RERA projects in Pachane

2 projects under 3 MahaRERA registrations, registered 2023–2026. 33% have a completion date extended beyond the one promised.

2RERA projects
3Registrationssome projects hold several
1Completion still due2 past their completion date
12 monthsMedian extension beyond promised date33% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20231
20241
20250
20261

Projects in Pachane

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Green Meadows Phase -2 AnnexNandan Rainbow Realties LLPPP126000260012017 Apr 20261 Feb 2027—Not yet due0
Green MeadowsNandan Rainbow Realties LLPP52100053712, P5210005481622 Nov 202330 Jun 202530 Jun 2026Extended 12 mo0

Other localities in Mawal

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Nandan Rainbow Realties LLP2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology