Shree Ganesh Galaxy
Completion due Nov 2026Charholi, Pune 412105 |Promoter: Mukesh Goyal Developers Private Limited
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 1
Location
Coordinates as published by MahaRERA
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2018
P52100011096The latest completion date on record passed 7 years and 10 months ago.
- Registered
- 31 Aug 2017
- Promised
- 31 Dec 2018
Completion promised for 30 Nov 2026
P52100023961- Registered
- 14 Jan 2020
- Promised
- 30 Nov 2026
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100011096 | 31 Aug 2017 | 31 Dec 2018 | — | Mukesh Goyal Developers Private Limited | Project page |
| P52100023961 | 14 Jan 2020 | 30 Nov 2026 | — | Mukesh Goyal Developers Private Limited | Project page |
Documents
2 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Charholi
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.
