Kagal, Kolhapur
Deedo IDDL-KOL-KAGAL8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects20
Registrations22some projects hold several
Completion still due810 past their date
Median extension4 months61% of registrations extended
Regulatory cases1on 1 project
8 in 10 registrations run late here
22 MahaRERA registrations in Kagal and the places within it
1 not yet due7 extended, not yet due10 past even the latest date4 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Kagal
20 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Sadguru PlazaMadhuri Shrikant Shirale | Due Apr 2029, extended 4 mo | — | — |
| Daffodils ResidencyM S Jadhav HUF | Due Jun 2027, extended 4 mo | — | 4% |
| The LandmarkSwarajya Associates | Due Apr 2027, extended 4 mo | — | 22% |
| Kagal Residency Phase IIIMahesh Namdev Magar | Completed | — | 24% |
| Pearl ResidencyAnnasaheb Adinath Athane | 2 yrs 11 mo late | — | — |
| Construction of 160 EWS 84 LIG and 28 MIG T/s at Gat no 425/2 Part Kagal Dist Kolhapur under PMAYPune Housing and Area Development Board Pune | Due Apr 2029, extended 4 mo | — | — |
| Construction of 176 EWS and 56 LIG t/s at Gat no 425/2 part Kagal, Dist. kolhapur under PMAY schemePune Housing and Area Development Board Pune | Due Apr 2029, extended 4 mo | — | — |
| Construction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist KolhapurPune Housing and Area Development Board Pune | Due Oct 2029, extended 4 mo | — | — |
| Powar ComplexPrakash Tatoba Powar | 5 mo late | — | — |
| Pawanraj ResidencyShree Samarth Infrastructure | 5 mo late | — | — |
| Tej ResidencyVishal Namdev Patil | Completed | — | 21% |
| Royal OrchidSushant Vijay Bhalbar | 3 yrs late | — | — |
| Royal AnnexSushant Vijay Bhalbar | Completed, extended 2 yrs 1 mo | — | 36% |
| Balaji Infra ProjectsBalaji Infra Projects | Completed, extended 1 yr 2 mo | — | 46% |
| Omkar ComplexBalaram Piraji Shingte | Completed | — | 18% |
| Viraj CityBhuyekar Patil Construction Company | Completed, extended 4 mo | — | 28% |
| samarth plaza | No date on record | — | — |
| Vedarjun Vaibhav B | No date on record | — | — |
| Viraj City Building E | No date on record | — | — |
| Viraj City Commercial 3 | No date on record | — | — |
Nearby: other talukas in Kolhapur
Most active promoters
- Pune Housing and Area Development Board Pune3 projects
- Pune Hsg. & Area Devp. Board2 projects
- Sushant Vijay Bhalbar2 projects
- Pune Hsg. & Area Devp. Board1 project
- Annasaheb Adinath Athane1 project
- Balaji Infra Projects1 project
- Balaram Piraji Shingte1 project
- Bhuyekar Patil Construction Company1 project
- Madhuri Shrikant Shirale1 project
- Mahesh Namdev Magar1 project
Kagal, in questions
How many projects in Kagal run late?
8 in 10 MahaRERA registrations (17 of 22): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Kagal by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology