Skip to content

Silvana County

Certificate Signed

Charholi, Pune 412105 |Promoter: Diamond Properties

30 Oct 2018Registered with MahaRERA
31 Dec 2019Promised completion
30 Oct 2020Revised completionPushed back 10 months
1Building
58Units registered14 booked (24%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1 BHK, 2 BHK58 units in all
Address
153/1, Pune Alandi Road, Charoli PhataPIN 412105
Designated bank account
196
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.66323, 73.88745
Silvana County is at latitude 18.66323, longitude 73.88745.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 10 months

The latest completion date on record passed 6 years ago.

Registered
30 Oct 2018
Promised
31 Dec 2019
Revised
30 Oct 2020

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001840330 Oct 201831 Dec 201930 Oct 2020Diamond PropertiesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Silvana County Phase 2758

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

14 of 58 units booked (24%), as the promoter reported to MahaRERA

1 BHK · 20 units2 BHK · 38 units
TypeCarpet areaUnitsBooked
1 BHK35.6 sq m · 383 sq ft40
1 BHK36.92 sq m · 397 sq ft40
1 BHK38.35 sq m · 413 sq ft60
1 BHK39.72 sq m · 428 sq ft62
2 BHK41.41 sq m · 446 sq ft125
2 BHK43.05 sq m · 463 sq ft122
2 BHK44.64 sq m · 481 sq ft84
2 BHK46.76 sq m · 503 sq ft61

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 25 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardDiamond Properties Pan Card 1 mb.pdf · uploaded 24 Oct 2018Source

Legal

  • Declaration Form BForm B Affidavit cum Declaration From Diamond Properties.pdf · uploaded 24 Oct 2018Source
  • Legal Title reportSearch Report 2017-2018.pdf · uploaded 24 Oct 2018Source
  • OtherCOMPLETION CERTIFICATE 1TO 5TH FLOOR.pdf · uploaded 20 Jul 2021Source
  • Otherform_4_Architects_Certificate.pdf · uploaded 20 Jul 2021Source

Migrated

  • 1 PAN CardDiamond Properties Pan Card 1 mb.pdf · uploaded 24 Oct 2018Source
Show all 27 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportSearch Report 2017-2018.pdf · uploaded 24 Oct 2018Source
  • 1 Details of encumbrancesDetail of Encumbarance 1mb.pdf · uploaded 24 Oct 2018Source
  • 1 Copy of Layout Approval (in case of layout)IOD.pdf · uploaded 24 Oct 2018Source
  • 1 Building Plan Approval (IOD)IOD.pdf · uploaded 24 Oct 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommincement Certificate.pdf · uploaded 24 Oct 2018Source
  • 1 Declaration in FORM BForm B Affidavit cum Declaration From Diamond Properties.pdf · uploaded 24 Oct 2018Source
  • 1 Certificates of CA (Form 3)FORM 3.pdf · uploaded 24 Oct 2018Source
  • 1 Proforma of Allotment letterAgreement To Sale And Alotment Letter.pdf · uploaded 25 Oct 2018Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FOMR 5 PHASE II 2018-19.pdf · uploaded 21 Dec 2019Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)SOCIETY CERTIFICATE.pdf · uploaded 23 May 2021Source
  • 1 OtherCOMPLETION CERTIFICATE 1TO 5TH FLOOR.pdf · uploaded 20 Jul 2021Source
  • 2 Otherform_4_Architects_Certificate.pdf · uploaded 20 Jul 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentSILVANA COMPLETION CERTIFICATE.pdf · uploaded 31 Mar 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA Form 1 silvana.pdf · uploaded 4 Apr 2022Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)RERA Form 4 silvana.pdf · uploaded 4 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Diamond Properties.pdf · uploaded 19 Apr 2022Source

Technical

  • DocumentIOD.pdf · uploaded 24 Oct 2018Source
  • DocumentIOD.pdf · uploaded 24 Oct 2018Source

Technical (Architect)

  • DocumentRERA Form 1 silvana.pdf · uploaded 4 Apr 2022Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Charholi, Haveli taluka

Survey, CTS, gat or plot numbers

153/1

Boundaries

North
Property Of Sudam D Rasal
South
Property Of Sampat Tapkir
East
Property Of Shankar Rasal
West
Pune-Alandi Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPravin Ashok Patil—
Registered real estate agentKiran Ramchandra Musale—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology