Deedo IDDL-PUN-CHARHOLI9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects171
Registrations183some projects hold several
Completion still due53130 past their date
Median extension4 months34% of registrations extended
Regulatory cases0none on MahaRERA's lists
9 in 10 registrations run late here
183 MahaRERA registrations in Charholi
16 not yet due37 extended, not yet due130 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Charholi
171 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Govinda EnclaveTirupati Tirumala Developers | 3 yrs 11 mo late | — | — |
| Vithai DevelopersVithai Developers | 6 yrs late | — | — |
| Silvana CountyDiamond Properties | Completed, extended 10 mo | — | 24% |
| Sai OrionShashikant Shivaji Bhosle | Completed | — | — |
| 18 JadeA V Contractors | 6 yrs 11 mo late | — | 38% |
| Avani AavasAvani Corp | Completed, extended 6 mo | — | 93% |
| Sairang ClassicSonetra Associates | Completed | — | — |
| Megha Sparkle TowersS D Bhosale Developers | 4 yrs 2 mo late | — | 95% |
| Pranam TowersAmis Constructions LLP | Completed | — | 98% |
| Dnyaneshwari ComplexShree Raghunath Maharaj Developers | Completed | — | — |
| Anand Tarang C BuildingR K Lunkad Builders And Promoters | Completed | — | 100% |
| Alankar F BuildingR K Lunkad Housing Company | Completed | — | 100% |
| Sai WaradSai Ashtavinayak Venture | Completed | — | — |
| Shivpadma ResidencyN B Properties | Completed, extended 2 yrs | — | — |
| Akshay SrushtiRajendra Ramanlal Lunakd | Completed | — | 29% |
| Shree Vitthal AnnexYuvraj Madolappa Chidre | Completed, extended 1 yr 6 mo | — | 50% |
| AarambhShrivardhan reality | 7 yrs 6 mo late | — | — |
| Abhiman ShriRatnadeep Pramoters And Builders | Completed, extended 1 yr | — | 68% |
| Gokuldham ResidencyS K Builders And Developers | Completed | — | 71% |
| Shanti Gopal AvenueYashraj sukesh nashikkar | Completed, extended 7 mo | — | — |
| Spring Valley Phase IIShubh Ganesh Properties | Completed, extended 1 yr 6 mo | — | 100% |
| OmshreeJay Ganesh Developers | Completed | — | 84% |
| Varad Vinayak VrundavanOm Sai Developers | Completed | — | 30% |
| SaiguruSadguru Realty | 8 yrs 1 mo late | — | 78% |
| Santiago SkymontAsha Heritage Developers | Due Dec 2030 | — | 28% |
Nearby: other localities in Haveli
Most active promoters
- Pride Builders Llp9 projects
- D R Gavhane Landmarks Llp6 projects
- Charholi Infrastructure Llp3 projects
- Diamond Nexus Associates3 projects
- Jaikul Associates3 projects
- Sai Tirupati Properties3 projects
- Sam Developers3 projects
- Aakar Realties2 projects
- Avani Corp2 projects
- Chaitanya Buildcon2 projects
Charholi, in questions
How many projects in Charholi run late?
9 in 10 MahaRERA registrations (167 of 183): their completion date was extended or has passed, data through 8 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Charholi by Deedo. Medians on fewer than 3 deeds are not shown.
Data through8 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology