Skip to content

Kapase, Palghar

Deedo IDDL-PAL-KAPASE

4 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects8
Registrations9some projects hold several
Completion still due90 past their date
Median extension4 months44% of registrations extended
Regulatory cases0none on MahaRERA's lists

4 in 10 registrations run late here

9 MahaRERA registrations in Kapase

5 not yet due4 extended, not yet due

Extended registrations moved their completion date by a median of 4 months.

Projects in Kapase

8 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Sadguru AashiyanaVisharia Sadguru Bhoomi LLPDue Dec 2029——
Trinity Vista Building No 3Trinity Concrete Structures Private LimitedDue Dec 2031——
Royal HeightsTasneem Mufaddal MerchantDue Dec 2029——
Ashiyana Building No 9North Star AshiyanaDue Apr 2029, extended 4 mo——
Elite Residency Building No 1Elite Builders And DevelopersDue Apr 2032, extended 4 mo——
All 8 projects →
Kapase market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Ananta Sb Developers1 project
  2. Elite Builders And Developers1 project
  3. Lxmi Infra1 project
  4. Naval Rambahadur Singh1 project
  5. North Star Ashiyana1 project
  6. Tasneem Mufaddal Merchant1 project
  7. Trinity Concrete Structures Private Limited1 project
  8. Visharia Sadguru Bhoomi Llp1 project

Kapase, in questions

How many projects in Kapase run late?

4 in 10 MahaRERA registrations (4 of 9): their completion date was extended or has passed, data through 3 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Kapase by Deedo. Medians on fewer than 3 deeds are not shown.

Data through3 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology