9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects171
Registrations183some projects hold several
Completion still due53130 past their date
Median extension4 months34% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

183 MahaRERA registrations in Charholi

16 not yet due37 extended, not yet due130 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Charholi

171 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Gatha HeightsOmgatha Builders And Developers Pvt LtdCompleted, extended 9 mo——
Samruddhi PlazaTrimurti Developers4 yrs 2 mo late—92%
Sankalp VastuSankalp Realty3 yrs 7 mo late—94%
Aakar Indigo 2Aakar RealtiesCompleted—93%
Saee ArjunVishal Hariram TapkirCompleted—100%
ShreenagariSharda Sarla Builders1 yr 11 mo late——
Shiv TirthChaitanya Buildcon4 yrs 11 mo late——
Avani NivasAvani Corp.Completed—97%
Destination Osiyan C WingD R Gavhane Landmarks LLPCompleted——
Shrushti HomesSpace CreativeCompleted—95%
Vision SquareUnity Landmarks2 yrs 8 mo late——
YashobhoomiRadheshyam Rameshwardas Agarwal3 yrs 2 mo late——
Anand Tarang A buildingR K Lunkad Builders And PromotersCompleted——
AASARA Crystal HeightsSandeep Shivaji TapkirCompleted, extended 1 yr—33%
Lotus AvenueMauli DevelopersCompleted—99%
Kate EstateArihant PropertiesDue Dec 2026——
Omshree B WingJay Ganesh Developers2 yrs 11 mo late——
Amrutdhara A buildingLunkad Gruh Nirman CompanyCompleted—55%
SingaPuneXrbia Mirth Properties LLPDue Apr 2029, extended 4 mo—32%
Parshwa Gold County Wing BParshwa PropertiesCompleted, extended 1 yr 6 mo—70%
Shree Ganesh HilllviewMukesh Jagdish GoyalCompleted, extended 2 mo—81%
NabhanganSky RealtyCompleted—79%
Alankapuram Ph 3 B and C buildingR K Lunkad Housing corporationCompleted—100%
Nexus GulmoharDiamond Nexus AssociatesCompleted—66%
Mauli ResidencyAtharva Developers2 yrs 11 mo late——
Charholi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Pride Builders Llp9 projects
  2. D R Gavhane Landmarks Llp6 projects
  3. Charholi Infrastructure Llp3 projects
  4. Diamond Nexus Associates3 projects
  5. Jaikul Associates3 projects
  6. Sai Tirupati Properties3 projects
  7. Sam Developers3 projects
  8. Aakar Realties2 projects
  9. Avani Corp2 projects
  10. Chaitanya Buildcon2 projects

Charholi, in questions

How many projects in Charholi run late?

9 in 10 MahaRERA registrations (167 of 183): their completion date was extended or has passed, data through 8 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Charholi by Deedo. Medians on fewer than 3 deeds are not shown.

Data through8 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology