CastleUrbanbrick Developers LLP | P52100025688 | 1 Jul 2020 | 30 Dec 2025 | 30 Dec 2025 | Promised date passed | 0 |
| Keshav VatikaUday Infra | P52100007032 | 17 Aug 2017 | 31 Mar 2019 | 30 Dec 2021 | Extended 33 mo | 0 |
Nearby: other localities in Mawal
Most active promoters
- Urbanbrick Developers LLP3 projects
- Homeway Creations LLP1 project
- Padma-Raj Realtors LLP1 project
- Terracotta Developers LLP1 project
- Uday Infra1 project
- Urbanbrick Realtors LLP1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology