RERA projects in Pachane
2 projects under 3 MahaRERA registrations, registered 2023–2026. 33% have a completion date extended beyond the one promised.
2RERA projects
3Registrationssome projects hold several
1Completion still due2 past their completion date
12 monthsMedian extension beyond promised date33% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2023 | 1 |
| 2024 | 1 |
| 2025 | 0 |
| 2026 | 1 |
Projects in Pachane
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Green Meadows Phase -2 AnnexNandan Rainbow Realties LLP | PP1260002600120 | 17 Apr 2026 | 1 Feb 2027 | — | Not yet due | 0 |
| Green MeadowsNandan Rainbow Realties LLP | P52100053712, P52100054816 | 22 Nov 2023 | 30 Jun 2025 | 30 Jun 2026 | Extended 12 mo | 0 |
Other localities in Mawal
- Talegaon Dabhade (M Cl)199 projects
- Wadagaon (Ct)111 projects
- Talegaon Dabhade (R)96 projects
- Lonavala (M Cl)40 projects
- Kivale39 projects
- Varale38 projects
- Gahunje31 projects
- Somatane25 projects
- Urse12 projects
- Kanhe11 projects
- Chandkhed10 projects
- Jambhul10 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Nandan Rainbow Realties LLP2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology