RERA projects in Kapase
7 projects under 7 MahaRERA registrations, registered 2017–2026. 14% have a completion date extended beyond the one promised.
7RERA projects
7Registrations
7Completion still due0 past their completion date
41 monthsMedian extension beyond promised date14% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 0 |
| 2019 | 1 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 0 |
| 2025 | 3 |
| 2026 | 2 |
Projects in Kapase
7 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Trinity Vista Building No 3Trinity Concrete Structures Private Limited | PR1240002601523 | 12 Aug 2026 | 31 Dec 2031 | — | Not yet due | 0 |
| Royal HeightsTasneem Mufaddal Merchant | PM1240002601493 | 10 Aug 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Ashiyana Building No 9North Star Ashiyana | PR1240002501407 | 7 Nov 2025 | 30 Dec 2028 | — | Not yet due | 0 |
| Elite Residency Building No 1Elite Builders And Developers | P99000080675 | 25 Jun 2025 | 31 Dec 2031 | — | Not yet due | 0 |
| Siddhivinayak ApartmentAnanta Sb Developers | P99000079008 | 31 Jan 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| Mithila ComplexNaval Rambahadur Singh | P99000022165 | 4 Sep 2019 | 31 Dec 2028 | — | Not yet due | 0 |
| Aakash ComplexLxmi Infra | P99000006053 | 14 Aug 2017 | 1 Jul 2023 | 30 Nov 2026 | Extended 40 mo | 0 |
Other localities in Palghar
Most active promoters
By projects registered here, as named on MahaRERA.
- Ananta Sb Developers1 project
- Elite Builders And Developers1 project
- Lxmi Infra1 project
- Naval Rambahadur Singh1 project
- North Star Ashiyana1 project
- Tasneem Mufaddal Merchant1 project
- Trinity Concrete Structures Private Limited1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology