Deedo IDDL-PUN-CHARHOLI9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects171
Registrations183some projects hold several
Completion still due53130 past their date
Median extension4 months34% of registrations extended
Regulatory cases0none on MahaRERA's lists
9 in 10 registrations run late here
183 MahaRERA registrations in Charholi
16 not yet due37 extended, not yet due130 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Charholi
171 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Galaxy ApartmentSharayu Associates | Completed | — | 45% |
| Shree Ganesh GalaxyMukesh Goyal Developers Private Limited | Completed | — | 22% |
| Sai Tirupati Greens Phase- ISai Tirupati Properties | Completed | — | 77% |
| Destination Osiyan Wing AbD R Gavhane Landmarks LLP | Completed | — | 11% |
| Sairang Residency Phase IIPriyanka Santosh Dhobale | Completed | — | 56% |
| Destination AnkurKirti Landmarks | Completed | — | 70% |
| Jay Ganesh ApartmentHemant Arun Upare | Completed, extended 1 yr | — | 53% |
| Siddha SaiDattakrupa Associates | Completed | — | 44% |
| Global HeightsMd Creation | Completed, extended 1 yr 6 mo | — | 28% |
| Sai Tirupati Greens Phase-2Sai Tirupati Properties | Completed | — | 99% |
| Sai Tirupati Greens Phase 3Sai Tirupati Properties | Completed | — | 100% |
| Destination Ankur - A and B BuildingKirtilandmarks | Completed | — | 96% |
| Suvarna NagariMaheshwari Developers | 3 yrs 11 mo late | — | 63% |
| Dreams Carnival-A buildingSam Developers | Completed | — | 100% |
| Tanish PlatinumTanish Associates | Completed | — | 3% |
| The Regent ParkKamdhenu Infrastructure | Completed, extended 1 mo | — | 85% |
| Eco ParkDelight Developers | Completed, extended 2 yrs | — | 60% |
| KingsburyJaikul Associates | Completed | — | 86% |
| SwapnashilpKalaje Associates | Completed, extended 1 yr 5 mo | — | 81% |
| Notting Hill Phase IJaikul Associates | Completed | — | 21% |
| Tanish OrchidTanish Associates | 3 yrs 8 mo late | — | — |
Nearby: other localities in Haveli
Most active promoters
- Pride Builders Llp9 projects
- D R Gavhane Landmarks Llp6 projects
- Charholi Infrastructure Llp3 projects
- Diamond Nexus Associates3 projects
- Jaikul Associates3 projects
- Sai Tirupati Properties3 projects
- Sam Developers3 projects
- Aakar Realties2 projects
- Avani Corp2 projects
- Chaitanya Buildcon2 projects
Charholi, in questions
How many projects in Charholi run late?
9 in 10 MahaRERA registrations (167 of 183): their completion date was extended or has passed, data through 8 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Charholi by Deedo. Medians on fewer than 3 deeds are not shown.
Data through8 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology