RERA projects in Umberpada
9 projects under 9 MahaRERA registrations, registered 2018–2025. 67% have a completion date extended beyond the one promised.
Locality
9RERA projects
9Registrations
5Completion still due4 past their completion date
8 monthsMedian extension beyond promised date67% of registrations extended
0Regulatory casesnone on MahaRERA's lists
7Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 1 |
| 2019 | 0 |
| 2020 | 2 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 2 |
| 2024 | 3 |
| 2025 | 1 |
Projects in Umberpada
9 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shree HeightsShree Mangalmurti Realtors | P99000080058 | 22 Apr 2025 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Megastone VedantaChetan Shantaram Patil | P99000077746 | 25 Oct 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Hamida Complex D WingSabari Developers | P99000077588 | 15 Oct 2024 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Narayani Darshan Building No. 5, Type - DShivalik Realtors | P99000056027 | 6 May 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Nivetam ApartmentShree Mangalmurti Enterprises | P99000050551 | 21 Apr 2023 | 30 Jun 2026 | 30 Jun 2026 | Promised date passed | 0 |
| Pride GreensM V Corp | P99000049158 | 1 Feb 2023 | 31 Dec 2024 | 31 Dec 2025 | Extended 12 mo | 0 |
| Virkud PlazaSanjari Builders | P99000025589 | 1 Jul 2020 | 30 Jun 2024 | 30 Jun 2024 | Promised date passed | 0 |
| Shree Niwas 8Pravin Madhukar Raut | P99000024416 | 12 Feb 2020 | 30 Dec 2023 | 30 Dec 2028 | Extended 60 mo | 0 |
| Pride ResidencyM V Corp | P99000019050 | 28 Dec 2018 | 30 Dec 2022 | 30 Dec 2023 | Extended 12 mo | 0 |
Other localities in Palghar
Most active promoters
By projects registered here, as named on MahaRERA.
- M V Corp2 projects
- Chetan Shantaram Patil1 project
- Pravin Madhukar Raut1 project
- Sabari Developers1 project
- Sanjari Builders1 project
- Shivalik Realtors1 project
- Shree Mangalmurti Enterprises1 project
- Shree Mangalmurti Realtors1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology